Joseph Zygler v. Hawkins Construction

CourtMissouri Court of Appeals
DecidedSeptember 22, 2020
DocketED108543
StatusPublished

This text of Joseph Zygler v. Hawkins Construction (Joseph Zygler v. Hawkins Construction) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Zygler v. Hawkins Construction, (Mo. Ct. App. 2020).

Opinion

In the Missouri Court of Appeals Eastern District DIVISION FOUR

JOSEPH ZYGLER ) No. ED108543 ) Appellant, ) Appeal from the Circuit Court of ) St. Louis County vs. ) ) Honorable David L. Vincent III HAWKINS CONSTRUCTION, ET AL., ) ) Respondent. ) Filed: September 22, 2020

Introduction

Plaintiff-appellant Joseph Zygler (“Appellant”) appeals the entry of summary judgment on

his negligence claims for defendant-respondents Hawkins Construction & Flat Work Contracting

Co. (“Hawkins”) and Deluca Plumbing, Inc. (“Deluca”) (“Respondents”). Respondents were

subcontracted by general contractor K&S Associates to work on a new government building in

Wildwood, Missouri. Hawkins was hired to perform concrete work and Deluca was hired to

perform plumbing work. Appellant was an employee of St. Charles Acoustics, the flooring

subcontractor on the project. The issue here is a question of law: whether the acceptance doctrine

applies to shield Respondents from liability.

Appellant raises six points on appeal – three points regarding Deluca’s liability and three

regarding Hawkins’ liability. Appellant’s arguments are parallel in Points I and IV, Points II and

V, and Points III and VI. In Points I and IV, Appellant argues summary judgment was improper because Respondents owed a duty of reasonable care to Appellant under a general negligence

theory. Respondents contend they are protected from liability by the acceptance doctrine, an

affirmative defense available to subcontractors under Missouri negligence law. Appellant argues

the acceptance doctrine does not apply. In Points II and V, Appellant argues even if the acceptance

doctrine applies, summary judgment was improper because genuine issues of material fact exist

about whether K&S accepted Respondents’ work before Appellant’s injury. In Points III and VI,

Appellant argues he was a third-party beneficiary of the contracts between K&S and Respondents

and Respondents owed a heightened duty of care to protect Appellant from injury. Finding no

genuine issues of material fact Respondents were entitled to judgment as a matter of law, we

affirm.

Factual and Procedural History1

In 2012, K&S constructed a government building for the City of Wildwood, Missouri.

K&S subcontracted various construction tasks to several subcontractors. Three subcontractors

relate to this appeal. K&S hired subcontractor Hawkins to perform concrete foundation and

flatwork-related tasks on the project, Deluca to perform plumbing work, and St. Charles Acoustics

to perform floor tiling.

This case concerns a workplace injury. On November 14, 2012, Appellant was doing floor

tiling work on the project for St. Charles Acoustics. Around noon, Appellant was walking in an

unlit hallway when his boot caught on a plumbing cleanout that protruded approximately ¾-1 inch

from the concrete floor. Appellant tripped, injuring his ankle. Deluca installed the rough plumbing

including the cleanout. Hawkins poured the concrete floor over the roughed in plumbing and

around the cleanout. The cleanout had no warning signs or markers around it. Appellant says the

1 Because this is an appeal of summary judgment, the facts are set forth in the light most favorable to Appellant’s case.

2 cleanout was difficult to see because it was dirty and similar in color to the surrounding concrete.

Appellant testified that in his experience on other job sites, plumbing cleanouts are sometimes

marked with cones or rings to alert others to the possible tripping hazard.

Respondents claim they finished work on the area where Appellant was injured several

months before the injury. Deluca alleges it finished rough in plumbing work in the hallway where

Appellant was injured by April 27, 2012 and moved on to other finishing projects throughout the

building. Hawkins alleges it finished its concrete work in the interior of the building by May 15,

2012 and performed outdoor work only after that date. Respondents argue K&S reviewed and

accepted the quality and completeness of their work on the hallway several months before

Appellant’s injury. Respondents supported their assertions by submitting proof of payment from

K&S for their work in the hallway, while noting other tasks that were uncompleted had not yet

been paid.2

Appellant sued K&S on March 7, 2016. He then amended his petition to include

Respondents on July 8, 2016. Appellant voluntarily dismissed K&S without prejudice on August

8, 2016. After discovery, Respondents moved for summary judgment on June 14, 2017. The trial

court granted Respondents’ motion on October 27, 2017. This appeal follows.

Standard of Review

The standard of review on summary judgment is essentially de novo. ITT Commercial

Finance Corp. v. Mid-America Marine Supply Corp., 854 S.W.2d 371, 376. When considering

appeals from summary judgment, we review the record in the light most favorable to the party

against whom judgment was entered. Id. (citing Zafft v. Eli Lilly, 676 S.W.2d 241, 244 (Mo. banc

1984)). This Court exercises great care in affirming summary judgment because doing so denies

2 Respondents submitted affidavits signed by K&S president Thomas Kraska that certified Respondents’ work in the hallway was complete and to K&S’s satisfaction by no later than May of 2012.

3 the losing party its day in court. Id. at 377. We accord the nonmoving party the benefit of all

reasonable inferences from the record. Id. at 376 (citing Martin v. City of Washington, 848 S.W.2d

487, 489 (Mo. banc 1993)). We will affirm summary judgment when there is no genuine issue of

material fact and the moving party is entitled to judgment as a matter of law. Germania Bank v.

Thomas, 810 S.W.2d 102, 105 (Mo. App. 1991).

Discussion

Points I-III apply to Appellant’s action against Hawkins and Points IV-VI apply to

Appellant’s action against Deluca. Points I and IV, II and V, and III and VI are parallel arguments.

We will address Appellant’s parallel arguments together.

Points I & IV: Whether the Acceptance Doctrine Applies

In Points I and IV, Appellant argues Respondents negligently caused his injuries because

(1) they owed a duty of care to protect Appellant from injury, (2) they failed to perform their duty,

and (3) their failure was the proximate cause of Appellant’s injury. Appellant also argues the

acceptance doctrine should not shield Respondents from liability here because the doctrine applies

only to cases involving premises liability, not general negligence. Appellant notes the single count

of his amended petition alleged negligence and not premises liability. He argues the acceptance

doctrine is irrelevant to the question of Respondents’ liability.

Respondents argue K&S accepted and paid for their work on the plumbing cleanout six

months before Appellant’s injury. They further argue they had no control over the area at the time

of the injury because they vacated the space to make way for other subcontractors to work,

including Appellant’s employer. Respondents argue the acceptance doctrine is a complete

affirmative defense shielding them from liability.

4 A. The Acceptance Doctrine

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zafft v. Eli Lilly & Co.
676 S.W.2d 241 (Supreme Court of Missouri, 1984)
State Ex Rel. William Ranni Associates, Inc. v. Hartenbach
742 S.W.2d 134 (Supreme Court of Missouri, 1987)
Martin v. City of Washington
848 S.W.2d 487 (Supreme Court of Missouri, 1993)
OFW CORP. v. City of Columbia
893 S.W.2d 876 (Missouri Court of Appeals, 1995)
ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp.
854 S.W.2d 371 (Supreme Court of Missouri, 1993)
Killian v. Wheeloc Engineering Company
350 S.W.2d 759 (Supreme Court of Missouri, 1961)
Singleton v. Charlebois Construction Co.
690 S.W.2d 845 (Missouri Court of Appeals, 1985)
Weber v. McBride & Son Contracting, Co.
182 S.W.3d 643 (Missouri Court of Appeals, 2005)
LeBlanc v. Patton
247 S.W.3d 573 (Missouri Court of Appeals, 2008)
Smith v. Dewitt and Associates, Inc.
279 S.W.3d 220 (Missouri Court of Appeals, 2009)
Daoukas v. City of St. Louis
228 S.W.3d 30 (Missouri Court of Appeals, 2007)
Coleman v. City of Kansas City, Mo.
859 S.W.2d 141 (Missouri Court of Appeals, 1993)
Roskowske v. Iron Mountain Forge Corp.
897 S.W.2d 67 (Missouri Court of Appeals, 1995)
Gruhalla v. George Moeller Construction Co.
391 S.W.2d 585 (Missouri Court of Appeals, 1965)
Clyde Woodall v. Christian Hospital NE-NW
473 S.W.3d 649 (Missouri Court of Appeals, 2015)
Germania Bank v. Thomas
810 S.W.2d 102 (Missouri Court of Appeals, 1991)
Williamson v. Cox
844 S.W.2d 95 (Missouri Court of Appeals, 1992)
Wilson v. Dura-Seal & Stripe, Inc.
519 S.W.3d 479 (Missouri Court of Appeals, 2017)
Casey v. Wrought Iron Bridge Co.
89 S.W. 330 (Missouri Court of Appeals, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
Joseph Zygler v. Hawkins Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-zygler-v-hawkins-construction-moctapp-2020.