Wilson v. Dura-Seal & Stripe, Inc.

519 S.W.3d 479, 2017 WL 1058574, 2017 Mo. App. LEXIS 185
CourtMissouri Court of Appeals
DecidedMarch 21, 2017
DocketED 104570
StatusPublished
Cited by2 cases

This text of 519 S.W.3d 479 (Wilson v. Dura-Seal & Stripe, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. Dura-Seal & Stripe, Inc., 519 S.W.3d 479, 2017 WL 1058574, 2017 Mo. App. LEXIS 185 (Mo. Ct. App. 2017).

Opinion

Gary M. Gaertner, Jr., Judge

Introduction

Appellant Patricia A. Wilson (Wilson) appeals the trial court’s summary judgment in favor of Respondent Dura-Seal and Stripe, Inc. (Dura-Seal) on Wilson’s negligent construction claim. Wilson argues that summary judgment was improper because genuine issues of material fact [481]*481exist regarding whether Dura-Seal was in control of the premises at the time of Wilson’s injury. We affirm.

Background

In March of 2006, the Fox C-6 School District (School District) hired Dura-Seal by oral agreement to construct an asphalt overlay of a drive lane near the auditorium at one of the District’s schools. Dura-Seal performed the work in August of 2006 and then sent an invoice to the School District, which the School District paid in September of 2006.

The parties agree that in paving the drive lane, Dura-Seal did not pave all the way to the curb, but left a “gutter area” between the road and the curb, resulting in the asphalt in the drive lane being taller than the gutter area in between the drive lane and the curb. Wilson offered evidence that the height differential was three to four inches.1 No written specifications for the project were in evidence.

On November 3, 2006, Wilson was attending a school-sponsored function. On her way from the auditorium to the parking lot, Wilson fell when crossing the drive lane, sustaining injuries. She claimed it was the same drive lane paved by Dura-Seal, and that she fell as a result of the height differential between the gutter area and the new asphalt. There was evidence that sometime after this incident, the School District asked Dura-Seal to fill in the gutter area gap along at least part of the drive lane, and Dura-Seal did so. There was also evidence that Dura-Seal offered a one-year guarantee of its work, but no written terms of the guarantee were in evidence.

Wilson filed a premises liability claim against the School District, which in turn added Dura-Seal as a third-party defendant. Wilson then amended her petition to include a claim for negligent construction directly against Dura-Seal. Wilson settled her claim against the School District. Dura-Seal filed a motion for summary judgment on Wilson’s claim against Dura-Seal, and the trial court granted Dura-Seal’s motion. This appeal follows.

Standard of Review

Our review of summary judgment is essentially de novo. ITT Commercial Fin. Corp. v. Mid-Am. Supply Corp., 854 S.W.2d 371, 376 (Mo. banc 1993). We review the record in the light most favorable to the party against whom summary judgment was entered, according the non-mov-ant the benefit of all reasonable inferences from the record. Id. A movant must show that there is no genuine dispute as to any material fact, and that he or she is entitled to judgment as a matter of law. Rule 74.04(c); ITT Commercial Fin. Corp., 854 S.W.2d at 380. A genuine dispute “exists where the record contains competent materials that evidence two plausible, but contradictory, accounts of the essential facts.” ITT Commercial Fin. Corp., 854 S.W.2d at 382.

Discussion

Wilson raises four points on appeal. First, she argues that the trial court erred in granting summary judgment based on the acceptance doctrine because genuine issues of fact remain as to whether Dura-Seal completed the work and whether the School District accepted it. Second, Wilson argues that Dura-Seal’s guarantee operated to extend Dura-Seal’s liability to third parties for the duration of the guarantee, despite any acceptance by the School District. Third, Wilson argues that even if the [482]*482acceptance doctrine applied, it should not defeat Wilson’s claim here because an exception applies. Finally, Wilson argues that we should reject the acceptance doctrine as inconsistent with Missouri’s comparative fault doctrine.

Point I

First, Wilson argues the trial court improperly entered summary judgment because a genuine issue of material fact existed regarding whether Dura-Seal completed the work and whether the School District accepted it. We disagree.

In Missouri, “[a]fter [an] owner accepts a structure, the general rule is that a general contractor is not hable to persons with whom he did not contract.” Gast v. Shell Oil Co., 819 S.W.2d 367, 370 (Mo. banc 1991). “In the absence of formal acceptance, constructive or practical acceptance will suffice.” Roskowske v. Iron Mountain Forge Corp., 897 S.W.2d 67, 71 (Mo. App. E.D. 1995). “Acceptance of the work is attended by the presumption that the owner ... made a reasonably careful inspection of the work, knows of its defects, and so ‘accepts the defects and the negligence that caused them as his own.’ ” Coleman v. City of Kansas City. Mo., 859 S.W.2d 141, 146 (Mo. App. W.D. 1993). Wilson bears the burden of showing that the School District had not accepted Dura-Seal’s work and that Dura-Seal was still in control of or had a right to control the area where Wilson’s injury occurred at the time of the injury. See Roskowske, 897 S.W.2d at 71.

Wilson’s argument in this point is essentially that there is no evidence in the summary judgment record of the School District’s acceptance of Dura-Seal’s work. She notes there is no written acceptance or communication between the parties regarding completion of the work (besides the invoice Dura-Seal sent, which does not specifically say the work was complete), no evidence regarding whether the work met specifications, and no evidence that anyone performed an inspection of Dura-Seal’s work. There was competing testimony from two Dura-Seal employees about whether it was an industry standard to pave all the way to the curb or to leave a gap or gutter area, and Wilson argues that this creates an issue of fact as to whether the job was completed. Wilson argues, moreover, that the fact that Dura-Seal performed additional work to close the gap in the gutter area after Wilson’s injury showed Dura-Seal maintained control over the drive lane.2

However, it is not Dura-Seal’s burden to prove acceptance; it is Wilson’s burden to prove there was no acceptance. It was undisputed that Dura-Seal had not performed any work on the drive lane for at least two months before Wilson’s injury and that the School District had paid Dura-Seal in full for the work. Dura-Seal returned to perform additional work only upon the School District’s request. Here, the undisputed facts establish that the School District had possession and use of the premises, rather than Dura-Seal. See Gruhalla v. George Moeller Constr. Co., 391 S.W.2d 585, 598 (Mo. App. 1965) (plaintiff failed to establish ongoing construction in area where plaintiff was injured; owner had resumed use of disputed area and construction was completed). At such point, whether the initial completed work conformed to industry standards or specifications is not at issue because we presume the owner accepts and takes on [483]*483any negligence in construction.3 See Coleman, 859 S.W.2d at 146.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
519 S.W.3d 479, 2017 WL 1058574, 2017 Mo. App. LEXIS 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-dura-seal-stripe-inc-moctapp-2017.