City of Kimberling City v. Leo Journagan Construction Co.

337 S.W.3d 48, 2011 Mo. App. LEXIS 130, 2011 WL 549499
CourtMissouri Court of Appeals
DecidedFebruary 14, 2011
DocketSD 30611
StatusPublished

This text of 337 S.W.3d 48 (City of Kimberling City v. Leo Journagan Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Kimberling City v. Leo Journagan Construction Co., 337 S.W.3d 48, 2011 Mo. App. LEXIS 130, 2011 WL 549499 (Mo. Ct. App. 2011).

Opinion

NANCY STEFFEN RAHMEYER, Presiding Judge.

City of Kimberling City (“the City”) and Leo Journagan Construction Company, Inc. (“Journagan”) entered into an agreement for the construction of a sanitary sewer system (“Journagan Contract”); the City also entered into a contract with E.T. Archer Corporation (“Archer”) to provide professional engineering services with regard to the system for the City (“Archer Contract”). The City brought suit against Journagan for breach of contract and breach of warranty; Journagan asserted an affirmative defense that the City had waived its claim under the Contract Documents 1 by accepting the work and making final payment to Journagan. The trial court granted summary judgment to Jour-nagan and the City appeals. We find Journagan is not entitled to judgment as a matter of law; we reverse and remand.

Interpretation of the Contract

“The interpretation and construction of a contract are questions of law, which we review de novo and without deference to the trial court’s construction.” Stahlhuth v. SSM Healthcare of St. Louis, 289 S.W.3d 662, 670 (Mo.App. E.D.2009); Monsanto Co. v. Syngenta Seeds, Inc., 226 S.W.3d 227, 230 (Mo.App. E.D.2007). In order to ascertain whether Journagan was entitled to judgment as a matter of law on the Contract Documents, we first set out the relevant provisions. Journagan relies upon paragraph 14.4.:

14.4. Review of Applications for Progress Payment:
[[Image here]]
B. Engineer’s recommendation of any payment requested in an Application for Payment will constitute a representation by Engineer to Owner, based on Engineer’s on-site observations of the Work in progress as an experienced and qualified design professional and on Engineer’s review of the Application for Payment and the accompanying data and schedules that the Work has progressed to the point indicated; that, to the best of Engineer’s knowledge, information and belief, the quality of the Work is in accordance with the Contract Documents ...; and that Contractor is entitled to payment of the amount recommended. However, by recommending any such payment, En *50 gineer will not thereby be deemed to have represented that exhaustive or continuous on-site inspections have been made to check the quality or the quantity of the Work beyond the responsibilities specifically assigned to Engineer in the Contract Documents or that there may not be other matters or issues between the parties that might entitle Contractor to be paid additionally by Owner or Owner to withhold payment to Contractor, or to have represented that any examination has been made to ascertain how or for what purpose Contractor has used or intends to use the monies paid or to be paid to Contractor on account of the Contract Price, or that title to any Work, materials or equipment has passed to Owner free and clear of any Lien.
C. Engineer’s recommendation of final payment will constitute an additional representation by Engineer to Owner that the conditions precedent to Contractor’s being entitled to final payments as set forth in paragraph 14.10.A. have been fulfilled.

(our emphasis added). The City, however, relies upon paragraph 14.9.:

14.9.Contractor’s Continuing Obligation:
A. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. Neither recommendation of any progress or final payment by Engineer, nor the issuance of a certificate of Completion, nor any payment by Owner to Contractor under the Contract Documents, nor any use or occupancy of the Work or any part thereof by Owner, nor any act of acceptance by Owner nor any failure to do so, nor any review and acceptance of a Shop Drawing or sample submission, nor the issuance of a notice of acceptability by Engineer pursuant to paragraph 14.10.A., nor any correction of defective Work by Owner will constitute an acceptance of Work not in accordance with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents (except as provided in paragraph 14.10.A.).
14.10.Waiver of Claims:
A. The making and acceptance of final payment will constitute:
1. A waiver of all claims by Owner against Contractor except claims arising from unsettled Liens, from defective Work appearing after final inspection pursuant to paragraph 14.8.A. or from failure to comply with the Contract Documents or the terms of any special guarantees specified therein; however, it will not constitute a waiver by Owner of any rights in respect of Contractor’s continuing obligations under the Contract Documents; and
2. A waiver of all claims by Contractor against Owner other than those previously made in writing and still unsettled.

(our emphasis added).

Point I

The trial court granted summary judgment on the City’s claim for a breach of contract; it found that Archer was properly authorized as an agent for the City, Archer acted within the scope of its authority and Archer accepted all of Journa-gan’s work, and the City waived any claims for breach of contract when it made final payment to Journagan with full knowledge of the alleged defect. Citing Article 2 of *51 the Journagan Contract, 2 the trial court found that “the City retained Archer ‘to (a) act as the [City’s] representative, and (b) assume all duties and responsibility [sic] of, and have the rights and authority assigned to, the Engineer in the Contract Documents with respect to the completion of the Work in accordance with the Contract Documents.’ ”

The problem with the trial court’s finding is that the Archer Contract, on its face, does not bind the City for the actions of Archer. The trial, court simply listed the duties that were delegated to Archer by the City to administer the Contract Documents. The trial court impermissibly inferred that the rights and duties of Archer correlated into an assignment of authority to bind the City under the Journagan Contract. By them terms, the Contract Documents spell out the duties of Archer, but the City does not give up its rights under the Contract Documents to Archer. 3 The Contract Documents, as specifically cited by the trial court, allowed Archer to give authority for “minor variations in the Work from the requirements of the Contract Documents,” under paragraph 9.5.A. Archer had the “authority to disapprove or reject Work at any time during the completion of the Work, which [Archer] believe[d] to be defective,” under paragraph 9.6.A. Archer was to be the “initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder,” under paragraph 9.9.A. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stahlhuth v. SSM Healthcare of St. Louis
289 S.W.3d 662 (Missouri Court of Appeals, 2009)
Murphy v. Jackson National Life Insurance Co.
83 S.W.3d 663 (Missouri Court of Appeals, 2002)
Reiss & Goodness Engineers, Inc. v. City of Goodman
303 S.W.3d 605 (Missouri Court of Appeals, 2010)
ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp.
854 S.W.2d 371 (Supreme Court of Missouri, 1993)
Barekman v. City of Republic
232 S.W.3d 675 (Missouri Court of Appeals, 2007)
City of Springfield v. Gee
149 S.W.3d 609 (Missouri Court of Appeals, 2004)
Stormer v. Richfield Hospitality Services, Inc.
60 S.W.3d 10 (Missouri Court of Appeals, 2001)
Monsanto Co. v. Syngenta Seeds, Inc.
226 S.W.3d 227 (Missouri Court of Appeals, 2007)
Smith v. Dewitt and Associates, Inc.
279 S.W.3d 220 (Missouri Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
337 S.W.3d 48, 2011 Mo. App. LEXIS 130, 2011 WL 549499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-kimberling-city-v-leo-journagan-construction-co-moctapp-2011.