Reiss & Goodness Engineers, Inc. v. City of Goodman

303 S.W.3d 605, 2010 Mo. App. LEXIS 118, 2010 WL 447902
CourtMissouri Court of Appeals
DecidedFebruary 10, 2010
DocketSD 29600
StatusPublished
Cited by2 cases

This text of 303 S.W.3d 605 (Reiss & Goodness Engineers, Inc. v. City of Goodman) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reiss & Goodness Engineers, Inc. v. City of Goodman, 303 S.W.3d 605, 2010 Mo. App. LEXIS 118, 2010 WL 447902 (Mo. Ct. App. 2010).

Opinion

NANCY STEFFEN RAHMEYER, Judge.

Reiss & Goodness Engineers, Inc. (“Reiss & Goodness”), and Lynnson, Inc. (“Lynnson”), brought a breach of contract action against the City of Goodman, Missouri (“the City”), which filed a counterclaim for breach of contract against Lynn-son and Reiss & Goodness. Following a jury trial, the Circuit Court of McDonald County, Missouri, entered judgments against Reiss & Goodness and Lynnson in the amount of $318,669 each, which Lynn-son now appeals. We affirm.

The facts viewed in the light most favorable to the verdict 1 are as follows. The City retained Reiss & Goodness as the architect and engineer on a project to replace its dilapidated water distribution system, and awarded a contract to Lynnson to complete the project. As architect and engineer, Reiss & Goodness provided the plans and specifications for the project, which called for the installation of new water lines and accoutrements. According to the plans, Lynnson was to install new main lines, service mains, service lines, meter boxes, fire hydrants, and valves for purging the water system. All lines and mains were to be buried at a minimum depth of thirty-six inches, and the meters were to be a minimum of eighteen inches below the tops of the meter boxes, which kept dirt off the meters and provided an insulating air blanket to protect against freeze damage. Any departures from the plans regarding depth of lines and meters were to be in the form of a written change order. An addendum was executed changing the depth of the meter boxes from thirty-six to twenty-four inches; however, the plans still required a thirty-six inch backfill over the mains and the service lines.

Reiss & Goodness was charged with interpreting the intent of plans and overseeing construction. An inspector from Reiss & Goodness, Maurice Clark, was to monitor construction to ensure that it met the specifications and acceptable engineering practice standards. Under the contract, Lynnson was to be “held strictly to the intent of the contract documents in regard to the quality of materials, workmanship, and execution of the work.” From the outset of the project, complaints arose about the quality of workmanship, depths *608 of the mains, lines and meters, and general cleanup. Throughout the construction period, Lynnson submitted monthly pay estimates describing the work performed and materials used, which were then reviewed and approved by Reiss & Goodness and submitted to the City for payment. Of the seventeen pay estimates, all were approved by Reiss & Goodness, and all were paid with the exception of the final payment of $92,757.83, which the City refused despite Reiss & Goodness’s approval and final certification of the project.

Lynnson filed its breach of contract action on October 2, 2006, and the City filed an answer and counterclaim on November 1, 2006, alleging that Lynnson failed to install the water system in accordance with the specifications, failed to install lines and meters to the proper depths, and failed to repair road and yard cuts. At trial, Robert Persons, the president of Lynnson, admitted that the plans called for thirty-six inches of backfill over all lines, that the mains were to connect to the meter setter at a depth of thirty-six inches, that the mains were buried at a depth of twenty-four inches, and that no written field orders regarding depth changes were received. A1 Reiss, the president of Reiss & Goodness, also acknowledged that all pipe was to be buried with thirty-six inches of backfill, that meters were to be buried at eighteen inches below grade, that if the meter depths were shallower than eighteen inches it would indicate that the service mains were buried at shallower than thirty-six inches, that no written change orders regarding depth changes were issued, and that Reiss & Goodness’s obligations under the contract did not relieve Lynnson of its obligation to perform the work in accordance with the plans.

Tom Conrad, an inspector, gas repairman, and general handyman for Reiss & Goodness, testified that he measured the depths of the main lines throughout the town at three separate locations per city block and that all main lines he measured were at a depth of at least thirty-six inches. Chris Morgan, a heavy equipment operator who was subcontracted by Lynn-son to dig trenches in which to lay pipe and who was later retained by the City to dig up some of the lines and determine their depth, testified that Clark monitored his work toward the beginning of the project, but that he was later pushed to lay pipe as quickly as possible, and that upon further examination of the lines and mains, none were buried at the appropriate depth. David Brodie, the City’s superintendent, testified that fire hydrants were installed too high, that one hydrant had been installed in the middle of a residential driveway facing the wrong direction, that ninety percent of Lynnson’s street cuts had sunk and needed repair, that other driveways required repair, that of five hundred meters installed, four hundred and thirty were installed at less than the contract depth, and that several lines were discovered to be too shallow. In addition to Brodie’s testimony, thirty-three photographs were introduced into evidence demonstrating main lines buried at depths varying from fourteen to thirty-two inches.

The City also called Steve Lett, a professional engineer, as an expert witness to testify on the issues of construction, oversight, and damages. Lett testified that, upon review of the work, project plans, photographs, and measurements, the construction had not been done in accordance with the contract documents. Lett also testified regarding damages, the portion of his testimony relevant to this appeal being that concerning the cost of lowering the water mains. Lett was examined outside the presence of the jury, and when asked if he could state to a reasonable degree of engineering certainty that thirty percent of the mains were too shallow, he responded, “[n]o; there may be more than that.” *609 On direct, the City asked Lett whether he believed that the thirty percent figure could be exceeded, to which he answered in the affirmative. When asked if he believed within a reasonable degree of certainty particular in his profession whether the figure was lower than thirty percent, he responded, “[n]o,” and went on to agree that in his professional opinion, thirty percent was the least amount of main line that needed to be replaced. Following objections and further examination, the trial court posited a question as to what the absolute minimum would be within a reasonable degree of professional certainty, leading to the following exchange:

[COUNSEL FOR THE CITY]: Do you have an opinion within a reasonable degree of certainty, particularly in your profession as an engineer, with respect to the minimum amount of ... main lines that need to be replaced?
[LETT]: I believe that the thirty percent that’s contained in my preliminary report is the minimum amount that would need to be replaced, and I can say that with a reasonable amount of certainty.

Following that exchange, the trial court overruled the objections and allowed Lett to repeat his testimony in front of the jury. Lett further testified that the thirty percent was a conservative figure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Kimberling City v. Leo Journagan Construction Co.
337 S.W.3d 48 (Missouri Court of Appeals, 2011)
Rogers v. Hester Ex Rel. Mills
334 S.W.3d 528 (Missouri Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
303 S.W.3d 605, 2010 Mo. App. LEXIS 118, 2010 WL 447902, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reiss-goodness-engineers-inc-v-city-of-goodman-moctapp-2010.