Skinny's, Inc. v. Hicks Brothers Construction Co. of Abilene

602 S.W.2d 85, 30 U.C.C. Rep. Serv. (West) 996, 1980 Tex. App. LEXIS 3512
CourtCourt of Appeals of Texas
DecidedMay 29, 1980
Docket5471
StatusPublished
Cited by12 cases

This text of 602 S.W.2d 85 (Skinny's, Inc. v. Hicks Brothers Construction Co. of Abilene) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skinny's, Inc. v. Hicks Brothers Construction Co. of Abilene, 602 S.W.2d 85, 30 U.C.C. Rep. Serv. (West) 996, 1980 Tex. App. LEXIS 3512 (Tex. Ct. App. 1980).

Opinion

DICKENSON, Justice.

The principal issues are the scope of an oral agreement and the sufficiency of proof as to the amounts due for labor and materials.

The general contractor, Hicks Brothers Construction Company of Abilene, Inc., sued the owner, Skinny’s, Inc., for labor and materials furnished plus “contractor’s fees” equal to 20% of the actual cost of labor and materials. Hicks Brothers also sought foreclosure of eleven Mechanic’s Liens which had been filed in connection with the unpaid, disputed bills. The owner filed a cross-action against the general contractor, and a subcontractor, Binswanger Glass Company, filed a petition in intervention, seeking payment from the general contractor in the sum of $12,546.00 plus attorney fees and also seeking foreclosure on three of the owner’s properties in connection with its Mechanic’s Liens. Following a nonjury trial, judgment was rendered for the general contractor against the owner for the sum of $176,761.71 plus prejudgment interest of $10,054.76 and attorney fees of $24,000.00; the owner was given an offset of $2,893.00 on its cross-action; the subcontractor was awarded judgment against the general contractor for the sum of $12,546.00 plus prejudgment interest of $713.58 and attorney fees of $1,000.00; and judgment was rendered against the owner for foreclosure of all fourteen Mechanic’s Liens. The owner appeals. We affirm.

The trial court made findings of fact which include the following:

* * * * * ⅜:

3. On or about April 11, 1978, at Abilene, Taylor County, Texas, Plaintiff and Defendant entered into an oral contract whereby Plaintiff agreed to furnish labor and materials for the construction of improvements upon properties owned by the Defendant.
4. Defendant agreed that Plaintiff was to be paid for the actual cost of the labor used in, subcontracts arranged for and supervised by Plaintiff, and materials purchased for the construction of said improvements and, in addition thereto, 20% of the amount of that cost for contractor’s services and overhead.
5. On or about May 10, 1978 Plaintiff began to procure and furnish labor, materials, and subcontractors pursuant to the agreement between the parties and continued performing in accordance with the agreement originally made by the parties until on or about August 16, 1978 when the Defendant refused to pay for such services and asked the Plaintiff to discontinue work.
6. Plaintiff periodically delivered statements to the Defendant showing the actual costs incurred by Plaintiff, plus an amount equal to 20% of said actual costs.
*88 7. During the initial period of the performance of the contract, Defendant fully paid the amount shown on the statements so delivered by Plaintiff which included the contractor’s services and overhead to that time. On or about August 16, 1978, the Defendant ceased all payment and has since refused to make any payment as demanded by Plaintiff.
8. The improvements that Plaintiff agreed to construct consisted of small grocery stores, generally known as convenience stores, together with attendant retail gasoline pumping facilities. Additionally, Plaintiff was to construct two storage buildings.
9. For use in the construction contract, Plaintiff purchased twenty prefabricated metal buildings which were designed for the purposes of this contract and which are of substantially less value for any purpose other than that contemplated for this contract. Four of these prefabricated metal buildings were erected on the property owned by Defendant. The other sixteen have not been erected. Fourteen are located on the property of Plaintiff. The two for storage buildings are on the property of Defendant.
10. The total cost incurred by Plaintiff for materials purchased under the contract, and for labor used in constructing the improvements, is $407,533.19. Plaintiff is due under the contract an additional $81,506.64, being 20% of the cost of the labor and materials. Plaintiff has received $312,278.12 in payment from the Defendant. The total amount due and owing Plaintiff under the contract is therefore $176,761.71. This amount is just and reasonable and is now due and owing.
11. The paving done on the location at the job site identified as East Highway 80 is defective and Defendant is entitled to a set-off for the repair of such pavement, said set-off being in the amount of $2,893.00.
* * * * * *

The owner has briefed eleven points of error, contending first that there is no evidence to support the trial court’s finding of an “express contract” for the general contractor to furnish labor and materials for the construction of convenience stores on “numerous properties.” In the alternative the owner contends that this finding is against the great weight of the evidence and is manifestly unjust.

The trial court’s findings of fact have the same force and dignity as a jury verdict; if supported by any competent evidence, they will not be disturbed on appeal unless they are against the great weight of the evidence. See 4 McDonald, Texas Civil Practice § 16.05 (rev.1971). In testing the court’s findings on the complaint that there is no evidence to support them, we will consider only the evidence and inferences which support the findings, disregarding all evidence to the contrary. Brown v. Frontier Theatres, Inc., 369 S.W.2d 299 (Tex.1963). In considering the complaint that these findings are against the great weight of the evidence, we will consider all of the evidence. In re King’s Estate, 244 S.W.2d 660 (Tex.1951).

George Hicks, the general contractor’s president, testified that he visited Joe Davis, the owner’s president, in the early part of 1978 and later submitted a typed proposal to build a 50' X 50' X 12' metal building. The written proposal was not accepted, and Hicks refigured the building, using the dimensions of 40' X 60' X 12'. At this time Hicks said that Davis talked with him about them starting to do the work on a “cost plus 20%” basis. Hicks said there was no change in this arrangement until they quit work. The general contractor worked on seventeen different locations, and it furnished labor and equipment. It also arranged for subcontractors who looked to the general contractor for payment.

Hicks also testified that the first three invoices included the “20% fee for contractor’s services.” One of the invoices was revised by Charley Guernsey, the owner’s treasurer, and he applied the 20% figure to the invoice. The fourth billing was on Au *89 gust 14, 1978. The owner paid the actual costs of this billing (except for one disputed item which was postponed by agreement), but the owner deducted the 20% fee for contractor’s services. Several metal buildings had been charged to the owner at the actual wholesale cost paid by the general contractor, and a dispute developed as to whether the 20% fee should be added to the cost of these buildings. At this point all work ceased.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Truss World, Inc. v. ERJS, INC.
284 S.W.3d 393 (Court of Appeals of Texas, 2009)
Circle Double "C" Enterprises, Inc. v. Wisco Electric, Inc.
782 S.W.2d 299 (Court of Appeals of Texas, 1989)
Evans v. Pollock
793 S.W.2d 14 (Court of Appeals of Texas, 1989)
Gill Sav. Ass'n v. International Supply Co. Inc.
759 S.W.2d 697 (Court of Appeals of Texas, 1988)
BC & S Construction, Inc. v. Action Electric Co.
753 S.W.2d 841 (Court of Appeals of Texas, 1988)
Investors, Inc. v. Hadley
738 S.W.2d 737 (Court of Appeals of Texas, 1987)
Ellebracht v. Ellebracht
735 S.W.2d 658 (Court of Appeals of Texas, 1987)
Nichols v. William A. Taylor, Inc.
662 S.W.2d 396 (Court of Appeals of Texas, 1983)
Jackson v. Lone Star Plywood & Door Corp.
652 S.W.2d 830 (Court of Appeals of Texas, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
602 S.W.2d 85, 30 U.C.C. Rep. Serv. (West) 996, 1980 Tex. App. LEXIS 3512, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skinnys-inc-v-hicks-brothers-construction-co-of-abilene-texapp-1980.