BC & S Construction, Inc. v. Action Electric Co.

753 S.W.2d 841, 1988 Tex. App. LEXIS 1960, 1988 WL 82596
CourtCourt of Appeals of Texas
DecidedJuly 21, 1988
Docket2-87-234-CV
StatusPublished
Cited by5 cases

This text of 753 S.W.2d 841 (BC & S Construction, Inc. v. Action Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BC & S Construction, Inc. v. Action Electric Co., 753 S.W.2d 841, 1988 Tex. App. LEXIS 1960, 1988 WL 82596 (Tex. Ct. App. 1988).

Opinion

OPINION

FARRIS, Justice.

This is an appeal of a summary judgment granted in favor of a subcontractor against a general contractor and its surety under the McGregor Act. See TEX.REV.CIV. STAT.ANN. art. 5160 (Vernon 1987). The subcontractor, Action Electric Company (Action) sued the general contractor, BC & S Construction, Inc. (BC & S) for breach of a subcontract agreement by failing to fully pay sums due and owing for electrical work on a public works project initiated by a previous electrical subcontractor. Lloyd’s, *842 Texas (Lloyd’s) provided the payment bond on the public works project pursuant to the McGregor Act. Action filed a motion for summary judgment, and a partial summary judgment was granted on June 30, 1987. On July 2,1987, trial was held on the issue of the amount of attorney’s fees recoverable by Action. On July 29, 1987, the trial court entered a judgment in which both BC & S and Lloyd’s were found jointly and severally liable to Action in the amount of $22,556.04 plus pre-judgment interest and attorney's fees.

Appellants raise three points on appeal. Their first point contends that Action failed to establish by competent summary judgment evidence the performance of conditions precedent required by the McGregor Act in order to perfect its right to sue and recover from Lloyd’s under the payment bond. Appellants’ second point argues that the affidavits attached to Action’s motion for summary judgment are insufficient because the affiants failed to swear or affirm under oath that all facts stated in the affidavits were true and correct. Finally, appellants argue that Action did not sustain its summary judgment burden by showing that there was no genuine issue as to any material fact and that Action was entitled to any judgment as a matter of law. We overrule all of appellant’s points of error and affirm the judgment of the trial court.

Appellants’ first point, that Action did not provide Lloyd’s with notice as a condition precedent to recovery under the McGregor Act, is without merit. TEX. REV.CIV.STAT.ANN. art. 5160 (Vernon 1987) allows a subcontractor who has furnished labor or material to a public works project to sue the surety for unpaid claims. As a condition precedent to recovery from the surety, the claimant is required to give written notice of the claim by registered mail to the general contractor and the surely. See TEX.REV.CIV.STAT.ANN. art. 5160(B) (Vernon 1987). The summary judgment evidence reveals that notice was sent to BC & S, the City of Arlington, and a company called Aztec Insurance (not a party to the suit). Lloyd’s contends there was no summary judgment evidence showing notice to Lloyd’s or showing that Aztec had any authority to accept notice on behalf of Lloyd’s.

Action alleged in its petition that all relevant conditions precedent to the appellants’ liability had occurred or been performed. Appellants filed only a general denial and did not specifically deny that Action had given the statutory notice. TEX.R.CIV.P. 54 states in pertinent part:

In pleading the performance or occurrence of conditions precedent, it shall be sufficient to aver generally that all conditions precedent have been performed or have occurred. When such performances or occurrences have been so plead, the party so pleading same shall be required to prove only such of them as are specifically denied by the [other] party.

Since Action affirmatively pleaded that all conditions precedent had been met, and since appellants failed to specifically deny such performance, Action was not required to offer proof that proper notification had been given. See Skinny’s, Inc. v. Hicks Bros. Const. Co., 602 S.W.2d 85, 90 (Tex.Civ.App.—Eastland 1980, no writ); Continental Contractors, Inc. v. Thorup, 578 S.W.2d 864, 866 (Tex.Civ.App.—Houston [1st Dist.] 1979, no writ). Appellants’ first point of error is overruled.

Appellants argue in point of error two that the three affidavits, supporting the appellee’s motion for summary judgment, are insufficient in that they fail to swear or affirm under oath that all of the facts stated in the affidavits are true and correct. In support of their argument, appellants rely on two cases: Brown Foundation v. Friendly Chevrolet Co., 715 S.W.2d 115 (Tex.App.—Dallas 1986, writ ref’d n.r.e.) and Dixon v. Mayfield Bldg. Supply Co., Inc., 543 S.W.2d 5 (Tex.Civ.App.—Fort Worth 1976, no writ). We believe that appellants’ reliance is misplaced since both cases are distinguishable from the situation in the instant case. Both the Dixon and Brown cases involved verified answers in suits on sworn accounts. In both cases, the pleadings specifically denied under oath that the debts involved were just and true. The court held that the verifications of *843 these pleadings were not effective because the affiant failed to swear or affirm under oath that the facts stated were true.

We believe that the facts preclude us from following the holdings in these cases. In examining the affidavits, we find they are extremely detailed and specific. Two of the affidavits, one from the president of Action and one from the former president of BC & S, went into great detail as to the reasonableness of the charges for materials and labor involved in the project. Furthermore, both affidavits stated that the various invoices attached as exhibits were true and correct. Both affiants, officers in the companies involved, stated they were personally acquainted with the facts regarding the materials and labor involved in the project. Both signed the affidavits and the verifications of the notary public state that the affidavits were “sworn to and subscribed before me.” Although the affidavits do not specifically recite the matters stated therein are true and correct, we believe this is their obvious effect when considered in their entirety and therefore, they are not fatally defective. See Southwest Park Outpatient Surgery, Ltd. v. Chandler, 572 S.W.2d 51, 52 (Tex.Civ.App.—Houston [1st Dist.] 1978, no writ); Gutierrez v. Hachar 's Department Store, 484 S.W.2d 433, 435 (Tex.Civ.App.—San Antonio 1972, writ ref'd n.r.e.). Appellants’ second point of error is overruled.

Appellants’ third point contends that summary judgment was improper because there existed a genuine issue of fact as to the amount owed by BC & S to Action.

Action’s summary judgment proof contained an affidavit signed by Raymond Balboa. In that affidavit, Balboa stated that he served as BC & S’s president from the time the corporation was organized until September 22, 1986.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Financial Co. v. Delgado
1 S.W.3d 181 (Court of Appeals of Texas, 1999)
Franks v. Brookshire Bros., Inc.
986 S.W.2d 375 (Court of Appeals of Texas, 1999)
Greathouse v. Charter National Bank-Southwest
851 S.W.2d 173 (Texas Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
753 S.W.2d 841, 1988 Tex. App. LEXIS 1960, 1988 WL 82596, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bc-s-construction-inc-v-action-electric-co-texapp-1988.