OPINION
Before BURKE, C. J., RABINOWITZ, CONNOR and MATTHEWS, JJ., and SCHULZ, Judge.
RABINOWITZ, Justice.
This appeal involves a challenge to the validity of a decision made by the Alaska Department of Health and Social Services.
The Department determined that the Lake Otis Hospital project, for which a conditional certificate of need
had previously been issued, had been “substantially implemented.” As a consequence of this decision, the certificate of need will remain in effect indefinitely, until the project is completed or the certificate is revoked.
I.
Background
From April 19, 1972 to July 1, 1977, the Department issued a series of “construction only” licenses to LOC for a hospital to be built in Anchorage, adjacent to the Lake Otis Medical Center. Construction commenced in 1973 but was stalled at the initial ground preparation and foundation stage, mainly due to difficulties LOC encountered in obtaining long term financing.
On July 27,1977, the Department issued LOC a certificate of need for a “125 bed general hospital in Anchorage, Alaska.” By its terms, the certificate would expire in 18 months from the date of issue unless an extension were granted.
The Department subsequently granted LOC two six-month
extensions, the second extending the certificate of need from July 1,1979, to December 31, 1979.
On September 4, 1979, Dr. Michael Beirne, president of LOC, wrote to Department Deputy Commissioner McGinnis suggesting that LOC’s activities on the project, i.e., the signing of construction contracts and the initial construction work, would support a finding of “substantial implementation” thereby avoiding the December 31, 1979, expiration date.
On December 7, 1979, Beirne again requested a decision on “substantial implementation” and submitted a list of documents in support of this request. On December 31, 1979, the Department issued a conditional decision that the project was substantially implemented.
The Department stated that a final decision would be made within 70 days, so that interested parties could be notified and given a chance to submit comments on the decision.
On March 10, 1980, after receiving and reviewing the comments of interested parties including Providence, the Department issued a final determination that the project was substantially implemented. The Department sent letters to Providence and other interested parties informing them of the final decision and of their right to request a hearing under 7 AAC 07.080(b).
Thereafter, Providence submitted a request for a hearing to challenge the “substantial implementation” decision. Providence also filed a notice of appeal and a demand for a trial de novo in the superior court. The Department subsequently filed a motion to dismiss for failure to exhaust administrative remedies and oral argument was set for August 8, 1980. Prior to this hearing the Department notified Providence that its request for an administrative hearing was denied, and filed a supplemental memorandum in support of its motion to dismiss, contending that the proper remedy for Providence was to file an accusation to revoke the LOC certificate under AS 18.07.-081.
Judge Mark Rowland denied the Department’s motion to dismiss and granted Providence’s request for a trial de novo on the validity of the Department’s decision.
Pursuant to court order, Providence then filed an amended complaint joining LOC as an additional defendant. At the conclusion of discovery, LOC moved for summary judgment on the grounds that its grandfathered certificate of need was not subject to any time limits and therefore could not have expired on December 31,1979, regardless whether it was substantially implemented. Providence subsequently filed two motions for summary judgment, the first charging that the Department’s substantial implementation decision was invalid, and the second seeking a declaration that the Department had authority to impose time limits on the certificate of need. It also opposed LOC’s motion on the ground that there were disputed issues of material fact regarding the validity of the grandfathered certificate issued to LOC.
On May 5,1981, the superior court granted summary judgment for LOC, concluding: (1) the LOC certificate of need was properly issued pursuant to the grandfather clause; (2) the LOC certificate was not subject to any time limits; (3) that even if the Department had authority to impose time limits, those limits were lifted by the Department’s substantial implementation decision; and (4) Providence did not have the right to seek judicial review of the Department’s “substantial implementation” decision. Providence’s motion to reconsider was denied, and the superior court subsequently awarded LOC attorney’s fees in the amount of $7,500. This appeal followed.
II.
Does Providence Have The Right to Seek Judicial Review of the Department’s
Decision?
The superior court ruled that Providence did not have the right to obtain review of the Department’s implementation decision. In regard to this ruling, two issues have been raised by the parties: whether Providence’s allegations of injury are sufficient to meet general standing requirements, and whether the Department’s decision is subject to judicial review.
Standing is a judicial rule of self-restraint necessary to assure “the adversity which is fundamental to judicial proceedings.”
Moore v. State,
553 P.2d 8, 23 (Alaska 1976). In order to establish standing, a party must demonstrate that he has or will suffer some “injury in fact” from the contested action or proceeding.
Wagstaff v. Superior Court,
535 P.2d 1220, 1225 (Alaska 1975). As stated, however, in
State v. Lewis,
559 P.2d 630, 634 (Alaska 1977), “this court has liberally construed the judicial limitation of standing and has favored increased accessibility to the courts.”
We have recognized the right of interested third parties to challenge administrative decisions where the party demonstrates a sufficient personal stake in the outcome of the controversy.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
Before BURKE, C. J., RABINOWITZ, CONNOR and MATTHEWS, JJ., and SCHULZ, Judge.
RABINOWITZ, Justice.
This appeal involves a challenge to the validity of a decision made by the Alaska Department of Health and Social Services.
The Department determined that the Lake Otis Hospital project, for which a conditional certificate of need
had previously been issued, had been “substantially implemented.” As a consequence of this decision, the certificate of need will remain in effect indefinitely, until the project is completed or the certificate is revoked.
I.
Background
From April 19, 1972 to July 1, 1977, the Department issued a series of “construction only” licenses to LOC for a hospital to be built in Anchorage, adjacent to the Lake Otis Medical Center. Construction commenced in 1973 but was stalled at the initial ground preparation and foundation stage, mainly due to difficulties LOC encountered in obtaining long term financing.
On July 27,1977, the Department issued LOC a certificate of need for a “125 bed general hospital in Anchorage, Alaska.” By its terms, the certificate would expire in 18 months from the date of issue unless an extension were granted.
The Department subsequently granted LOC two six-month
extensions, the second extending the certificate of need from July 1,1979, to December 31, 1979.
On September 4, 1979, Dr. Michael Beirne, president of LOC, wrote to Department Deputy Commissioner McGinnis suggesting that LOC’s activities on the project, i.e., the signing of construction contracts and the initial construction work, would support a finding of “substantial implementation” thereby avoiding the December 31, 1979, expiration date.
On December 7, 1979, Beirne again requested a decision on “substantial implementation” and submitted a list of documents in support of this request. On December 31, 1979, the Department issued a conditional decision that the project was substantially implemented.
The Department stated that a final decision would be made within 70 days, so that interested parties could be notified and given a chance to submit comments on the decision.
On March 10, 1980, after receiving and reviewing the comments of interested parties including Providence, the Department issued a final determination that the project was substantially implemented. The Department sent letters to Providence and other interested parties informing them of the final decision and of their right to request a hearing under 7 AAC 07.080(b).
Thereafter, Providence submitted a request for a hearing to challenge the “substantial implementation” decision. Providence also filed a notice of appeal and a demand for a trial de novo in the superior court. The Department subsequently filed a motion to dismiss for failure to exhaust administrative remedies and oral argument was set for August 8, 1980. Prior to this hearing the Department notified Providence that its request for an administrative hearing was denied, and filed a supplemental memorandum in support of its motion to dismiss, contending that the proper remedy for Providence was to file an accusation to revoke the LOC certificate under AS 18.07.-081.
Judge Mark Rowland denied the Department’s motion to dismiss and granted Providence’s request for a trial de novo on the validity of the Department’s decision.
Pursuant to court order, Providence then filed an amended complaint joining LOC as an additional defendant. At the conclusion of discovery, LOC moved for summary judgment on the grounds that its grandfathered certificate of need was not subject to any time limits and therefore could not have expired on December 31,1979, regardless whether it was substantially implemented. Providence subsequently filed two motions for summary judgment, the first charging that the Department’s substantial implementation decision was invalid, and the second seeking a declaration that the Department had authority to impose time limits on the certificate of need. It also opposed LOC’s motion on the ground that there were disputed issues of material fact regarding the validity of the grandfathered certificate issued to LOC.
On May 5,1981, the superior court granted summary judgment for LOC, concluding: (1) the LOC certificate of need was properly issued pursuant to the grandfather clause; (2) the LOC certificate was not subject to any time limits; (3) that even if the Department had authority to impose time limits, those limits were lifted by the Department’s substantial implementation decision; and (4) Providence did not have the right to seek judicial review of the Department’s “substantial implementation” decision. Providence’s motion to reconsider was denied, and the superior court subsequently awarded LOC attorney’s fees in the amount of $7,500. This appeal followed.
II.
Does Providence Have The Right to Seek Judicial Review of the Department’s
Decision?
The superior court ruled that Providence did not have the right to obtain review of the Department’s implementation decision. In regard to this ruling, two issues have been raised by the parties: whether Providence’s allegations of injury are sufficient to meet general standing requirements, and whether the Department’s decision is subject to judicial review.
Standing is a judicial rule of self-restraint necessary to assure “the adversity which is fundamental to judicial proceedings.”
Moore v. State,
553 P.2d 8, 23 (Alaska 1976). In order to establish standing, a party must demonstrate that he has or will suffer some “injury in fact” from the contested action or proceeding.
Wagstaff v. Superior Court,
535 P.2d 1220, 1225 (Alaska 1975). As stated, however, in
State v. Lewis,
559 P.2d 630, 634 (Alaska 1977), “this court has liberally construed the judicial limitation of standing and has favored increased accessibility to the courts.”
We have recognized the right of interested third parties to challenge administrative decisions where the party demonstrates a sufficient personal stake in the outcome of the controversy.
Providence alleges it has a personal stake in the Department’s decision because: (1) the proposed LOC hospital would be a direct competitor of, and would have a direct economic impact on, Providence; (2) the continued recognition of the LOC certificate inhibits Providence’s ability to expand its own facilities;
(3) as a competitor
subject to the certificate of need statutes and regulations, Providence has a personal interest in the proper administration of these laws.
LOC’s first argument is that Providence’s allegations of future harm from the hospital project and the outstanding certificate are too speculative. LOC puts forth a series of hypothetical future developments which would eliminate the alleged threat to Providence: (1) the LOC hospital might never be built; (2) the demand for hospitals might increase; (3) the Alaska hospital might be purchased by a native corporation thereby reducing the available beds; or (4) LOC’s certificate might be revoked in a currently pending action challenging LOC’s certificate.
LOC also asserts that Providence’s claims are premature since Providence’s application for a certificate has not yet been considered or denied by the Department.
LOC’s argument that the threat of future injury to Providence is insufficient to create standing is contrary to precedent and logic. Courts have recognized threatened harm as a clear basis for standing.
United States v. Students Challenging Regulatory Agency Procedures,
412 U.S. 669, 93 S.Ct. 2405, 37 L.Ed.2d 254 (1973);
Moore v. State,
553 P.2d 8 (Alaska 1976). Given the time limits for appeal from administrative decisions, the adverse effects of a certificate of need approval will almost always be based on future events.
LOC’s second argument is that Providence should be denied standing since a separate proceeding to revoke LOC’s certificate is currently pending.
While the revocation proceeding may ultimately render this case moot, it does not follow that Providence lacks standing. In
K & L Distributors, Inc. v. Murkowski,
486 P.2d 351, 354 (Alaska 1971), we based our holding regarding standing partially on our conclusion that no one but the plaintiffs were likely to raise the issues involved. Both the revocation proceeding and this action attack the validity of LOC’s certificate, so it is arguable that many of Providence’s objections will be raised in the revocation hearing. LOC has not, however, disputed Providence’s claim that the revocation proceeding will not adjudicate the issue of the procedural and substantive validity of the “substantial implementation” decision.
Based on the foregoing, we conclude that Providence has demonstrated a sufficient personal stake in the outcome of the controversy to assure that the proceedings will be adversarial in nature and therefore that Providence has satisfied the general standing requirements.
This brings us to the second facet of the right to review issue, whether the Department’s “substantial implementation”
decision is subject to judicial review. We hold that the decision is subject to review.
Initially we note that neither the statutes nor the administrative regulations expressly authorize Providence to obtain judicial review of the Department’s “substantial implementation” decision.
LOC argues that Providence’s only remedy is to file an accusation to initiate a proceeding to revoke the LOC certificate. Providence asserts that if a revocation proceeding is its only remedy then the Department’s decision is not subject to any judicial review since the revocation proceeding will attack the current validity of the certificate rather than the procedures and criteria employed by the Department in reaching its decision. Providence argues this limitation on judicial review is inconsistent with Alaska’s preference for increased accessibility to judicial forums.
Moore v. State,
553 P.2d at 23.
In
Alyeska Ski Corp. v. Holdsworth,
426 P.2d 1006, 1011 (Alaska 1967), this court held that the decisions of the Director of the Division of Lands and the Commissioner of Natural Resources in leasing state lands were subject to judicial review despite the absence of any express provision for judicial review. We cited the general rule favoring reviewability stated by Professor Davis:
The presumption of reviewability controls unless it is rebutted by affirmative indication of legislative intent in favor of unreviewability, or by some special reason for unreviewability growing out of the subject matter or the circumstances.
Id.
at 1011 n.16,
quoting
4 K. Davis,
Administrative Law Treatise
§ 28.21 (Supp.1965). This court interpreted the statutory provisions which accorded the right to an administrative appeal as evidence of the legislature’s concern for adherence to legal procedures in the leasing of state lands.
Id.
at 1011. We concluded that the legislature did not manifest a clear intent that this administrative appeal was to be the exclusive remedy available to the aggrieved party.
In this case, we think the administrative remedies provided by AS 18.07.081
(administrative revocation) and AS 18.07.-091(a)
(injunctive relief) similarly demonstrate the legislature’s concern for adherence to proper procedures in the certification of health facilities and conclude that these remedies were not intended to be exclusive.
We conclude that Providence was entitled to seek judicial review of the Department’s substantial implementation decision.
III.
Did the Superior Court Err in Ruling That LOC’s Certificate of Need Is Not Subject to Time Limits?
A.
Is the Department’s Substantial Implementation Decision Invalid Due to its Failure to Adopt Procedural Regulations?
In granting summary judgment the superior court concluded that any time limits which were imposed on LOC’s certificate of need were properly lifted when the Department issued its final determination that the hospital project had been substantially implemented.
Providence claims that under AS 18.07.101 the Department was required to adopt regulations establishing specific procedures for its “substantial implementation” decision.
It argues that the Department’s failure to establish specific procedural guidelines rendered the “substantial implementation” decision invalid, citing
United States Smelting, Refining & Mining Co.
v.
Local Boundary Commission,
489 P.2d 140 (Alaska 1971), and
Mukluk Freight Lines, Inc. v. Nabors Alaska Drilling, Inc.,
516 P.2d 408 (Alaska 1973).
Providence concludes that the Department’s decision was void and without legal effect and that it therefore could not operate to lift the time restrictions on LOC’s certificate.
The Department persuasively argues that AS 18.07.101 does not specifically require procedural regulations governing “substantial implementation” decisions and that therefore the mandatory duty relied on in
Mukluk
and
United States Smelting
is not present in this case. The Department further asserts that it had adopted substantive standards for determining when a project is “substantially” implemented and that a formal hearing was not required.
We think that
Mukluk
and
United States Smelting
are distinguishable from this case. In
United States Smelting,
we stressed the
fact that the agency had failed to establish any substantive standards to guide its discretion in changing local boundary lines. In this case, the Department promulgated regulations specifying the criteria which would govern its implementation decisions. 7 AAC 07.090(e), (f). In
Mukluk,
we noted that the agency’s failure to adopt procedural regulations and its ad hoc adoption of a modified evaluation procedure deprived the appellant of a fair and adequate opportunity to present evidence or to comment on the proposed agency decision.
Mukluk,
516 P.2d at 414. Here, Providence and other interested parties were given the chance to submit evidence and comments regarding the Department’s consideration of LOC’s certificate of need. The Department issued its final determination that the project was substantially implemented after receiving and reviewing the information submitted by Providence and other parties. Providence has not argued that the Department refused to accept or consider this evidence in reaching its final decision.
In light of the foregoing, we hold that the Department’s use of this informal notice and comment procedure was reasonable and that the lack of published procedural regulations did not invalidate its substantial implementation decision.
B.
Were the Department’s Criteria For Determining Substantial Implementation Invalid?
7 AAC 07.090(e) and (f) set out the criteria for determining substantial implementation.
Providence claims that these criteria are invalid because they set too low a standard. Providence argues that under these criteria a finding of substantial implementation could be obtained based on only token activity, a result inconsistent with the goal of the certificate of need program. According to Providence, the automatic expiration provision of the regulations
was intended to encourage continuous progress towards completion of authorized projects and this intent is frustrated by the sections which permit a finding of substantial implementation based on preliminary work, as in this case. The Department acknowledges that 7 AAC 07.090(e) may impose only minimum criteria but asserts that this allows the Department the flexibility it needs to protect the interests of the public as well as of the certificate holders.
After reviewing the challenged regulations and the parties’ arguments we conclude that Providence has not made a sufficient showing to overcome the presumption of validity of the regulations.
Union Oil Co. of California v. State,
574 P.2d 1266 (Alaska 1978). Many of Providence’s objections go to the Department’s application of these criteria rather than to the criteria themselves. In essence, Providence argues that the Department is too lenient in its interpretation of the requirements. Considering the criteria individually, Providence’s position becomes even more tenuous. The first three criteria refer to com
pleted actions, installations, or modifications. The fourth and fifth criteria require the signing of a contract for a portion of the actual construction, excluding site preparation, or the expenditure or obligation of at least twenty percent of the project cost. The satisfaction of any of these criteria would involve more than mere token activity. The final “catch all” criterion refers to similar expenditures or obligations. While this clause may admittedly be subject to broad interpretation we cannot conclude that it is unreasonable on its face.
IV.
Did the Superior Court Err in Holding That This Litigation Did Not Come Within the Public Interest Exception to Civil Rule 82?
The superior court awarded attorney’s fees against Providence in the amount of $7,500. In so doing, the court rejected Providence’s argument that this case came within the public interest litigation exception to Civil Rule 82.
When the litigation encompasses issues of public interest, we have recognized that it would be inappropriate to award Civil Rule 82 attorney’s fees against an unsuccessful plaintiff who has litigated in good faith.
Gilbert v. State,
526 P.2d 1131, 1136 (Alaska 1974).
Three preliminary factors are considered in making the determination whether a case qualifies as public interest litigation. These factors are: (1) the effectuation of strong public policy; (2) the fact that numerous people would benefit from the litigation; and (3) the fact that only a private party could have been expected to bring the action.
Anchorage v. McCabe,
568 P.2d 986, 991 (Alaska 1977). In addition, we have alluded to a fourth criterion and described it as follows:
[T]he fourth criterion may be expressed as whether the litigant claiming public interest status would have had sufficient economic incentive to bring the lawsuit even if it involved only narrow issues lacking general public importance. Such
a litigant is less apt than a party lacking this incentive to be deterred from bringing a good faith claim by the prospect of an adverse award of attorney’s fees.
Our review of the record has persuaded us that the superior court could have concluded that Providence had sufficient private economic reasons to litigate the Department’s “substantial implementation” decision.
Thus, we affirm the superior court’s determination that the case did not come within the public interest exception.
AFFIRMED in part, REVERSED in part, and REMANDED for determination of the substantive validity of the Department’s “substantial implementation” decision.
COMPTON, J., not participating.