Shimer v. Foley, Hoag & Eliot LLP

795 N.E.2d 599, 59 Mass. App. Ct. 302, 2003 Mass. App. LEXIS 972
CourtMassachusetts Appeals Court
DecidedSeptember 16, 2003
DocketNo. 00-P-1088
StatusPublished
Cited by18 cases

This text of 795 N.E.2d 599 (Shimer v. Foley, Hoag & Eliot LLP) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shimer v. Foley, Hoag & Eliot LLP, 795 N.E.2d 599, 59 Mass. App. Ct. 302, 2003 Mass. App. LEXIS 972 (Mass. Ct. App. 2003).

Opinion

Rapoza, J.

This is a legal malpractice case brought by a client, Stephen Shimer, who claims that, but for the negligent advice of his attorneys at Foley, Hoag & Eliot LLP (FHE), he would have settled his underlying dispute with Synthes Ltd. (U.S.A.) (Synthes) and avoided costly litigation. With a jury waiting in the wings, a Superior Court judge granted FHE’s written motion in limine to preclude certain evidence of damages. As a consequence of that ruling, Shimer was unable to prove the essential element of damages as to the two pending counts in his legal malpractice complaint, and the judge dismissed both on FHE’s oral motion.2 At issue in this appeal is the propriety of those rulings.3

1. Background. Shimer, a medical instruments distributor, alleges that he hired FHE to advise him concerning the interpretation of a termination provision in his written contract with Synthes, for which he served as a sales agent in the New England area. Synthes claimed the agreement was due to expire on January 1, 1994, while Shimer asserted that it would automatically renew and continue in effect after that date. According to Shimer, in the course of this dispute, Synthes offered him new, albeit less favorable, contractual terms, which he rejected based on encouraging advice he had received from FHE concerning the viability of his position on the original agreement. In a declaratory judgment action eventually brought by Synthes in [304]*304Federal District Court in Pennsylvania to resolve the underlying contract dispute, summary judgment entered in favor of Synthes, a ruling that was upheld on appeal.4

Subsequently, at the malpractice trial, Shimer’s expert was expected to testify that FHE negligently failed to advise him of the existence of legal precedents adverse to FHE’s interpretation of-the contract between Shimer and Synthes.5 FHE had originally evaluated Shimer’s legal position and concluded that it was “very likely” that Shimer’s agreement with Synthes would be enforced as a self-renewing contract under Pennsylvania law6 and would be terminable only for certain limited reasons not applicable to Shimer’s situation. Nonetheless, FHE told Shimer that further research would be necessary. At a later point, Shimer asked FHE to perform additional research so that he could better evaluate whether to continue defending the Federal litigation initiated by Synthes or to accept that company’s offer of a new contract.

FHE conducted further research that revealed two appellate cases involving facts similar to those in Shimer’s case, neither of which was helpful to his position. Indeed, one of the cases7 actually supported Synthes’s position that its contract with Shimer was not self-renewing and was, in fact, terminable in the circumstances. Shimer was advised of neither the results of FHE’s research nor the existence of precedent supporting the position of Synthes. Instead, Shimer was told that FHE’s additional legal research revealed nothing that changed its original analysis that Shimer’s legal position was sound.

[305]*305Shimer contends that he was denied the opportunity to reassess the strength of his position in light of the new information, which he claims indicated that the issue was less clear than FHE had led him to believe. See Williams v. Ely, 423 Mass. 467, 476 (1996) (certainty of counsel’s opinion unwarranted when underlying issue not conclusively resolved, thus denying plaintiffs the opportunity to evaluate different courses of action). As a result, he was unable to assess the risks associated with further litigation compared to the benefits connected to Synthes’s offer of a new contract. Shimer now asserts that he would have accepted Synthes’s latest contract offer had he known that, in circumstances similar to his, an appellate court had taken a position essentially supporting that of Synthes. In any event, had he accepted the offer, the Federal litigation, in which he claims to have incurred $135,000 in legal expenses, would have been rendered moot.

2. Discussion. The trial judge’s allowance of FHE’s motion in limine to preclude certain evidence of damages ultimately proved fatal to Shimer’s case. In addition to proving that FHE failed to exercise reasonable care and skill in rendering him legal advice, Pongonis v. Saab, 396 Mass. 1005 (1985); Glidden v. Terranova, 12 Mass. App. Ct. 597, 598 (1981), it was Shimer’s obligation to prove that FHE’s negligence was the proximate cause of his reasonably foreseeable damages or loss. Fishman v. Brooks, 396 Mass. 643, 646-647 (1986). See Girardi v. Gabriel, 38 Mass. App. Ct. 553, 558 (1995). Following an exhaustive consideration of Shimer’s proof, the trial judge concluded that Shimer was unable to prove either his damages or their collectibility and dismissed the action without reaching the issue of negligence.

Shimer’s complaint should not have been dismissed. Rather, his proposed evidence should have been admitted to prove not only the terms of the new contract offered by Synthes, but also the damages stemming from his rejection of the offer as well as their collectibility. Independent of the lost opportunity to accept the new contract offered by Synthes, Shimer also claims that he suffered damages in the form of unnecessary legal fees expended [306]*306in litigating the declaratory judgment action.8 Shimer was prepared to prove the amount of legal fees and costs that he paid relative to the Federal suit, a sum that could have been averted, he states, had he been provided the fruits of FFlE’s legal research. We conclude that evidence of such expenditures should not have been excluded by the trial judge, with the consequence being that Shimer’s complaint was improperly dismissed.

a. Evidence concerning the offer of a new contract. For a jury to infer that FHE’s alleged negligence caused him harm, Shimer must prove not only that Synthes offered him a new contract, but also the benefits he would have realized had he accepted the proposal. The measure of his damages would thus be the value of the benefits lost when he rejected the offer based on FHE’s legal analysis of his case. See; e.g., Brady v. Nestor, 398 Mass. 184, 189-190 (1986) (in malpractice case in which plaintiff alleged that attorney’s negligent handling of employment discrimination suit deprived her of a valuable claim for reinstatement, plaintiff’s verdict set aside for failure to prove damages resulting from her rejection of her employer’s reinstatement offer). Moreover, Shimer had to demonstrate that benefits offered by Synthes in its contract offer were actually collectible. See Poly v. Moylan, 423 Mass. 141, 148 (1996), cert. denied, 519 U.S. 1114 (1997) (plaintiff in a legal malpractice action asserting negligence in handling of his claim bears burden of showing that he would have been able to collect something had a judgment been obtained in the underlying case). See also Jernigan v. Giard, 398 Mass. 721, 723-724 (1986).

i. Damages. Shimer’s theory of damages was that, had FHE adequately apprised him of the law, he would have accepted Synthes’s last offer, thereby reaping the financial benefits of the proposed agreement and forgoing the costs of litigation.9 See, e.g., Van Brode Group, Inc. v. Bowditch & Dewey, 36 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Halawi Investment Trust, S.A.L. v. Bacon
Massachusetts Appeals Court, 2024
DELEO v. JONES
D. Maine, 2024
McCrohan v. Sandulli Grace, P.C.
D. Massachusetts, 2019
McCrohan v. Sandulli Grace, P.C.
369 F. Supp. 3d 324 (District of Columbia, 2019)
Degiacomo v. Holland & Knight, LLP
219 F. Supp. 3d 265 (D. Massachusetts, 2016)
RFF Family Partnership, L.P. v. Burns & Levinson, LLP
30 Mass. L. Rptr. 502 (Massachusetts Superior Court, 2012)
Commonwealth v. Purdy
945 N.E.2d 372 (Massachusetts Supreme Judicial Court, 2011)
Palano v. Bellagio Corp.
2009 Mass. App. Div. 125 (Mass. Dist. Ct., App. Div., 2009)
Lennon v. Durcan-Cuddy Insurance Agency
2008 Mass. App. Div. 147 (Mass. Dist. Ct., App. Div., 2008)
Cummings Properties, LLC v. Massachusetts General Physicians Organization
23 Mass. L. Rptr. 205 (Massachusetts Superior Court, 2007)
Farineau v. Easley
2007 Mass. App. Div. 128 (Mass. Dist. Ct., App. Div., 2007)
Guardian Life Insurance Co. of America v. Grant
22 Mass. L. Rptr. 157 (Massachusetts Superior Court, 2007)
Nortek, Inc. v. Liberty Mutual Insurance
843 N.E.2d 706 (Massachusetts Appeals Court, 2006)
Commonwealth v. Vasquez
20 Mass. L. Rptr. 319 (Massachusetts Superior Court, 2005)
Glover v. Glover
92 P.3d 387 (Alaska Supreme Court, 2004)
Coastal Orthopaedic Institute, P.C. v. Bongiorno
807 N.E.2d 187 (Massachusetts Appeals Court, 2004)
Manos v. Merrimac Mutual Fire Insurance
13 Mass. L. Rptr. 638 (Massachusetts Superior Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
795 N.E.2d 599, 59 Mass. App. Ct. 302, 2003 Mass. App. LEXIS 972, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shimer-v-foley-hoag-eliot-llp-massappct-2003.