Salem Building Supply Co. v. J.B.L. Construction Co.

407 N.E.2d 1302, 10 Mass. App. Ct. 360, 1980 Mass. App. LEXIS 1275
CourtMassachusetts Appeals Court
DecidedAugust 4, 1980
StatusPublished
Cited by20 cases

This text of 407 N.E.2d 1302 (Salem Building Supply Co. v. J.B.L. Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salem Building Supply Co. v. J.B.L. Construction Co., 407 N.E.2d 1302, 10 Mass. App. Ct. 360, 1980 Mass. App. LEXIS 1275 (Mass. Ct. App. 1980).

Opinion

Hale, C.J.

The plaintiff in this action was the supplier of dry wall and other materials to W. J. Martinoli, 2 a subcontractor on an apartment complex in Lincoln. The de *361 fendants, J.B.L. Construction Co., Inc. (J.B.L.), the principal contractor, and United Pacific Insurance Company (United Pacific), as surety, executed a labor and material bond for the project. The plaintiff claims the right to recover under the bond for the unpaid balance of its account with Martinoli. Upon the plaintiff’s motion for summary judgment the judge entered judgment for the plaintiff in the amount of $46,881.39. After a later hearing on the plaintiff’s motion for counsel fees, judgment was entered for the plaintiff for an additional $13,200. The defendants appeal from each judgment.

In allowing the plaintiff’s motion for summary judgment, the judge ruled that the bond had been given as security for payment of the plaintiff’s claim under G. L. c. 149, § 29. Section 29, as appearing in St. 1957, c. 682, § 2, sets out bond requirements and procedures for “ [ojfficers or agents contracting in behalf of the commonwealth or in behalf of any county, city, town, district or other political subdivision of the commmonwealth or other public instrumentality for the construction, reconstruction, alteration, remodeling, repair or demolition of public buildings or other public works . . . .” The judge must therefore have concluded that the Lincoln apartment project was public. That conclusion, if correct, would have two consequences in this case. First, the provision of § 29 stating that a judgment in favor of a claimant shall include reasonable legal fees would apply. Second, the notice provisions of § 29 would apply, which, as we explain below, would eliminate the dispute as to whether the plaintiff complied with the notice provisions of the bond itself.

There is no dispute in the parties’ affidavits about the basic character of the Lincoln apartment project. The owner is the Lincoln Homes Corp. (Lincoln), a nonprofit corporation, and the project is financed through the Massachusetts Housing Finance Agency. The dispute is whether a project such as this is a “public building” or other “public work.” We do not view this as an issue of fact but rather as a question of law which can appropriately be decided on summary judgment.

*362 The Massachusetts Housing Finance Agency (MFHA) was established by St. 1966, c. 708, § 3. It is empowered, among other things, to make mortgage loans at favorable rates to qualified developers of housing projects in which at least one-quarter of the tenants will be “low income” and the other tenants will be of moderate income. St. 1966, c. 708, § 4(a), as amended by St. 1974, c. 689, § 1; § 5, as amended by St. 1968, c. 709, § 2, and St. 1970, c. 855, §§ 3, 5; and § 6, as amended by St. 1970, c. 855, § 6. Massachusetts Housing Fin. Agency v. New England Merchants Natl. Bank, 356 Mass. 202, 209 (1969). MHFA is authorized to act only as mortgagee in such a project and is not empowered to develop, own, maintain or control the project unless it is necessary to protect its loan interest. St. 1966, c. 708, § 4(h). Such is not alleged to be the case here. Nothing in this statutory scheme would render a private development financed by MHFA, such as the one at issue here, a public building or public work, or make Lincoln an agent or servant of a public instrumentality, and thus bring the project within the reach of G. L. c. 149, § 29. See V. Petrillo & Son v. American Constr. Co., 148 N.J. Super. 1, 6-7 (1977). Compare Andover Consultants, Inc. v. Lawrence, ante 156, 157-161 (1980). Even the “declaration of public necessity,” St. 1966, c. 708, § 2, makes clear that the statute is designed to encourage private enterprise to build needed housing. The private owner of an MHFA financed project can be a nonprofit corporation, as is Lincoln, or can be a corporation, partnership, or other form of venture organized for profit. St. 1966, c. 708, § 5(h).

Because an MHFA financed housing project does not fall within the general terms of G. L. c. 149, § 29, the Legislature would have had to provide expressly that § 29 apply to such a project. Compare Johnson-Foster Co. v. D’Amore Constr. Co., 314 Mass. 416, 419 (1943) (without express legislative provision [later enacted] G. L. c. 149, § 29, did not apply to housing projects developed by a housing authority). In fact, § 5(a) of St. 1966, c. 708, as originally enacted, did make G. L. c. 149, § 29, applicable “to all construction and *363 alteration projects which are the subject of a mortgage loan by the MHFA.” Section 5(a) was amended, however, by St. 1970, c. 855, § 3, and the reference to G. L. c. 149, § 29, was omitted. Statute 1966, c. 708, § 5(a), as so amended and amended by St. 1971, c. 1030, makes other provisions of G. L. c. 149 applicable to MHFA financed projects but now includes a substitute security provision, requiring a bond or equivalent escrow arrangement “to assure payment out of the construction loan funds for all labor and materials for which claimants would have been able to claim a mechanic’s lien if the claimants had complied with the provisions of chapter two hundred and fifty-four.” We can reach no conclusion other than that the Legislature intended that G. L. c. 149, § 29, no longer apply to a housing project such as the one planned by Lincoln.

As G. L. c. 149, § 29, does not apply, the plaintiff’s motion for counsel fees pursuant to that section was erroneously allowed. No other basis for the award of counsel fees has been suggested. See Donaldson v. Boston Herald-Traveler Corp., 347 Mass. 274, 280-281 (1964); Chartrand v. Riley, 354 Mass. 242, 243-245 (1968); United Tool and Industrial Supply Co. v. Torrisi, 359 Mass. 197, 197-198 (1971); Bournewood Hosp., Inc. v. Massachusetts Comm. Against Discrimination, 371 Mass. 303, 311-313 (1976).

If the bond had been subject to G. L. c. 149, § 29, the notice provisions of that section would have applied, and the plaintiff would have been required to give notice of its claim only to the contractor principal. However, because § 29 did not apply, the plaintiff’s rights under the bond are to be determined by the terms of the bond itself. Under those terms, the plaintiff was required to give notice to two of three named parties: the principal (J.B.L.), the owner (Lincoln) and the surety (United Pacific). '

Included in the record appendix are three affidavits filed by the plaintiff in support of its motion for summary judgment which seek to establish proper notice. In one of them the plaintiff’s attorney states that he sent written notice to J.B.L. and to “Kent Corporation, agent for owner Lincoln *364 Homes Corporation.” In another, Lincoln’s president describes Lincoln’s relationship with Kent Corporation (Kent): “On or about September 16, 1975, the Lincoln Foundation retained Kent... to act as management consultants in connection with Lincoln Woods.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Regional Rehabilitation Associates Management Corp. v. Pilgrim Insurance
2012 Mass. App. Div. 182 (Mass. Dist. Ct., App. Div., 2012)
Brasi Development Corp. v. Attorney General
925 N.E.2d 826 (Massachusetts Supreme Judicial Court, 2010)
C&I Steel, LLC v. Peabody Construction Co.
22 Mass. L. Rptr. 402 (Massachusetts Superior Court, 2007)
James G. Grant Co. v. R.A.D. Steel, Inc.
2003 Mass. App. Div. 164 (Mass. Dist. Ct., App. Div., 2003)
Shimer v. Foley, Hoag & Eliot LLP
795 N.E.2d 599 (Massachusetts Appeals Court, 2003)
Knight v. Commonwealth
709 N.E.2d 436 (Massachusetts Appeals Court, 1999)
Ahepa Charitable Corp. v. Marlborough West Associates Ltd. Partnership
1995 Mass. App. Div. 15 (Mass. Dist. Ct., App. Div., 1995)
Finbow v. Morrill Insurance Agency, Inc.
1994 Mass. App. Div. 212 (Mass. Dist. Ct., App. Div., 1994)
Ashburnham-Westminster Regional School District Committee v. Katter
2 Mass. L. Rptr. 12 (Massachusetts Superior Court, 1994)
David Frankina v. First National Bank of Boston
991 F.2d 786 (First Circuit, 1993)
Dineen v. Roux
1992 Mass. App. Div. 222 (Mass. Dist. Ct., App. Div., 1992)
Helmes v. Commonwealth
550 N.E.2d 872 (Massachusetts Supreme Judicial Court, 1990)
USTrust Co. v. Kennedy
456 N.E.2d 775 (Massachusetts Appeals Court, 1983)
Joseph A. Fortin Construction, Inc. v. Massachusetts Housing Finance Agency
17 Mass. App. Ct. 911 (Massachusetts Appeals Court, 1983)
Sachs v. Hirshom
454 N.E.2d 928 (Massachusetts Appeals Court, 1983)
Davidson Pipe Supply Co., Inc. v. Johnson
440 N.E.2d 1194 (Massachusetts Appeals Court, 1982)
Hardy v. Baran
413 N.E.2d 1138 (Massachusetts Appeals Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
407 N.E.2d 1302, 10 Mass. App. Ct. 360, 1980 Mass. App. LEXIS 1275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salem-building-supply-co-v-jbl-construction-co-massappct-1980.