James G. Grant Co. v. R.A.D. Steel, Inc.

2003 Mass. App. Div. 164, 2003 Mass. App. Div. LEXIS 60
CourtMassachusetts District Court, Appellate Division
DecidedOctober 7, 2003
StatusPublished

This text of 2003 Mass. App. Div. 164 (James G. Grant Co. v. R.A.D. Steel, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James G. Grant Co. v. R.A.D. Steel, Inc., 2003 Mass. App. Div. 164, 2003 Mass. App. Div. LEXIS 60 (Mass. Ct. App. 2003).

Opinion

Wheatley, PJ.

The plaintiff (Grant) files this expedited appeal, under Mass. Dist/Mun. Cts. R. A. D. A., Rule 8A, of two judgments of dismissal as to C & I Steel, Inc. (C&I) and Continental Insurance Company (Continental).1 We affirm the judgment on both motions.2

Fox, the owner, hired Bond, the general contractor, to build a new television studio in Dedham, Massachusetts. Bond, in turn, hired a subcontractor, C&I, to fabricate the steel framework for the building. C&I hired RAD to erect the steel, and RAD, for the purposes of this appeal, hired Grant to provide crane service to lift the framework into place. Continental issued a payment bond for C&I. Grant performed some work, for which demand for payment was made to no avail. In the matters pertinent to this appeal, Grant sued C&I for labor and materials and quantum meruit, and sued Continental on its bond and for a violation of G.L.c. 93A.

The two rulings under consideration here concern, 1. C&I’s motion to dismiss and/or for summary judgment and 2. Continental’s motion to dismiss. Motions to dismiss only address the sufficiency of the complaint. “The plaintiffs claim must be based on facts set forth in the complaint; all materials outside the pleadings are excluded from this review.” Nader v. Citron, 372 Mass. 96, 98 (1977), quoting Conley v. Gibson, 355 U.S. 41, 45-46 (1957). The exception to the limited area of review on a motion to dismiss arises when “matters outside the pleadings are presented to and not excluded by the court....” Mass. R. Civ. R, Rule 12(b) (6), para. 2. On the other hand, with motions for summary judgment, the court may consider matters outside the pleadings, namely, the pleadings, depositions, answers to interrogatories, admissions on file, and affidavits. Mass. R Civ. R, Rule 56(c).

The docket in this case reflects that C&I’s motion to dismiss/and or for summary judgment was heard and allowed on January 31, 2003, and findings were made that referred to affidavits outside the pleadings. The docket further shows that, on February 4, the court heard and allowed Continental’s motion to dismiss, [165]*165with no findings, which we would ordinarily determine was treated as a motion to dismiss. However, a reading of the judge’s findings, dated January 31, clearly show that they apply, not to the ruling on C&I’s motion for summary judgment, heard January 31, but rather to the hearing on Continental’s motion held four days later. Thus, we conclude that the court referred, at the hearing on Continental’s motion, to affidavits outside the pleadings. It appears to be merely an entry error concerning the date. We will, therefore, treat both motions as motions for summary judgment.

C&I’s motion to dismiss and/or for summary judgment.

“Summary judgment shall be upheld when, viewing the evidence in the light most favorable to the nonmoving party, all material facts have been established and the moving party is entitled to a judgment as a matter of law. [Citations omitted] The moving party bears the burden of affirmatively demonstrating the absence of a triable issue, and that the moving party is entitled to judgment as a matter of law.” 1-A Equip. Co. v. Icode, Inc., 2003 Mass. App. Div. 30, 31; Mass. R Civ. P., Rule 56(c).

In its complaint, count III, Grant alleges an implied contract in that C&I hired RAD to erect a steel frame, that C&I knew or should have known that Grant provided crane and trucking services for such work, that C&I controlled the funding for the steel erection and was obligated to assure that Grant was paid, and that C&I was notified that there was an unpaid balance ‘but failed to assure payment.” Elsewhere in the complaint, Grant alleges that RAD “engaged [Grant] to provide crane and trucking services,” and Grant provided them to RAD “from October 16th to November 14, 2001, at agreed charges.” In count V, Grant alleges quantum meruit, and seeks payment for the fair and reasonable value of its services.

Together with its motion to dismiss and for summary judgment, C&I filed an affidavit signed by C&I’s president, John Paulding, Sr. Mr. Paulding states that, from October 12 through December 3, 2001, C&I paid RAD on a weekly basis and each time received a release of lien from RAD stating that all work for which payment was being made had been completed and paid for; that, based on the releases C&I believed that Grant had been paid, that they had never entered into any kind of agreement with Grant and never expected to pay any subcontractor of RAD.

“If the motion for summary judgment is properly supported by affidavits, the adverse party must then respond by affidavits and set forth facts showing that there is a genuine issue for trial.” 1-A Equip. Co., supra; Mass. R. Civ. P., Rule 56(e). Grant made no evidentiary response to C&I’s affidavit and argues that, before the motion was decided, it ought to have been given an opportunity for discovery. Rule 56(f), Mass. R Civ. P., can provide such relief. The court may continue the hearing to allow the party opposing the motion to obtain affidavits, take depositions or do other discovery to support its opposition. However, to obtain a continuance, Grant was required to file a motion supported by an affidavit stating the factual basis and the reasons for its inability to oppose summary judgment J. SMITH & H. ZOBEL, RULES Rracuce, §56.8, Mass. Fractice Series, p. 361. Grant filed neither an affidavit nor a motion, which is fatal. Brick Construction Corp. v. CEI Development, Tetrault v. Mahoney, Hawkes and Goldings, 425 Mass. 456, 458 (1997); 46 Mass. App. Ct. 837, 840 (1999). Therefore, we consider only the documents on record before us.

It is undisputed that there was no express contract between Grant and C&I. As a basis for its claims for labor and materials and quantum meruit, Grant urges us to determine that, because C&I hired Continental to issue a payment bond that includes Grant as a “... claimant who do[es] not have a direct contract with [C&I] ...,” C&I knew that Grant expected to be paid by C&I, if not paid by RAD. The only factual evidence relating to this is C&I’s president’s denial. In fact, the bond terms, in the event of failure by RAD, require Continental to pay Grant, not C&I. Nothing in the record indicates that a reasonable man in the position of C&I’s employees [166]*166should have understood from what they knew that Grant expected payment from them for its services and materials. True v. Lebowich, 243 Mass. 369, 371 (1922). There being no contract by C&I to pay Grant, and no reasonable expectation on the part of either party of payment from C&I to Grant, Grant’s claim under count III fails. See LaChance v. Rigoli, 325 Mass. 425, 427 (1950).

Grant’s assumption that the theory of quantum meruit applies in this case is also flawed. “Recovery in quantum meruit presupposes that no valid contract covers the subject matter of a dispute. Where such a contract exists, the law need not create a quantum meruit right to receive compensation for services rendered.” Boswell v. Zephyr Lines, Inc., 414 Mass. 241, 250 (1993). At the time Grant performed the services, it had a valid contract for payment with RAD.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Boswell v. Zephyr Lines, Inc.
606 N.E.2d 1336 (Massachusetts Supreme Judicial Court, 1993)
General Electric Co. v. Lexington Contracting Corp.
292 N.E.2d 874 (Massachusetts Supreme Judicial Court, 1973)
Salem Building Supply Co. v. J.B.L. Construction Co.
407 N.E.2d 1302 (Massachusetts Appeals Court, 1980)
LaChance v. Rigoli
91 N.E.2d 204 (Massachusetts Supreme Judicial Court, 1950)
Nader v. Citron
360 N.E.2d 870 (Massachusetts Supreme Judicial Court, 1977)
True v. Lebowich
243 Mass. 369 (Massachusetts Supreme Judicial Court, 1923)
Tetrault v. Mahoney
425 Mass. 456 (Massachusetts Supreme Judicial Court, 1997)
Simplex Time Recorder Co. v. Federal Insurance
641 N.E.2d 1358 (Massachusetts Appeals Court, 1994)
Brick Construction Corp. v. CEI Development Corp.
710 N.E.2d 1006 (Massachusetts Appeals Court, 1999)
1-A Equipment Co. v. Icode, Inc.
2003 Mass. App. Div. 30 (Mass. Dist. Ct., App. Div., 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2003 Mass. App. Div. 164, 2003 Mass. App. Div. LEXIS 60, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-g-grant-co-v-rad-steel-inc-massdistctapp-2003.