Sheridan Corp. v. United States

94 Fed. Cl. 663, 2010 WL 3542805
CourtUnited States Court of Federal Claims
DecidedSeptember 13, 2010
DocketNo. 10-547C
StatusPublished
Cited by22 cases

This text of 94 Fed. Cl. 663 (Sheridan Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheridan Corp. v. United States, 94 Fed. Cl. 663, 2010 WL 3542805 (uscfc 2010).

Opinion

OPINION AND ORDER ON PLAINTIFF’S MOTION FOR A PRELIMINARY INJUNCTION

WHEELER, Judge.

In this bid protest, Plaintiff Sheridan Corporation (“Sheridan”) is challenging an agency’s corrective action that would involve the submittal of revised proposals where no apparent reason for such action exists. The United States Property and Fiscal Office of Maine, National Guard Bureau (“the agency”) awarded a contract to Sheridan on May 12, 2010 for the construction of a KC-135 aircraft hangar in Bangor, Maine. The agency made the award to Sheridan on the basis of initial proposals, without conducting any discussions with offerors. The agency evaluated all of the proposals received, and determined that Sheridan’s proposal, considering price and past performance, represented the overall best value to the Government. The agency issued a notice to proceed to Sheridan, and established a contract completion date of August 7, 2012.

Following the award to Sheridan, a competing offeror, JCN Construction Company (“JCN”), filed a protest at the Government Accountability Office (“GAO”) alleging disparate treatment in the evaluation of proposals. Upon the filing of the GAO protest, the agency suspended the performance of Sheridan’s contract. A short time later, the agency decided to take corrective action. The GAO then dismissed JCN’s protest as academic.

Under the proposed corrective action, the agency allowed JCN and another offeror, Nauset Construction Company (“Nauset”), into the “competitive range.” The agency invited Sheridan, JCN, and Nauset to submit revised proposals, which were due on August 13, 2010. Unless enjoined, the agency plans to evaluate the revised proposals and make a new contract award in early September 2010. The Administrative Record contains no explanation for why the agency invited revised proposals in circumstances where none of the agency’s requirements had changed. Moreover, the concept of a “competitive range” under Federal Acquisition Regulation (“FAR”) 15.306(c) has no application where an agency awards a contract without conducting any offeror discussions. The agency has not terminated Sheridan’s contract, but Sheridan’s performance remains suspended pending the agency’s completion of the corrective action.

Sheridan filed suit in this Court on August 12, 2010 requesting declaratory and injunc-tive relief, alleging that the agency’s corrective action is unlawful and lacks a rational basis. The agency disclosed Sheridan’s winning price before requesting revised proposals, and thus has authorized an impermissible auction to occur by allowing two unsuccessful offerors a second chance for the award, knowing the Sheridan price that they must beat. Although revised proposals often are appropriate where an agency has modified its solicitation requirements, or where the agency has engaged in discussions or negotiations before inviting offerors to submit final proposal revisions, the Court cannot see any [666]*666lawful or rational basis for the corrective action here.2

The Court heard argument on Sheridan’s motion for a preliminary injunction on August 31, 2010. At the close of the argument, the Court stated on the record that the preliminary injunction would be issued, and explained orally the reasons supporting the need for this action. See Aug. 31, 2010 Transcript (“Tr.”) 55-59, 61. On September 1, 2010, the Court issued the Preliminary Injunction drafted by Sheridan’s counsel and reviewed by Defendant’s and JCN’s counsel. The Court indicated both at the hearing and in the September 1, 2010 Order that this opinion would follow. The effect of the Preliminary Injunction is to prohibit the agency from proceeding further with its corrective action until the Court issues a final ruling on Plaintiffs motion for permanent injunction and declaratory judgment.

Background,

On December 4, 2009, the agency issued Solicitation No. W912JD-10-R-0001 (“RFP”) for a firm fixed price contract to construct a new 78,000 square foot aircraft maintenance hangar at the Bangor International Airport in Maine. Administrative Record (“AR”) 60-120, 489-90. The RFP stated that the award would be based on a best value determination comprised of two approximately equal factors: past performance and price. AR 78-79. “Past performance” included the review of an offeror’s references in the areas of quality control, timely performance, and management effectiveness as the most significant factors. AR 511. The RFP also indicated that the relevancy of an offeror’s references “may affect an offeror’s overall Past Performance rating.” AR 79-80 (emphasis in original). The RFP included, in pertinent part, the following performance risk ratings:

Very Low Risk: Performance met all contract requirements and exceeded many to the Government’s benefit. Problems, if any, were negligible and were resolved in a timely and highly effective manner. Performance was current and generally very relevant to relevant. Excellent probability of success with overall very low degree of risk in meeting Government’s requirements.
Low Hsk: Performance met contract requirements. Good quality. Minor problems were identified; however, contractor took satisfactory corrective action to resolve where appropriate. Performance was current and generally very relevant to relevant. Good probability of success with overall low degree of risk in meeting the Government’s requirements.
Average Risk: Performance met most contract requirements. Adequate quality. Problems were identified; however, contractor usually took adequate corrective action. OR although performance exceeds expectations and was rated excellent to very good the projects submitted were generally semi-relevant to the efforts required by this solicitation. Fair probability of success with an average degree of risk in meeting the Government’s requirements.

AR 82 (emphasis in original). The agency planned to evaluate “Price” on the basis of total amount proposed, including all options, taking into account price reasonableness and realism. AR 82-83. The RFP stated that the agency intended to evaluate proposals and award a contract without any offeror discussions. AR 78.

Sheridan submitted its initial proposal in response to the RFP on January 28, 2010. AR 313-99. Sheridan’s total proposed price was $14,764,996, which was the second-lowest price submitted. AR 515, 519. Nauset, JCN, and five other offerors also submitted timely proposals. See AR 121-240, 241-312, 511-16. Nauset’s total proposed price of $14,495,625 was the lowest price submitted. JCN’s proposed price of $15,112,974 was the third lowest price. AR 515, 519.

On March 10, 2010, the agency’s Source Selection Evaluation Board (“SSEB”) com[667]*667pleted its evaluation of the eight proposals. AR 489-509, 519. The SSEB assigned Sheridan a past performance rating of “Low Risk”, which was the best rating received by any offeror. AR 492, 496, 498-99. The other seven offerors received lower past performance ratings. Nauset and JCN each received a rating of “Average Risk” in past performance. AR 492, 496.

The agency’s contracting officer received the SSEB’s summary evaluation report, and decided to establish a “competitive range” of offerors who had reasonable pricing and the lowest past performance rating. AR 519. Sheridan was the only offeror in this category. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Novak Birch, Inc. v. United States
132 Fed. Cl. 578 (Federal Claims, 2017)
Progressive Industries, Inc. v. United States
129 Fed. Cl. 457 (Federal Claims, 2016)
Palantir Usg, Inc. v. United States
129 Fed. Cl. 218 (Federal Claims, 2016)
Algese 2 S.C.A.R.L. v. United States
125 Fed. Cl. 431 (Federal Claims, 2016)
Rush Construction, Inc v. United States
117 Fed. Cl. 85 (Federal Claims, 2014)
Palladian Partners, Inc. v. United States
119 Fed. Cl. 417 (Federal Claims, 2014)
Whr Group, Inc. v. United States
115 Fed. Cl. 386 (Federal Claims, 2014)
Fcn, Inc. v. United States
115 Fed. Cl. 335 (Federal Claims, 2014)
Caddell Construction Co., Inc. v. United States
111 Fed. Cl. 49 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
94 Fed. Cl. 663, 2010 WL 3542805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheridan-corp-v-united-states-uscfc-2010.