Shell v. Schollander Companies, Inc.

369 P.3d 1101, 358 Or. 552, 2016 Ore. LEXIS 124
Oregon Supreme Court·Decided February 19, 2016·No. CC 106480CV; CA A150509; SC S062791·Published·Cited by 10 cases

Opinion

*554 KISTLER, J.

The primary question in this construction defect case is which of two statutes of repose applies when a buyer enters into a purchase and sale agreement to buy an existing home. Although each statute provides for a 10-year period of repose, the two periods of repose run from different dates. One runs from “the date of the act or omission complained of.” ORS 12.115(1). The other runs from the date that construction is “substantial [ly] complet[e].” ORS 12.135(l)(b). In this case, the trial court found that plaintiff filed her action more than 10 years after “the date of the act or omission complained of” but less than 10 years after the construction was “substantial [ly] complet[e].” The trial court ruled that the first statute, ORS 12.115(1), applied and accordingly entered judgment in defendant’s favor. The Court of Appeals affirmed. Shell v. Schollander Companies, Inc., 265 Or App 624, 336 P3d 569 (2014). We allowed plaintiffs petition for review and now affirm the Court of Appeals decision and the trial court’s judgment.

Defendant is a general contractor that builds “spec” houses — houses built without preexisting construction contracts in anticipation of eventual sale to the public. 1 Defendant’s president explained that his company ordinarily does not sell homes to the public until the homes have been completed. In particularly strong markets, however, defendant has sold homes that are approximately 95 percent complete. On May 30, 2000, defendant and plaintiff entered into a purchase and sale agreement for a house. Although most of the construction had been completed, the agreement specified that defendant would make changes to the interior of the house. Specifically, defendant agreed to upgrade some of the flooring, install an air conditioning unit, and install a gas dryer in the laundry room. After defendant made those changes and the parties conducted a walk-through inspection, the sale closed on July 12, 2000.

More than 10 years after plaintiff entered into the purchase and sale agreement but less than 10 years after *555 the sale closed, plaintiff filed a complaint against defendant in which she alleged that, as a result of defendant’s negligence, some of the exterior elements of her house — the windows, siding, water resistant barrier, and flashing — were defective. In its answer, defendant alleged, as an affirmative defense, that the statute of repose set out in ORS 12.115(1) barred plaintiffs negligence claims. 2 Defendant also filed a motion for summary judgment in which it submitted evidence that all the acts or omissions that gave rise to plaintiffs specifications of negligence occurred before plaintiff signed the purchase and sale agreement on May 30, 2000, and thus more than 10 years before she filed her complaint. It followed, defendant reasoned, that the 10-year statute of repose in ORS 12.115(1) barred plaintiffs negligence claims.

Plaintiff responded that defendant was relying on the wrong statute of repose. In her view, ORS 12.135(l)(b) applied and gave her 10 years from the date of “substantial completion * * * of construction” in which to bring her action. Plaintiff reasoned that, because a reasonable juror could find that the construction of her house was not substantially complete until the sale closed on July 12, 2000, her complaint came within the 10-year period of repose set out in ORS 12.135(l)(b) and thus was timely.

After considering the parties’ argument, the trial court ruled that ORS 12.135(1) applies to claims arising from contracts to construct, alter, or repair homes. The trial court concluded that, because plaintiffs claims did not arise out of a contract to construct a home, ORS 12.135(1) did not apply. 3 It ruled instead that ORS 12.115(1) applied. The court also concluded that, because the alleged “acts or omissions” that gave rise to plaintiffs negligence claims occurred before plaintiff entered into the purchase and sale agreement (and thus more than 10 years before she filed her *556 action), defendant was entitled to summary judgment. The trial court entered judgment accordingly. 4

The Court of Appeals affirmed. It reasoned that the 10-year period of repose set out in ORS 12.135(l)(b) runs from the date of “substantial completion” of construction. Because the date of “substantial completion” is defined as the date that the “contractee” accepts the construction as complete, the Court of Appeals adhered to its decisions holding that ORS 12.135(1) applies only to claims that “derive from a contractor-contractee relationship.” See Shell, 265 Or App at 632 (following Lozano v. Schlesinger, 191 Or App 400, 84 P3d 816 (2004)). Because plaintiffs construction defect claims did not derive from such a relationship, the court agreed with the trial court that ORS 12.135(1) was inapplicable. It also agreed that ORS 12.115(1) applied and that the alleged acts or omissions that gave rise to plaintiffs negligence claims occurred more than 10 years before plaintiff filed her complaint. Id. at 633-34. It accordingly affirmed the trial court’s judgment.

We allowed plaintiffs petition for review to consider which of the two statutes of repose applies. On that issue, plaintiff does not argue that ORS 12.115(1) is, by its terms, inapplicable. Rather, she argues that ORS 12.135(1) is the more specific statute and, for that reason, controls. We agree with plaintiffs implicit recognition that ORS 12.115

Free access — add to your briefcase to read the full text and ask questions with AI

Shell v. Schollander Companies, Inc., 369 P.3d 1101, 358 Or. 552, 2016 Ore. LEXIS 124 (Or. 2016).

369 P.3d 1101 (Shell v. Schollander Companies, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Marshall v. PricewaterhouseCoopers, LLP
505 P.3d 40 (Court of Appeals of Oregon, 2021)
Slatten v. R&B Builders, Inc.
Court of Appeals of Kansas, 2021
State v. Squires
2019 UT App 113 (Court of Appeals of Utah, 2019)
Brockway v. Allstate Property & Casualty Insurance Co.
391 P.3d 871 (Court of Appeals of Oregon, 2017)
Wyers v. American Medical Response Northwest, Inc.
377 P.3d 570 (Oregon Supreme Court, 2016)
Goodwin v. Kingsmen Plastering, Inc.
375 P.3d 463 (Oregon Supreme Court, 2016)
Shell v. Schollander Companies, Inc.
Oregon Supreme Court, 2016