PIH Beaverton, LLC v. Super One, Inc.

323 P.3d 961, 355 Or. 267
CourtOregon Supreme Court
DecidedApril 24, 2014
DocketCC C072107CV; CA A142268, A142301; SC S061488, S061505
StatusPublished
Cited by9 cases

This text of 323 P.3d 961 (PIH Beaverton, LLC v. Super One, Inc.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PIH Beaverton, LLC v. Super One, Inc., 323 P.3d 961, 355 Or. 267 (Or. 2014).

Opinion

*272 WALTERS, J.

In this case, we consider the meaning of the term “substantial completion” as used in ORS 12.135, a statute of ultimate repose for claims arising from the construction, alteration, or repair of improvements to real property. We affirm the decision of the Court of Appeals and remand to the circuit court for further proceedings.

The following facts are taken from the record on summary judgment and are undisputed. Defendant general contractor Super One, Inc., and various subcontractors, including defendant subcontractor T. T. & L. Sheet Metal, Inc., contracted with VIP’s Industries, Inc. and VIP’s Motor Inns, Inc. (VIP’s) to build a hotel. 1 Defendant general contractor and VIP’s used a standard form contract supplied by the American Institute of Architects (AIA). Defendants began work in 1996. On February 13, 1997, VIP’s posted a “completion notice” pursuant to ORS 87.045, a statute governing construction liens. 2 On or about that same date, VIP’s also obtained a certificate for temporary occupancy and began accepting paying guests. However, a Certificate of Substantial Completion was not issued by the architect or accepted by VIP’s as had been contemplated by the contract between the parties. After the date on which VIP’s posted the completion notice, defendants continued to perform construction work. The county issued a certificate of final occupancy on September 24, 1997.

In 2006, plaintiff purchased the hotel and soon thereafter allegedly discovered damage. Plaintiff filed an action against defendants for negligence, nuisance, and trespass *273 on May 23, 2007, a date that was more than 10 years after the posting of the completion notice but less than 10 years after the issuance of the certificate of final occupancy. Defendants moved for summary judgment, arguing that plaintiffs claims were barred by ORS 12.135, 3 which applies to claims arising from the construction, alteration, or repair of improvements to real property. 4 ORS 12.135(1) requires that such claims be commenced within the applicable statute of limitations, but in any event not later than 10 years from “substantial completion” or abandonment, whichever comes earlier. ORS 12.135(3) defines “substantial completion” to mean

“the date when the contractee accepts in writing the construction, alteration or repair of the improvement to real property or any designated portion thereof as having reached that state of completion when it may be used or occupied for its intended purpose or, if there is no such written acceptance, the date of acceptance of the completed construction, alteration or repair of such improvement by the contractee.”

*274 Defendants argued that “substantial completion” occurred on February 13, 1997, when VIP’s either accepted the construction in writing by posting the completion notice or demonstrated acceptance of the construction by opening its doors to the public. Plaintiff responded that a completion notice pursuant to ORS 87.045 is not a written acceptance of construction sufficient to satisfy the requirements of ORS 12.135 and that the 10-year period of ultimate repose did not begin to run until VIP’s accepted “completed” construction of the hotel.

The trial court accepted defendants’ argument that, because the hotel was open for business by February 13,1997, “substantial completion” occurred on that date and plaintiffs claims were time-barred. Plaintiff appealed, and the Court of Appeals reversed. PIH Beaverton, LLC v. Super One, Inc., 254 Or App 486, 294 P3d 536 (2013). Like the trial court, the Court of Appeals rejected defendants’ argument that the notice of completion posted by VIP’s pursuant to ORS 87.035 satisfied the requirements for written acceptance in ORS 12.135(3). However, unlike the trial court, the Court of Appeals also rejected defendants’ argument that “substantial completion” occurred when VIP’s opened for business. The court reasoned that, in the absence of written acceptance, ORS 12.135(3) requires evidence that the owner accepted the construction as fully completed. Because the evidence adduced on summary judgment indicated that construction was not fully complete on February 13, 1997, but continued thereafter, the Court of Appeals held that the trial court had erred in granting summary judgment. 254 Or App at 500.

Defendants petitioned for review, which this court granted to decide two legal questions presented by defendants’ motions for summary judgment:

1. When a constructed facility is opened for business, does the owner’s written completion notice pursuant to ORS 87.045 demonstrate written acceptance of construction sufficient to satisfy ORS 12.135(3)?
2. If there is no written acceptance that satisfies ORS 12.135(3), must a defendant that seeks the benefit of the 10-year limitations period demonstrate that the owner *275 accepted the construction as fully complete, or is evidence that the owner accepted the construction as sufficiently complete for its intended use or occupancy sufficient? 5 6

In reviewing a trial court’s disposition of a motion for summary judgment, this court determines whether the moving party is entitled to judgment as a matter of law. ORCP 47 C.

COMPLETION NOTICE AS ACCEPTANCE OF CONSTRUCTION

The first question presented focuses on the first clause of ORS 12.135

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SOMERSETT OWNERS ASS'N VS. SOMERSETT DEV. CO., LTD.
2021 NV 35 (Nevada Supreme Court, 2021)
Shell v. Schollander Companies, Inc.
369 P.3d 1101 (Oregon Supreme Court, 2016)
Montara Owners Assn. v. La Noue Development, LLC
353 P.3d 563 (Oregon Supreme Court, 2015)
Riverview Condominium Ass'n v. Cypress Ventures, Inc.
339 P.3d 447 (Court of Appeals of Oregon, 2014)
Shell v. Schollander Companies
336 P.3d 569 (Court of Appeals of Oregon, 2014)
Sunset Presbyterian Church v. Brockamp & Jaeger, Inc.
325 P.3d 730 (Oregon Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
323 P.3d 961, 355 Or. 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pih-beaverton-llc-v-super-one-inc-or-2014.