City of Burlington, Iowa v. S.G. Construction Co., Inc.

Court of Appeals of Iowa·Decided July 30, 2014·No. 12-1985·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 12-1985

Filed July 30, 2014

CITY OF BURLINGTON, IOWA, Plaintiff-Appellee,

vs.

S.G. CONSTRUCTION CO., INC., Defendant-Appellant.

Appeal from the Iowa District Court for Des Moines County, Cynthia Danielson, Judge.

A general contractor appeals the denial of its request for sanctions against the City of Burlington and its attorneys. AFFIRMED.

James A. Hales of Law Offices of James A. Hales, P.L.L.C., Burlington, for appellant.

W. Scott Power and Brent Ruther of Aspelmeier, Fisch, Power, Engberg & Helling, P.L.C., Burlington, for appellee.

Considered by Vaitheswaran, P.J., and Tabor and Bower, JJ.

TABOR, J.

This appeal raises the question whether a city or its attorneys should be sanctioned under Iowa Rule of Civil Procedure 1.413(1) for filing a lawsuit against a general contractor—before attempting to mediate the city’s claim— when the standard construction contract entered by the parties required mediation as a condition precedent to instituting legal proceedings. The district court denied a request by S.G. Construction for sanctions, finding the attorneys for the City of Burlington did not bring the suit for a malicious or improper purpose. In the same ruling, the court found a question of material fact regarding S.G.’s waiver of its right to mediate. Finding no abuse of discretion in the court’s denial of sanctions, we affirm. I. BACKGROUND FACTS AND PROCEEDINGS In October 2004, the City entered into a contract with S.G. Construction to design and construct a geothermal heating and cooling system for the public library. The project was substantially completed in November 2006. In November 2010, the system developed a crack resulting in the leaking of all liquid, including a twenty percent glycol solution.1 The librarian notified S.G. of the problem and S.G. contacted its subcontractors to make the repairs in January 2011, pursuant to the contract’s five-year warranty. But the glycol was not replaced because of disagreements about responsibility for the rupture. The library reported eventually spending nearly $24,000 to replace the lost glycol solution.

1 During a hearing before the district court, the city attorney described the glycol solution as serving the same purpose for the geothermal system as anti-freeze in a car radiator.

In December 2011, the city attorney sent a letter addressed to S.G. and two subcontractors demanding payment of $24,000 for the glycol replacement and other costs. The city attorney received no response to that letter.

On May 8, 2012, the city attorney filed a breach of contract and breach of warranty action against S.G. to compensate the library for damages sustained as a result of the leak in its geothermal system. Following the filing, the parties communicated with each other. S.G.’s attorney sent a letter to the city attorney on May 16, 2012, asserting commencement of the litigation was “premature” as their contract required the parties to undertake mediation as a condition precedent to the “institution of legal or equitable proceedings.” S.G. requested that the City dismiss the lawsuit.

Two days later, the city attorney responded, writing:

[Y[our suggestion to take this matter to mediation is an excellent one, especially in view of the amount involved. Because of the statute of limitations issue, I will not agree to dismissing the lawsuit now on file unless S.G., and perhaps the two subcontractors, execute a document waiving each entity’s right to impose a statute of limitations defense in the event the matter eventually ends up in litigation. In the alternative, and perhaps more practical, you could simply enter an appearance on behalf of S.G. and we could mutually agree to a court approved stay of the proceedings until we have had a chance to explore other dispute resolution options.

On May 22, 2012, S.G.’s attorney responded by suggesting the name of a mediator, but reiterating the company’s demand the City dismiss the lawsuit so it would not be able to create “some sort of leverage or other strategic advantage” in the mediation. S.G.’s attorney stated he did not understand the City’s basis for requesting a waiver of any statute of limitations defense, asserting the City was

not facing any kind of deadline for filing its suit. The city attorney wrote back on May 31, 2012, again expressing the City’s willingness to engage in “some form of alternative dispute resolution” but refusing to dismiss the lawsuit.

On June 15, 2012, the City filed a notice of intent to file a written application for default based on S.G.’s failure to respond to the initial petition. On June 26, 2012, S.G. responded with a motion to dismiss for failure to state a claim and for sanctions against the City and/or its attorneys for violating the contract terms by initiating legal proceedings before mediating the claim. S.G. requested the sanctions take the form of reasonable attorney fees as reimbursement for responding to the petition. The City resisted the dismissal motion and request for sanctions on July 9, 2012.

The district court held a hearing on S.G.’s motion to dismiss on July 16, 2012, and denied the motion by order the same day.

S.G. filed an answer to the petition on July 24, 2012. That same day, S.G.

filed a motion for summary judgment and renewed its request for sanctions against the City and its attorneys. The City resisted. The court held a hearing on the summary judgment motion on September 4, 2012.

On October 5, 2012, the district court denied summary judgment, finding “an issue of material fact with regard to whether the defendant waived its right to mediate as a condition precedent; that is whether the defendant was at fault for not allowing an alternative dispute resolution method to go forward.” The court also denied S.G.’s request for sanctions, concluding “the plaintiff did not engage in any malicious conduct with the intent to put the defendant at a disadvantage,

waste judicial resources, or bring the suit for an improper purpose in violation of Iowa Rule of Civil Procedure 1.413(1).”

The court stayed the proceedings on October 29, 2012. S.G. sought permission to bring an interlocutory challenge to the denial of summary judgment and sanctions. The supreme court granted interlocutory appeal on March 1, 2013. On April 22, 2013, the City dismissed the underlying action with prejudice.2 The supreme court transferred the remaining question concerning the propriety of sanctions under rule 1.413(1) to our court.3 II. SCOPE AND STANDARDS OF REVIEW Iowa appellate courts have adopted a deferential scope of review in sanction cases. Weigel v. Weigel, 467 N.W.2d 277, 279 (Iowa 1991). We review the district court’s decision whether to impose sanctions for abuse of discretion. Barnhill v. Iowa Dist. Ct., 765 N.W.2d 267, 272 (Iowa 2009). While our review is for abuse of discretion, we still may correct erroneous applications of the law. Id. If the pleading is signed in violation of rule 1.413, the court is required to impose an appropriate sanction. Id. We will be bound by the district court’s denial of sanctions if that decision is supported by substantial evidence. Id.

To decide if a pleading is sanctionable, we examine the facts at the time the party filed the pleading. Weigel, 467 N.W.2d at 280–81. We apply the standard of a reasonably competent attorney admitted to practice before the

2 The city asserts in a footnote to its appellee’s brief that the dismissal was “purely a business decision” by the library board. That information is outside the record and not properly before us. We do not consider the reason for the dismissal as relevant to the resolution of this appeal. 3 Iowa courts retain jurisdiction to impose sanctions even after a voluntary dismissal. See Lawson v. Kurtzhals, 792 N.W.2d 251, 260 n.4 (Iowa 2010).

Free access — add to your briefcase to read the full text and ask questions with AI

City of Burlington, Iowa v. S.G. Construction Co., Inc., (iowactapp 2014).

City of Burlington, Iowa v. S.G. Construction Co., Inc. (City of Burlington, Iowa v. S.G. Construction Co., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Halim v. Great Gatsby's Auction Gallery, Inc.
516 F.3d 557 (Seventh Circuit, 2008)
Barnhill v. Iowa District Court for Polk County
765 N.W.2d 267 (Supreme Court of Iowa, 2009)
Weigel v. Weigel
467 N.W.2d 277 (Supreme Court of Iowa, 1991)
Everly v. Knoxville Community School District
774 N.W.2d 488 (Supreme Court of Iowa, 2009)
Hearity v. Iowa District Court for Fayette County
440 N.W.2d 860 (Supreme Court of Iowa, 1989)
Tattoo Art, Inc. v. TAT International, LLC
711 F. Supp. 2d 645 (E.D. Virginia, 2010)
PIH Beaverton, LLC v. Super One, Inc.
323 P.3d 961 (Oregon Supreme Court, 2014)
William Neal Lawson Vs. Linda Irene Kurtzhals
792 N.W.2d 251 (Supreme Court of Iowa, 2010)
Travelers Casualty & Surety Co. of America, Inc. v. Long Bay Management Co.
792 N.E.2d 1013 (Massachusetts Appeals Court, 2003)