Sheffield Wind Project

CourtVermont Superior Court
DecidedJanuary 6, 2011
Docket252-10-08 Vtec
StatusPublished

This text of Sheffield Wind Project (Sheffield Wind Project) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheffield Wind Project, (Vt. Ct. App. 2011).

Opinion

STATE OF VERMONT

SUPERIOR COURT ENVIRONMENTAL DIVISION

} In re Sheffield Wind Project } Amended Individual Stormwater Permit } Docket No. 252-10-08 Vtec (No. 5535-INDC.A) } (Appeal of Brouha et al.) } }

Decision and Order on Motion to Alter Appellants Carol Brouha, Paul Brouha, Greg Bryant, Don Gregory, the King

George School, Linda Lavalle, Robert Tuthill, and David Zimmerman appealed from

a decision of the Vermont Agency of Natural Resources (ANR) issuing individual

stormwater discharge permit No. 5535-INDC, covering the construction of the

Sheffield Wind Project (the Project), and appealed from the amended individual

stormwater discharge permit (No. 5535-INDC.A) for the same project.1 The parties

agreed that the amended permit superseded the original one, and the appeal of the

amended permit was incorporated into the ongoing case.

Appellants are represented by Stephanie J. Kaplan, Esq., and Jared M.

Margolis, Esq.; Appellee-Applicants Signal Wind Energy, LLC and Vermont Wind,

LLC (referred to in the singular as “Vermont Wind” or “First Wind”) are

represented by Ronald A. Shems, Esq., Andrew N. Raubvogel, Esq., Geoffrey H.

Hand, Esq., and Elizabeth H. Catlin, Esq. The Vermont Agency of Natural

Resources (ANR) is represented by Judith L. Dillon, Esq.

The Court issued a decision on August 26, 2010, approving an amended

1 The project holds other permits and approvals from the Public Service Board and the Vermont Agency of Natural Resources (ANR) that were not appealed, including the ANR’s approval of the project’s operational stormwater discharge management system.

1 individual construction stormwater discharge permit covering the period during

construction of the Project. Appellants moved to alter the Court’s decision under

V.R.C.P. 59(e), asking the Court to correct what they characterize as six errors in the

Court’s decision. Appellants also later filed an emergency motion to stay the

operation of the permit pending appeal, which was fully briefed as of November 8,

2010 and which the Court addressed and denied in a written decision dated

November 19, 2010.

Standard Applicable to a Motion to Alter or Amend a Judgment

Vermont Rule of Civil Procedure 59(e), which is substantially identical to

Federal Rule 59(e), “gives the court broad power to alter or amend a judgment on

motion within ten days after entry thereof.” Drumheller v. Drumheller, 2009 VT 23,

¶ 28 (citing V.R.C.P. 59, Reporter's Notes). Rule 59(e) is a codification of the trial

court's “inherent power to open and correct, modify, or vacate its judgments.” Id.

(citing West v. West, 131 Vt. 621, 623 (1973)). Although there is no explicit

authorization in the rules of civil or appellate procedure, or in the rules specific to

this Court, for a motion to “reconsider” a final decision, such motions are also

treated as motions to amend or alter a judgment under V.R.C.P. 59(e). Appeal of

Berezniak, No. 171-9-03 Vtec, slip op. at 3 (Vt. Envtl. Ct. Apr. 6, 2007) (Wright, J.).

A Rule 59(e) motion “allows the trial court to revise its initial judgment if

necessary to relieve a party against the unjust operation of the record resulting from

the mistake or inadvertence of the court and not the fault or neglect of a party.”

Rubin v. Sterling Enterprises, Inc., 164 Vt. 582, 588 (1996) (citing In re Kostenblatt,

161 Vt. 292, 302 (1994)). More specifically, the limited functions of a motion to alter

or amend a judgment are “to correct manifest errors of law or fact on which the

decision was based, to allow the moving party to present newly discovered or

previously unavailable evidence, to prevent manifest injustice, or to respond to an

2 intervening change in the controlling law.” In re Vanishing Brook Subdivision, No.

223-10-07 Vtec, slip op. at 4 (Vt. Envtl. Ct. July 10, 2008) (Wright, J.) (quoting 11

Wright, Miller, & Kane, Federal Practice and Procedure: Civil § 2810.0 (2d ed. 1995));

see also Appeal of Van Nostrand, Nos. 209-11-04 & 101-5-05 Vtec, slip op. at 4 (Vt.

Envtl. Ct. Dec. 11, 2006) (Durkin, J.). On the other hand, Rule 59(e) should not be

used to “relitigate old matters” or “raise arguments or present evidence that could

have been raised prior to entry of the judgment.” Van Nostrand, Nos. 209-11-04 &

101-5-05 Vtec, slip op. at 4.

Appellants’ Motion to Alter

Appellants ask the Court to address the following six issues in the Court’s

decision and to alter that decision accordingly on each of the issues.

The finding that 65.6 acres of the 83.2 acres located within the flagged limits of construction will be disturbed during construction The Court found that 83.2 acres of the project property will lie within the

flagged limits of construction, but that, within the flagged limits of construction,

approximately 65.6 acres of the project property is actually proposed to be disturbed

during construction of the project. In re Sheffield Wind Project, No. 252-10-08 Vtec,

slip op. at 4 (Vt. Envtl. Ct Aug, 26 2010) (Wright, J.). Applicants argue that because

there is no clear delineation in the project plans indicating where within the 83.2

acres of the flagged limits of construction earth will be disturbed, the Court should

find that the area to be disturbed is instead 83.2 acres. Motion to Alter at 3.

Appellants then argue that, because the 83.2 acre area is significantly larger than the

60.5 acres that Applicants initially proposed to disturb, the Court should find that

the Best Management Practices (BMPs) proposed to be employed are insufficient to

protect water quality, and should instead deny the permit. Id. at 3–4.

3 As noted in the decision on the merits, the burden of overcoming the

presumption of compliance with the Vermont Water Quality Standards (VWQS) lies

with the Appellants. Sheffield Wind Project, No. 252-10-08 Vtec, slip op. at 19. In its

decision, the Court determined that the Appellants failed to present evidence

sufficient to overcome the presumption that the BMPs, if properly employed, will

cause the project to comply with the VWQS. Sheffield Wind Project, No. 252-10-08

Vtec, slip op. at 18-19.

Appellants’ Motion to Alter fails to present the Court with any additional

evidence or to point out any overlooked provisions of law that might change this

conclusion. The Court has reviewed the evidence and its notes as to the testimony at

trial, and declines to alter its decision on this issue.

The conclusion that Exhibit 2a is merely a different graphic representation of information that was already in the application materials During trial, the Court denied Appellants’ motion to add issues to their

Statement of Questions regarding the set of plans in evidence as Exhibit 2a, ruling

that all the information needed to prepare Exhibit 2a was contained in the

application materials, the Permit and the EPSC Plan, although the Court recognized

that the references to the plans produced for the operational stormwater permit

were not as clear as they could have been. Sheffield Wind Project, No. 252-10-08

Vtec, slip op. at 22. Appellants argue that the Court erred in finding that Exhibit 2a

presents the information that was already contained in Exhibits 1 and 2 in a different

graphical depiction. Appellants argue that based on this error, the presumption that

the BMPs will be sufficient to protect water quality on the site is unfounded and the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Drumheller v. Drumheller
2009 VT 23 (Supreme Court of Vermont, 2009)
In Re Kostenblatt
640 A.2d 39 (Supreme Court of Vermont, 1994)
West v. West
312 A.2d 920 (Supreme Court of Vermont, 1973)
Rubin v. Sterling Enterprises, Inc.
674 A.2d 782 (Supreme Court of Vermont, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Sheffield Wind Project, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheffield-wind-project-vtsuperct-2011.