Sheffield Wind Project

CourtVermont Superior Court
DecidedAugust 26, 2010
Docket252-10-08 Vtec
StatusPublished

This text of Sheffield Wind Project (Sheffield Wind Project) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheffield Wind Project, (Vt. Ct. App. 2010).

Opinion

STATE OF VERMONT

SUPERIOR COURT ENVIRONMENTAL DIVISION Docket No. 252-10-08 Vtec

} In re Sheffield Wind Project } Amended Individual Stormwater Permit (No. 5535-INDC.A) } (Appeal of Brouha et al.) } }

Decision and Order

Appellants Carol Brouha, Paul Brouha, Greg Bryant, Don Gregory, the King

George School, Linda Lavalle, Robert Tuthill, and David Zimmerman initially appealed1

in October 2008 from a decision of the Vermont Agency of Natural Resources (ANR)

issuing individual stormwater discharge permit No. 5535-INDC, covering the

construction of the Sheffield Wind Project (the Project) in Sheffield, Vermont. The

permit underwent an amendment before the ANR, and, in late May of 2009, Appellants

filed a notice of appeal from the amended individual stormwater discharge permit (No.

5535-INDC.A) for the same project. The parties agreed that the amended permit

superseded the original one, and that it would be most efficient to incorporate the

appeal of the amended permit in the ongoing case.

Appellants are represented by Jared M. Margolis Esq., and Stephanie J. Kaplan,

Esq.; Appellee-Applicants Signal Wind Energy, LLC and Vermont Wind, LLC (referred

to as in the singular as “Applicant” or “Vermont Wind”)2 are represented by Ronald A.

Shems, Esq., Andrew N. Raubvogel, Esq., Geoffrey H. Hand, Esq., and Elizabeth H.

Catlin, Esq. The Vermont Agency of Natural Resources (ANR) is represented by Judith

1 In addition, Jane Rollins was an appellant who later withdrew. 2 The amended permit lists only Vermont Wind, LLC as the “Principal Permittee” and

does not show a co-permittee; however Appellee-Applicants did not withdraw or dismiss Signal Wind Energy, LLC from this proceeding. 1 L. Dillon, Esq.

The Court issued two decisions on the parties’ motions for summary judgment,

and on other pending motions, on September 29, 2009 and October 19, 2009,

substantially narrowing the issues for trial.3 On October 13, 2009, Appellants filed a

more specific statement that further narrowed the issues in Questions 1 and 2 of the

Statement of Questions. Thirteen days of trial were held in this matter before Merideth

Wright, Environmental Judge. During trial, Question 4 of the Statement of Questions

was also resolved, as the parties recognized that no portion of the area proposed to be

disturbed by the project was located at an elevation over 2500 feet above sea level. In

addition, during trial the parties resolved Question 11 of the Statement of Questions by

agreeing to a revision to Part III.A.10 of the Project’s Permit4 and Erosion Prevention

and Sediment Control (EPSC)5 Plan to state as follows:

3 The September 29, 2009 Summary Judgment Decision discussed the discrepancies between the initial statement of questions and the statement of questions filed in June 2009 regarding the amended permit, and established a consolidated statement of questions remaining after that decision. The numbering used in the present decision refers to the question numbers used in that consolidated Statement of Questions. 4 The Permit at issue in this appeal (Vermont Wind Ex. 1), incorporates by reference an

EPSC Plan narrative prepared by VHB Pioneer (also found in VW Ex. 1), and associated EPSC Plan sheets 5C-116 through 123 and detail sheets 5C-601 through 603 prepared by James W. Sewall Co. (VW Ex. 2 and 2a). The Court notes that the part and section numbers referred to in this revision and in the other conditions proposed by Vermont Wind appear in the Permit document itself (Ex.1), rather than in the Plan narrative or Plan sheets, although Vermont Wind’s memoranda refer to the revisions as being to the EPSC Plan. Also see n. 8 at p. 8 below. 5 Several acronyms are used throughout the evidence and the parties’ memoranda and

other materials associated with this case and are provided here for the reader’s assistance: BMPs: Best Management Practices EPSC: Erosion Prevention and Sediment Control NPDES: National Pollutant Discharge Elimination System 2 When site conditions between April 15 and May 15 are similar to winter conditions—such as snow cover, frozen ground, or saturated soils— within the areas of planned earth disturbance, the appropriate winter restrictions on page 3.19 of the 2006 Vermont Standards and Specifications for Erosion Prevention and Sediment Control selected by the [On-Site Plan Coordinator] OSPC shall be applied to the portions of the site that are experiencing those conditions. Thus, as of the close of trial, Questions 1, 2, 3, and 7 remained to be addressed in the

appeal.

After trial, the parties were given the opportunity to submit written memoranda

and requests for findings. Upon consideration of the evidence and of the written

memoranda and requests for findings filed by the parties, the Court finds and

concludes as follows.

Vermont Wind, LLC proposes to construct and operate a wind electrical

generating facility (the Project) on property on Granby Mountain and Libby Hill in

Sheffield, Vermont, near the headwaters of small6 unnamed tributaries of Calendar

Brook, Nation Brook, Annis Brook, Willoughby Brook, and Clark Brook.

The Project consists of an array of sixteen wind turbines, each located on a

concrete pad, along a 16-foot-wide access roadway. The project also includes a

permanent meteorological tower, which appears on the project plans and narrative but

was not specifically at issue during trial. During construction, the access roadways will

be constructed to the 25-foot width necessary for crane access for the equipment used to

erect the wind turbine structures; at the conclusion of the need for crane access, the

Project’s permanent roadways will be reduced to the 16-foot width by seeding and

mulching the areas outside that width.

OSPC: On-Site Plan Coordinator VWQS: Vermont Water Quality Standards 6 Many of these small streams are under one foot in width on the Project property.

3 An electrical substation and a small operations and maintenance building are

also proposed as part of the Project. They are located on the lower portion of the

property, on either side of the project access road, near the public roadway. Electricity

will be conducted by underground and above-ground transmission lines from the

turbines down to the electrical substation. The Project is located adjacent to and will tie

into an existing VELCO electrical transmission line. In the amended permit application

now before the Court, the Project’s path or layout was altered from that presented in the

original permit application to decrease the total area of disturbed land, to minimize the

need to work on steep slopes and erodible soils, and to reduce impacts on wetlands and

streams.

The overall property on which the Project is located consists of approximately

three thousand acres leased from Meadowsend Timberlands, some of which has been

logged in the past. The Project will follow the path of existing logging roads and use

existing cleared areas to the greatest extent possible without adversely affecting

wetlands or streams on the Project property. Additional logging by Meadowsend is

anticipated to occur on approximately 500 acres of the overall project property over the

next five years.

Approximately 83.2 acres of the Project property is located within the flagged

limits of construction. Within that limits-of-construction area, approximately 65.6 acres

of the project property actually is proposed to be disturbed during construction of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Sheffield Wind Project, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheffield-wind-project-vtsuperct-2010.