Sheffield Wind Project

Vermont Superior Court·Decided August 26, 2010·No. 252-10-08 Vtec·Published

Opinion

STATE OF VERMONT

SUPERIOR COURT ENVIRONMENTAL DIVISION Docket No. 252-10-08 Vtec

}

In re Sheffield Wind Project } Amended Individual Stormwater Permit (No. 5535-INDC.A) } (Appeal of Brouha et al.) } }

Decision and Order

Appellants Carol Brouha, Paul Brouha, Greg Bryant, Don Gregory, the King George School, Linda Lavalle, Robert Tuthill, and David Zimmerman initially appealed1 in October 2008 from a decision of the Vermont Agency of Natural Resources (ANR) issuing individual stormwater discharge permit No. 5535-INDC, covering the construction of the Sheffield Wind Project (the Project) in Sheffield, Vermont. The permit underwent an amendment before the ANR, and, in late May of 2009, Appellants filed a notice of appeal from the amended individual stormwater discharge permit (No. 5535-INDC.A) for the same project. The parties agreed that the amended permit superseded the original one, and that it would be most efficient to incorporate the appeal of the amended permit in the ongoing case.

Appellants are represented by Jared M. Margolis Esq., and Stephanie J. Kaplan, Esq.; Appellee-Applicants Signal Wind Energy, LLC and Vermont Wind, LLC (referred to as in the singular as “Applicant” or “Vermont Wind”)2 are represented by Ronald A. Shems, Esq., Andrew N. Raubvogel, Esq., Geoffrey H. Hand, Esq., and Elizabeth H. Catlin, Esq. The Vermont Agency of Natural Resources (ANR) is represented by Judith

1 In addition, Jane Rollins was an appellant who later withdrew. 2 The amended permit lists only Vermont Wind, LLC as the “Principal Permittee” and

does not show a co-permittee; however Appellee-Applicants did not withdraw or dismiss Signal Wind Energy, LLC from this proceeding.

L. Dillon, Esq.

The Court issued two decisions on the parties’ motions for summary judgment, and on other pending motions, on September 29, 2009 and October 19, 2009, substantially narrowing the issues for trial.3 On October 13, 2009, Appellants filed a more specific statement that further narrowed the issues in Questions 1 and 2 of the Statement of Questions. Thirteen days of trial were held in this matter before Merideth Wright, Environmental Judge. During trial, Question 4 of the Statement of Questions was also resolved, as the parties recognized that no portion of the area proposed to be disturbed by the project was located at an elevation over 2500 feet above sea level. In addition, during trial the parties resolved Question 11 of the Statement of Questions by agreeing to a revision to Part III.A.10 of the Project’s Permit4 and Erosion Prevention and Sediment Control (EPSC)5 Plan to state as follows:

3 The September 29, 2009 Summary Judgment Decision discussed the discrepancies between the initial statement of questions and the statement of questions filed in June 2009 regarding the amended permit, and established a consolidated statement of questions remaining after that decision. The numbering used in the present decision refers to the question numbers used in that consolidated Statement of Questions. 4 The Permit at issue in this appeal (Vermont Wind Ex. 1), incorporates by reference an

EPSC Plan narrative prepared by VHB Pioneer (also found in VW Ex. 1), and associated EPSC Plan sheets 5C-116 through 123 and detail sheets 5C-601 through 603 prepared by James W. Sewall Co. (VW Ex. 2 and 2a). The Court notes that the part and section numbers referred to in this revision and in the other conditions proposed by Vermont Wind appear in the Permit document itself (Ex.1), rather than in the Plan narrative or Plan sheets, although Vermont Wind’s memoranda refer to the revisions as being to the EPSC Plan. Also see n. 8 at p. 8 below. 5 Several acronyms are used throughout the evidence and the parties’ memoranda and

other materials associated with this case and are provided here for the reader’s assistance: BMPs: Best Management Practices EPSC: Erosion Prevention and Sediment Control NPDES: National Pollutant Discharge Elimination System

When site conditions between April 15 and May 15 are similar to winter conditions—such as snow cover, frozen ground, or saturated soils—

within the areas of planned earth disturbance, the appropriate winter restrictions on page 3.19 of the 2006 Vermont Standards and Specifications for Erosion Prevention and Sediment Control selected by the [On-Site Plan Coordinator] OSPC shall be applied to the portions of the site that are experiencing those conditions.

Thus, as of the close of trial, Questions 1, 2, 3, and 7 remained to be addressed in the

appeal.

After trial, the parties were given the opportunity to submit written memoranda and requests for findings. Upon consideration of the evidence and of the written memoranda and requests for findings filed by the parties, the Court finds and concludes as follows.

Vermont Wind, LLC proposes to construct and operate a wind electrical generating facility (the Project) on property on Granby Mountain and Libby Hill in Sheffield, Vermont, near the headwaters of small6 unnamed tributaries of Calendar Brook, Nation Brook, Annis Brook, Willoughby Brook, and Clark Brook.

The Project consists of an array of sixteen wind turbines, each located on a concrete pad, along a 16-foot-wide access roadway. The project also includes a permanent meteorological tower, which appears on the project plans and narrative but was not specifically at issue during trial. During construction, the access roadways will be constructed to the 25-foot width necessary for crane access for the equipment used to erect the wind turbine structures; at the conclusion of the need for crane access, the Project’s permanent roadways will be reduced to the 16-foot width by seeding and mulching the areas outside that width.

OSPC: On-Site Plan Coordinator VWQS: Vermont Water Quality Standards 6 Many of these small streams are under one foot in width on the Project property.

An electrical substation and a small operations and maintenance building are also proposed as part of the Project. They are located on the lower portion of the property, on either side of the project access road, near the public roadway. Electricity will be conducted by underground and above-ground transmission lines from the turbines down to the electrical substation. The Project is located adjacent to and will tie into an existing VELCO electrical transmission line. In the amended permit application now before the Court, the Project’s path or layout was altered from that presented in the original permit application to decrease the total area of disturbed land, to minimize the need to work on steep slopes and erodible soils, and to reduce impacts on wetlands and streams.

The overall property on which the Project is located consists of approximately three thousand acres leased from Meadowsend Timberlands, some of which has been logged in the past. The Project will follow the path of existing logging roads and use existing cleared areas to the greatest extent possible without adversely affecting wetlands or streams on the Project property. Additional logging by Meadowsend is anticipated to occur on approximately 500 acres of the overall project property over the next five years.

Approximately 83.2 acres of the Project property is located within the flagged limits of construction. Within that limits-of-construction area, approximately 65.6 acres of the project property actually is proposed to be disturbed during construction of the project, including construction of the Project’s associated permanent and temporary stormwater management features. All the features are capable of being constructed in lifts or stages to avoid equipment intruding beyond the required limits.

Free access — add to your briefcase to read the full text and ask questions with AI

Sheffield Wind Project, (Vt. Ct. App. 2010).

Sheffield Wind Project (Sheffield Wind Project) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related