Sheffield Wind Project

CourtVermont Superior Court
DecidedSeptember 29, 2009
Docket252-10-08 Vtec
StatusPublished

This text of Sheffield Wind Project (Sheffield Wind Project) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheffield Wind Project, (Vt. Ct. App. 2009).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re Sheffield Wind Project } Docket No. 252-10-08 Vtec (Appeal of Brouha et al.) } }

Decision and Order on Pending Motions

Appellants Carol Brouha, Paul Brouha, Greg Bryant, Don Gregory, the King

George School, Linda Lavalle, Jane Rollins, Robert Tuthill, and David Zimmerman

initially appealed from a decision of the Vermont Agency of Natural Resources (ANR)

issuing individual stormwater discharge permit (No. 5535-INDC), covering the

construction of the Sheffield Wind Project in Sheffield, Vermont. In late May of 2009,

Appellants filed a notice of appeal from the amended individual stormwater discharge

permit (No. 5535-INDC.A) for the same project. The parties agreed that the amended

permit superseded the original one, and that it would be most efficient to incorporate

the appeal of the amended permit in the ongoing case, allowing the parties to

supplement their motion memoranda to address all issues from both appeals that still

pertain to the amended permit

Appellants are represented by Stephanie J. Kaplan, Esq.; Appellee-Applicants

Signal Wind Energy, LLC and Vermont Wind, LLC are represented by Ronald A.

Shems, Esq., Andrew N. Raubvogel, Esq., and Geoffrey H. Hand, Esq. The Vermont

Agency of Natural Resources is represented by Judith L. Dillon, Esq. Appellee-

Applicants have moved to dismiss certain questions in the statement of questions. Both

parties have moved for summary judgment. The facts stated in this decision are

undisputed unless otherwise noted.

1 Standards Applicable to the Present Motions

Summary judgment is appropriate “only where, taking the allegations of the

nonmoving party as true, it is evident that there exist no genuine issues of material fact

and the movant is entitled to judgment as a matter of law.” Fritzeen v. Trudell

Consulting Engineers, 170 Vt. 632, 633 (2000) (mem.). When presented with cross-

motions for summary judgment, the Court considers each motion independently and

“afford[s] all reasonable doubts and inferences to the party opposing the particular

motion under consideration.” In re Chimney Ridge Road Merged Parcels, No. 208-9-08

Vtec, slip op. at 2 (Vt. Envtl. Ct. July 31, 2009) (Durkin, J.) (citing DeBartolo v.

Underwriters at Lloyd’s of London, 2007 VT 31, ¶ 8, 181 Vt. 609).

In considering a motion for summary judgment, the trial court’s function is “not

to make findings on disputed factual issues.” Blake v. Nationwide Ins. Co., 2006 VT 48,

¶ 21, 180 Vt. 14; Gettis v. Green Mountain Economic Development Corp., 2005 VT 117,

¶ 19, 179 Vt. 117. In the context of summary judgment, the court does not adjudicate

the credibility of the parties or their witnesses or the weight of the facts offered through

the affidavits submitted on summary judgment. Provost v. Fletcher Allen Health Care,

Inc., 2005 VT 115, ¶ 15, 179 Vt. 545 (stating that summary judgment is not warranted

simply because a movant offers facts that appear more plausible than those tendered in

opposition, or if the opposing party appears unlikely to prevail at trial.)1

Trial courts are cautioned that summary judgment “is not a substitute for a

determination on the merits, so long as evidence has been presented which creates an

issue of material fact, no matter what view the court may take of the relative weight of

that evidence.” Fritzeen, 170 Vt. at 633 (internal citation omitted).

1 No responses to requests to admit have been submitted in the present case. See Gallipo v. City of Rutland, 2005 VT 83, ¶¶ 20–22, 178 Vt. 244 (citing Freed v. Plastic Packaging Materials, Inc., 66 F.R.D. 550, 552 (E.D. Pa. 1975) (facts in a request to admit that are deemed admitted become undisputed and can serve as a basis for summary judgment). 2 In interpreting and applying administrative rules or regulations, such as the

provisions of the Vermont Water Quality Standards (VWQS) at issue in this case, the

Court approaches regulatory construction in the same manner as statutory

interpretation. In re Williston Inn Group, 2008 VT 47, ¶ 14, 183 Vt. 621 (citing

Conservation Law Found. v. Burke, 162 Vt. 115, 121 (1993)). The Court’s “overall goal is

to discern the intent of the drafters,” first and foremost “by reference to the plain

meaning of the regulatory language.” Id. (citing Slocum v. Dep’t of Soc. Welfare, 154

Vt. 474, 478 (1990)). The other tools of statutory construction are also available “should

the plain-meaning rule prove unavailing.” Id.

Section 1-05 of the Vermont Water Quality Standards also addresses the issue of

their interpretation. That provision recognizes that ordinarily the Secretary of the ANR

will apply and interpret the regulations in permit proceedings, but specifically states

that:

[w]here a de novo appeal is taken from the Secretary’s decision, the appellate decision-maker must make determinations and interpretations under these rules to achieve the purposes of both state and federal law. The decision-maker in a de novo appeal is not bound by any determinations or interpretations of these rules made by the Secretary relative to an application, provided that review of such determinations is within the scope of the appeal.

VWQS § 1-05 (emphasis added).

Although the Court is not bound by the Agency’s determinations or

interpretations of the VWQS “relative to [a particular] application,” as in In re: Unified

Buddhist Church, Inc., No. 253-10-06 Vtec, slip op. at 3 (Vt. Envtl. Ct. Jan. 25, 2008)

(Wright, J.), “deference is to be given to the interpretation of regulations and to the

construction of a statute by the agency responsible for its execution.” Id. (citing In re

Appeal of Electronic Industries Alliance, 2005 VT 111, ¶7, 179 Vt. 539).

3 References to the Numbering of Questions in the Statements of Questions

Unfortunately, Appellants did not use a consistent numbering system between

the statement of questions pertaining to the original permit (Statement of Questions

filed January 5, 2009) and the statement of questions pertaining to the amended permit

(Statement of Questions filed June 18, 2009). This decision will refer to the questions

from the June Statement of Questions simply as “Question #,” and will refer to any

distinctions between the questions from the January and June Statements of Questions

as “January Question #” or “June Question #,” as necessary to minimize confusion.

Issues That Are Moot or Otherwise Have Been Resolved

January Question 2, regarding the project’s compliance with the provisions of

federal regulation 40 CFR § 131.12, was not included in the June Statement of Questions.

Accordingly, Applicants’ motions to dismiss or for summary judgment as to that

question are moot. Question 2 from the January Statement of Questions is not an issue

in the appeal from the amended permit, and will not be further discussed.

January Question 13, regarding whether the project’s “plan to bury 3.1 miles of

electricity collection cables complies with the acceptable practices in the Vermont

Stormwater Management Manual,” was withdrawn by Appellants on May 11, 2009.

Given that Appellants did not contest Applicants’ argument that the Stormwater

Management Manual only applies to operational permits, and therefore does not apply

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Insurance Co. of State of Pa. v. Johnson
2009 VT 92 (Supreme Court of Vermont, 2009)
Slocum v. Department of Social Welfare
580 A.2d 951 (Supreme Court of Vermont, 1990)
Gettis v. Green Mountain Economic Development Corp.
2005 VT 117 (Supreme Court of Vermont, 2005)
Conservation Law Foundation v. Burke
645 A.2d 495 (Supreme Court of Vermont, 1993)
Fritzeen v. Trudell Consulting Engineers, Inc.
751 A.2d 293 (Supreme Court of Vermont, 2000)
Blake v. Nationwide Insurance
2006 VT 48 (Supreme Court of Vermont, 2006)
In Re Appeal of Electronic Industries Alliance
2005 VT 111 (Supreme Court of Vermont, 2005)
Trickett v. Ochs
2003 VT 91 (Supreme Court of Vermont, 2003)
Gallipo v. City of Rutland
2005 VT 83 (Supreme Court of Vermont, 2005)
Provost v. Fletcher Allen Health Care, Inc.
2005 VT 115 (Supreme Court of Vermont, 2005)
In re Williston Inn Group
2008 VT 47 (Supreme Court of Vermont, 2008)
Freed v. Plastic Packaging Materials, Inc.
66 F.R.D. 550 (E.D. Pennsylvania, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
Sheffield Wind Project, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheffield-wind-project-vtsuperct-2009.