Scroggin v. National Lumber Co.

59 N.W. 548, 41 Neb. 195, 1894 Neb. LEXIS 144
Nebraska Supreme Court·Decided June 6, 1894·No. No. 4742·Published·Cited by 15 cases

Opinion

Irvine, C.

None of the errors alleged to have occurred on the trial of this case can be considered, for the reason that the case is brought here by petition in error and there was no motion for a new trial in the district court. (Cropsey v. Wiggenhorn, 8 Neb., 108; Wells v. Preston, 3 Neb., 444; Singleton v. Boyle, 4 Neb., 414; Hull v. Miller, 6 Neb., 128; Crutts v. Wray, 19 Neb., 581; Manning v. Cunningham, 21 Neb., 288; Smith v. Spaulding, 34 Neb., 128; Miller v. Antelope County, 35 Neb., 237.) This rule applies as well to equity cases brought here on error as to cases at law. (Harrington v. Latta, 23 Neb., 84; Carlow v. Aultman, 28 Neb., 672; Fitzgerald v. Brandt, 36 Neb., 683; Gray v. Disbrow, 36 Neb., 857.) This rule is so firmly established that parties would save to. themselves expense, [197] and to the court the expenditure of time which cannot be spared from the consideration of other eases by. paying due regard thereto. Whether or not the question is raised by the adverse party this court will look into the record and refuse to consider any assignments of error occurring at the trial unless the record discloses a motion for a new trial and a ruling thereon.

The only assignment of error sufficiently definite for consideration at all, and not relating to matters occurring upon the trial, is that the judgment is not supported; by the findings of the court. A consideration of this assignment requires a statement of the pleadings. The defendant in error was the plaintiff below and alleged the sale and delivery to the plaintiff in error, under an oral contract made by one McClellan as agent for plaintiff in error, pf certain lumber and material for the erection of a corn crib ánd hog pen upon land of the plaintiff in error, and the filing of a claim of lien therefor. The prayer was for judgment and a foreclosure of the mechanic’s lien. To this petition the plaintiff in error made answer, denying the sale or delivery to him of any lumber or material, and denying any contract, therefor; denying the agency of McClellan; averring that McClellan was a tenant of plaintiff in error, and thát whatever he may have purchased from the defendant in error was bought upon his own account, without authority, knowledge, or consent of the plaintiff in error. The answer then averred that after the improvements were made McClellan charged the plaintiff in error with the cost thereof, and thereafter McClellan and the plaintiff in error had a full settlement of said account, including the'cost of lumber, and in such settlement McClellan was allowed, satisfied, and paid in full for the same. This last averment renders a consideration of the special findings of the court, which practically confirm it, unnecessary. The answer thus far pleads a good defense to the lien by the denial of any direct transactions with the defendant in error and by [198] denial of McClellan’s authority to deal for plaintiff. Unfortunately, however, for plaintiff in error he followed these averments with the statement that after the material was furnished, McClellan had charged him therefor on the accounting between them, that he had settled with McClellan on that basis, and had allowed and paid him therefor. If McClellan had no authority to make the improvements so as to charge the plaintiff in error, plaintiff in error’s action in accepting them, and acknowledging that the expense thereof was chargeable against him, was a complete ratification of McClellan’s acts and operated to charge plaintiff in error’s estate with the lien. Having adopted and ratified McClellan’s acts, his payment to McClellan was no defense to this action. It amounted simply to his payment of money to his agent and did not discharge the debt or lien of defendant in error. Therefore, so far as we have considered the pleadings, they entitled the defendant in error to a decree regardless of the evidence or findings.

The next paragraph of the answer avers that the claim of lien was not filed within the time required by law. There is a distinct special finding by the trial court adverse to the plaintiff in error upon this issue. .

Free access — add to your briefcase to read the full text and ask questions with AI

Scroggin v. National Lumber Co., 59 N.W. 548, 41 Neb. 195, 1894 Neb. LEXIS 144 (Neb. 1894).

59 N.W. 548 (Scroggin v. National Lumber Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sanitary & Improvement District No. 32 v. Continental Western Corp.
343 N.W.2d 314 (Nebraska Supreme Court, 1983)
Kissick Const. Co. v. First Nat. Bank of Wahoo
46 F. Supp. 869 (D. Nebraska, 1942)
Hadley v. Corey
288 N.W. 826 (Nebraska Supreme Court, 1939)
United States Fidelity & Guaranty Co. v. Parker
121 P. 531 (Wyoming Supreme Court, 1912)
Scott v. DeGraw
133 N.W. 179 (Nebraska Supreme Court, 1911)
Bank of Miller v. Moore
116 N.W. 167 (Nebraska Supreme Court, 1908)
Satterlund v. Beal
95 N.W. 518 (North Dakota Supreme Court, 1903)
Hobson v. Cummins
78 N.W. 295 (Nebraska Supreme Court, 1899)
Albers v. City of Omaha
76 N.W. 911 (Nebraska Supreme Court, 1898)
Goodwin v. Cunningham
74 N.W. 315 (Nebraska Supreme Court, 1898)
Bell v. Rice
70 N.W. 25 (Nebraska Supreme Court, 1897)
Winters v. Means
69 N.W. 753 (Nebraska Supreme Court, 1897)
Childerson v. Childerson
66 N.W. 281 (Nebraska Supreme Court, 1896)
Losure v. Miller
63 N.W. 863 (Nebraska Supreme Court, 1895)
Southard v. Minneapolis, St. Paul & Sault Sainte Marie Railway Co.
62 N.W. 442 (Supreme Court of Minnesota, 1895)