Schindler Elev. Corp. v. Rich Const. Co., No. Cv 92 0125222 (Apr. 2, 1996)

1996 Conn. Super. Ct. 3271
CourtConnecticut Superior Court
DecidedApril 2, 1996
DocketNo. CV 92 0125222
StatusUnpublished

This text of 1996 Conn. Super. Ct. 3271 (Schindler Elev. Corp. v. Rich Const. Co., No. Cv 92 0125222 (Apr. 2, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schindler Elev. Corp. v. Rich Const. Co., No. Cv 92 0125222 (Apr. 2, 1996), 1996 Conn. Super. Ct. 3271 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION This case involves a contract by Westinghouse Elevator Company (Westinghouse) to install an exterior or outdoor glass CT Page 3272 elevator at the Marriott Hotel in Stamford. The plaintiff, Schindler Elevator Corporation (Schindler), alleges in its complaint that it is the "successor" to Westinghouse, that Westinghouse constructed and installed the elevator pursuant to a written contract with the defendant, F. D. Rich Construction Co., Inc. (F. D. Rich), and that it is owed approximately $50,000 as the balance due and unpaid under the contract.

The defendant filed a revised answer, special defense and a counterclaim dated April 20, 1994, in which it denied the material allegations of the complaint. Its special defenses contend that the elevator was inoperable, that both express and implied warranties by Westinghouse had been breached, and that the plaintiff's claim is barred by the statute of limitations set forth in General Statutes §§ 52-576 and 52-581.1 In its counterclaim, which contains three counts, breach of contract, detrimental reliance on promises and representations made by Westinghouse, and a violation of General Statutes § 42-110a et seq., the Connecticut Unfair Trade Practices Act (CUTPA), the defendant contends that Westinghouse knew that the elevator was to be installed on the outside of the hotel building, and therefore would be exposed to inclement weather. The defendant further alleges that the elevator does not function during the winter, that the elevator was constructed and/or installed in an unworkmanlike manner, and that the defendant had previously paid to Westinghouse more money than the elevator was worth because of its operating problems. In the second count of the counterclaim, the defendant asserts that it relied on promises and representations made by the plaintiff's predecessor or assignor, Westinghouse, that the elevator would function properly during the entire year, and that it suffered financial loss due to this reliance. The third count alleges that Westinghouse engaged in unfair and deceptive trade practices in violation of CUTPA.

The plaintiff filed an answer and several special defenses to the defendant's counterclaim, in which it agreed that Westinghouse constructed an elevator at the Marriott pursuant to a contract with F. D. Rich, and knew that it would be located outside and exposed to inclement weather, but otherwise denied the material allegations of the counterclaim. Its special defenses claim that the defendant's counterclaim is barred by the statute of limitations contained in General Statutes §§ 52-576,52-581, 52-577, and 42-110g(f).2

This case was referred to Attorney Bernadette Coomaraswamy, CT Page 3273 an attorney trial referee, in accordance with General Statutes § 52-434(a) and Practice Book § 428 et seq. The referee conducted a trial and then filed her report containing the following findings of fact: (1) that the contract for the installation of an outdoor elevator, which was a part of a major renovation of the Stamford Marriott, was between Westinghouse and the defendant, F. D. Rich, which was acting as general contractor and agent for the owner of the subject premises, the First Stamford New Urban Corporation;3 (2) that the contract was executed on or about October 6, 1983, and contained a provision, among others, that the owner must be satisfied with the elevator before the obligation to pay arose; (3) that the elevator was constructed outside the building and rose unenclosed for 18 stories to a revolving restaurant on the top of the Marriott; (4) that the parties to the contract understood and agreed that the elevator would not function for approximately twenty or thirty days per year because of anticipated high winds, but that, on an average, the outside elevator at the Marriott did not function and had to be shut down for approximately three months a year because of cold air infiltration; (5) that Westinghouse represented that it had constructed other similar outdoor elevators in colder climates, but actually had not done so; (6) that Westinghouse recommended and persuaded the defendant that a glass enclosure or tube for the elevator was not needed, but knew or should have known that such an encasement or enclosure was necessary; (7) that the defendant signed a "Final Acceptance Form" in July, 1986, but the defendant insisted on adding the words "substantial completion" to the form; (8) that the total cost of the elevator, which was installed in July, 1986, was roughly $268,000, of which the defendant has paid all but about $50,000 to Westinghouse; (9) that the contract provided that payment to Westinghouse by the defendant was not to be deemed a waiver of any defective work; (10) that the plaintiff became the successor or "assignee" of Westinghouse in 1989; and (11) that the defendant wrote to Westinghouse in November, 1986, stating that it refused to make any further payments for the elevator because of its dissatisfaction therewith.

The attorney trial referee concluded on the basis of the above findings of fact that: (1) the intent of the contract was to provide a unique outdoor elevator which itself would be a "a veritable tourist attraction" in Stamford, which the referee opined, was a "slick, chic city"; (2) the defendant relied on the superior knowledge of Westinghouse and its purported ability to construct an outdoor elevator in northern climates; (3) the CT Page 3274 addition of the words "substantial completion" to the "Final Acceptance Form" meant that the acceptance of the elevator by the defendant was not unqualified, but rather was conditional upon substantial completion of the project; (4) the defendant never unconditionally accepted the elevator installed by Westinghouse, nor was it ever satisfied with such elevator; (5) Westinghouse failed to fulfill its obligations under the contract with the defendant, and therefore the plaintiff, as successor to Westinghouse, could not prevail on its claim of breach of contract; (6) Westinghouse breached its express warranty that it would provide a functioning outdoor elevator, General Statutes § 42a-2-313(1)(a), and the implied warranty of fitness for a particular use, General Statutes § 42a-2-315; (7) although the defendant knew by at least early 1987 that Westinghouse had breached its contract in that the elevator had to be shut down during the winter months because of cold air infiltration, it did not file a counterclaim until April, 1994, and therefore such counterclaim is time barred by General Statutes § 52-576 regarding breach of contract; (8) the second count of the counterclaim, which alleges a tort, and the third count claiming a violation of CUTPA, are also both timed barred by the three year limitation periods contained in General Statutes §§ 52-577 and 42-110g(f), respectively; and (9) Westinghouse and the plaintiff, as the successor to Westinghouse, had been "more than adequately" compensated for their efforts on this project. The referee concluded by recommending that judgment enter for the defendant as to the plaintiff's complaint, and for the plaintiff with respect to F. D.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vincenzi v. Cerro
442 A.2d 1352 (Supreme Court of Connecticut, 1982)
Beckenstein v. Potter & Carrier, Inc.
464 A.2d 18 (Supreme Court of Connecticut, 1983)
Multi-Service Contractors, Inc. v. Town of Vernon
477 A.2d 653 (Supreme Court of Connecticut, 1984)
Dills v. Town of Enfield
557 A.2d 517 (Supreme Court of Connecticut, 1989)
Argentinis v. Gould
592 A.2d 378 (Supreme Court of Connecticut, 1991)
John T. Brady & Co. v. City of Stamford
599 A.2d 370 (Supreme Court of Connecticut, 1991)
Bernard v. Gershman
559 A.2d 1171 (Connecticut Appellate Court, 1989)
Argentinis v. Gould
579 A.2d 1078 (Connecticut Appellate Court, 1990)
Thermoglaze, Inc. v. Morningside Gardens Co.
583 A.2d 1331 (Connecticut Appellate Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 3271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schindler-elev-corp-v-rich-const-co-no-cv-92-0125222-apr-2-1996-connsuperct-1996.