Sbp Lllp v. Hoffman Construction Company
This text of Sbp Lllp v. Hoffman Construction Company (Sbp Lllp v. Hoffman Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS AUG 30 2023 MOLLY C. DWYER, CLERK U.S. COURT OF APPEALS FOR THE NINTH CIRCUIT
SBP LLLP, an Idaho limited liability limited No. 22-35150 partnership; JRS PROPERTIES III LP, an Idaho limited partnership; and J.R. D.C. No. 1:19-cv-00266-DCN SIMPLOT FOUNDATION, INC., an Idaho corporation MEMORANDUM * Plaintiffs-Appellees,
v.
HOFFMAN CONSTRUCTION COMPANY OF AMERICA, an Oregon corporation,
Defendant-Appellant.
Appeal from the United States District Court for the District of Idaho David C. Nye, District Judge, Presiding
Argued and Submitted August 23, 2023 Portland, Oregon
Before: BENNETT, VANDYKE, and H.A. THOMAS, Circuit Judges.
* This disposition is not appropriate for publication and is not precedent except as provided by Ninth Circuit Rule 36-3. Hoffman Construction Company contracted with Appellees—three affiliated
companies of agribusiness J.R. Simplot Company (collectively, Simplot)—to build
Simplot a headquarters in Boise, Idaho. A dispute arose concerning reimbursement
of costs Hoffman incurred during construction delays, and after Simplot repeatedly
declined to mediate the dispute, Hoffman initiated arbitration proceedings seeking
roughly $4.7 million for alleged breach of contract. Simplot sued in state court to
stay arbitration, and Oregon-based Hoffman removed the case to federal court.
The parties’ contracts are modified versions of two American Institute of
Architects (AIA) contract templates (A121 and A133) that incorporate by reference
a separate AIA form of general contract terms and conditions (A201). The main
question on appeal is whether the contracts, as modified, incorporate A201’s
standard arbitration provisions. The district court concluded that they do not,
ultimately basing its conclusion on parol evidence. It entered judgment for Simplot
and awarded Simplot attorneys’ fees and costs. Hoffman timely appealed both the
judgment and the fee and costs awards.
Hoffman makes a four-step argument on appeal. First, section 1.2 of each
signed contract incorporates the entirety of the modified A201 form the parties
attached to each contract when it was signed. Second, the parties made other
modifications to those A201 forms, but never removed the standard arbitration
clauses from them. Third, because section 1.2 of the signed contracts therefore
2 unambiguously incorporates those arbitration clauses, the district court erred when
it based its conclusion to the contrary on parol evidence from the contracts’ drafting
history. Fourth, even if the court did consider parol evidence, in the aggregate that
evidence compels a conclusion that the parties agreed to arbitrate disputes.
A determination whether the parties’ contracts contain valid arbitration
agreements is reviewed de novo under Idaho law, with the burden on Hoffman as
the party that argues they do. Reichert v. Rapid Invs., Inc., 56 F.4th 1220, 1226–27
(9th Cir. 2022) (per curiam). Determining whether a contract provides for arbitration
begins with a contract’s plain terms, and it ends there unless the language at issue is
ambiguous. Burns Concrete, Inc. v. Teton Cnty., 529 P.3d 747, 754 (Idaho 2023).
If a court concludes an ambiguity exists, it must try to resolve it first by analysis of
other language in the executed contract before finally turning to parol evidence as a
last resort. Steel Farms, Inc. v. Croft & Reed, Inc., 297 P.3d 222, 229 (Idaho 2012).
Section 1.2 of the contracts Hoffman and Appellees signed incorporates a
modified A201 form. It is undisputed that the modified A201 forms were attached
to two of the contracts at the time they were signed. For the third contract, while the
modified A201 form may not have been physically attached to the contract at the
time of signing, Simplot’s own representative testified that trial exhibit number
2017, which included a modified A201 form, was the final third contract. Thus, it
is undisputed that the third contract incorporated by reference the modified A201
3 that appeared in trial exhibit number 2017. And no party disputes the terms of the
three modified A201 forms. Each of those modified A201 forms contains the
following two sections:
§ 4.6.1 Any Claim arising out of or related to the Contract, except Claims relating to aesthetic effect and except those waived as provided for in Sections 4.3.10, 9.10.4 and 9.10.5, shall, after decision by the Architect or 30 days after submission of the Claim to the Architect, be subject to arbitration. …
§ 4.6.2 Claims not resolved by mediation shall be decided by arbitration which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect.
Simplot does not dispute that the modified version of the A201 forms (which we
have determined were incorporated by reference) contained those terms.
Rather than dispute that the modified A201 forms require arbitration, Simplot
instead argues that those forms are not what section 1.2 of the signed contracts is
referencing when it expressly incorporates “the AIA A201 … General Conditions as
modified.” Simplot seems to take the position that the “modified” A201 conditions
incorporated by section 1.2 are some unwritten set of conditions created by the
parties’ negotiations, but apparently never memorialized into a final writing.
As an initial matter, Simplot’s position is difficult to reconcile with the fact
that, for the first two contracts, Simplot itself provided a set of modified A201
conditions attached to the contracts when it sent the contracts (and attached
conditions) to Hoffman to sign. If those were not the “modified” conditions
4 referenced in the contract, then why send them with the contract? But even beyond
that, Idaho law requires that incorporated terms in a contract be both “adequately
identified” and “readily available for inspection by the parties” when the contract is
signed. City of Meridian v. Petra Inc., 299 P.3d 232, 242 (Idaho 2013) (citing
Harris, Inc. v. Foxhollow Constr. & Trucking, Inc., 264 P.3d 400, 416 (Idaho 2011)).
For the first two contracts, the modified A201 conditions that Simplot sent to
Hoffman along with the contracts to be signed easily fit those requirements.
Although there was no evidence showing that the modified A201 was transmitted
along with the third contract for signing, the undisputed evidence shows that the
modified A201, which was incorporated by reference into the third contract, also fit
those requirements. Indeed, Simplot’s representative testified that he received the
modified A201 as part of the final signed contract. In contrast, Simplot’s ambiguous
unwritten conditions clearly don’t meet the incorporation-by-reference
requirements. The written A201 forms “as modified” by the parties are the ones
referenced and incorporated by section 1.2 of the signed contracts.
The lack of ambiguity in the arbitration provisions of those written forms is
dispositive for determining whether the parties agreed to arbitrate disputes and
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Sbp Lllp v. Hoffman Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sbp-lllp-v-hoffman-construction-company-ca9-2023.