Save Our Sound OBX, Inc. v. N.C. Dep't of Transp.
This text of 324 F. Supp. 3d 597 (Save Our Sound OBX, Inc. v. N.C. Dep't of Transp.) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
LOUISE W. FLANAGAN, United States District Judge *601This matter is before the court on the parties' cross-motions for summary judgment. (DE 95, 107, 108, 115). The motions have been fully briefed, and the issues raised are ripe for ruling. For reasons noted, plaintiffs' motion is denied and defendants' and intervenor-defendants' motions are granted.
STATEMENT OF THE CASE
This action concerns the highway construction project designated in the administrative record as State Transportation Improvement Program Project No. B-2500 ("B-2500 project").1 The overall purpose the B-2500 project is to provide a reliable method of road transportation in North Carolina's outer banks through 2060 by replacing and improving a stretch of North Carolina Highway 12 ("NC-12") from the southern end of Bodie Island to the village of Rodanthe. The B-2500 project is segmented into phases. Phase I, wherein construction now is ongoing, involves construction of a new bridge to span Oregon Inlet-a short waterway that runs between Bodie and Hatteras Islands and connects the Pamlico Sound in the West with the Atlantic Ocean in the East. Phase I will serve to replace the aging Herbert C. Bonner Bridge ("Bonner Bridge"), which served as the only mode of crossing Oregon Inlet since that bridge opened in 1962.
In an earlier action brought prior to initiation of Phase I, intervenor-defendants Defenders of Wildlife and the National Wildlife Refuge Association (collectively, "conservation groups"), sued Eugene A. Conti, Jr., then-Secretary of the North Carolina Department of Transportation ("NCDOT"), and defendant NCDOT challenging a Record of Decision issued in 2010, ("2010 Phase I ROD"), which authorized construction of Phase I. Defenders of Wildlife v. North Carolina Department of Transportation,
Phase II, which has been further subdivided in Phases IIa and IIb, involves building improvements to NC-12 in two areas of the outer banks that defendant NCDOT has designated as "hot spots" where natural erosion and overwash regularly damage NC-12 requiring maintenance and road closures. Phase IIa embraces improvements in the area between the southern *602end of the Pea Island Wildlife Refuge's ("Refuge") South Pond and the northern end of the 2.1-mile section of NC-12 in the southern half of the Refuge that is not expected to be threatened by shoreline erosion prior to 2060. This area includes a breach caused by Hurricane Irene in August 2011 that temporarily opened an inlet between Pamlico Sound and the Atlantic Ocean, which inlet now is closed due to natural processes.
Phase IIb, which is the subject of this litigation, involves improvements to the area between the Emergency Ferry Dock in Rodanthe to approximately 1.8 miles north of the Refuge border. This area includes a breach in Rodanthe, also caused by Hurricane Irene, as well as the Rodanthe "S Curves Hot Spot" and two other areas identified in the 2008 Final Environmental Impact Statement ("2008 FEIS") as geologically susceptible to breaches.
On December 15, 2016, defendants NCDOT and James H. Trogdon, III ("Trogdon") (collectively, "state defendants") and defendant Federal Highway Administration ("FHWA") and John F. Sullivan, III ("Sullivan") (collectively, "federal defendants"), together with other interested agencies (collectively "the Agencies"), issued a Record of Decision ("2016 Phase IIb ROD"), which approved plans for Phase IIb. The 2016 Phase IIb ROD approves construction of a bridge that removes a section of NC-12 from the Refuge into the Pamlico Sound ("jug-handle bridge").
Plaintiffs initiated this action February 2, 2017, challenging the 2016 Phase IIb ROD under the National Environmental Policy Act ("NEPA"), Section 4(f) of the Department of Transportation Act ("Section 4(f)"), the North Carolina Environmental Policy Act, and the judicial review provisions of the Administrative Procedure Act ("APA").
The conservation groups, formerly plaintiffs in the settled Phase I litigation, moved to intervene on March 3, 2017. This court granted that unopposed motion. Plaintiffs then amended their complaint as a matter of right on March 7, 2017, abandoning their claims under North Carolina law. At the same time, plaintiffs moved for preliminary injunction, which motion this court initially stayed, and recently denied without prejudice rather than maintain indefinite stay, as the parties agreed that no ground-disturbing activities were scheduled to commence until March 2018, and further extended in the current schedule to June 6, 2018.
Federal defendants lodged the administrative record July 7, 2017, which consists of the prior administrative record underlying Phase I and additional documents generated since that time. Plaintiffs moved to compel completion of the administrative record, or, in the alternative, to compel production of agreement negotiation materials pertinent to the 2015 settlement agreement so that plaintiffs might assert them as extra-record evidence. This court denied that motion October 20, 2017. Also on October 20, 2017, plaintiffs moved for leave to file a second amended complaint, seeking to add claims arising under Section 106 of the National Historic Preservation Act ("Section 106"). On October 26, 2017, the court granted plaintiffs' request to withdraw the October 20, 2017, motion to amend the complaint and to assert, instead, a revised motion to amend. On December 5, 2017, the court granted in part the revised motion to amend allowing amendments related to a possible haul route located in the Rodanthe Historic District, but denied the motion as it pertained to claims related to a shipwreck off Pappy Lane in the Phase IIb project area. Plaintiffs moved for summary judgment on January 10, 2018. Defendants and intervenor-defendants *603cross-moved for summary judgment on February 21, 2018.
Plaintiff Save Our Sound OBX, Inc. ("Save Our Sound") is a non-profit corporation existing under the laws of North Carolina with its principal place of business in North Carolina. The individual plaintiffs are members of Save Our Sound. Each individual plaintiff claims non-economic injury arising from, among other things, regular use of the public lands, wetlands, and waters in and around the Refuge and the Rodanthe Historic District.
Defendant FHWA is a federal administrative agency within the United States Department of Transportation. Defendant Sullivan is administrator for the FHWA's North Carolina Division Office.
Free access — add to your briefcase to read the full text and ask questions with AI
LOUISE W. FLANAGAN, United States District Judge *601This matter is before the court on the parties' cross-motions for summary judgment. (DE 95, 107, 108, 115). The motions have been fully briefed, and the issues raised are ripe for ruling. For reasons noted, plaintiffs' motion is denied and defendants' and intervenor-defendants' motions are granted.
STATEMENT OF THE CASE
This action concerns the highway construction project designated in the administrative record as State Transportation Improvement Program Project No. B-2500 ("B-2500 project").1 The overall purpose the B-2500 project is to provide a reliable method of road transportation in North Carolina's outer banks through 2060 by replacing and improving a stretch of North Carolina Highway 12 ("NC-12") from the southern end of Bodie Island to the village of Rodanthe. The B-2500 project is segmented into phases. Phase I, wherein construction now is ongoing, involves construction of a new bridge to span Oregon Inlet-a short waterway that runs between Bodie and Hatteras Islands and connects the Pamlico Sound in the West with the Atlantic Ocean in the East. Phase I will serve to replace the aging Herbert C. Bonner Bridge ("Bonner Bridge"), which served as the only mode of crossing Oregon Inlet since that bridge opened in 1962.
In an earlier action brought prior to initiation of Phase I, intervenor-defendants Defenders of Wildlife and the National Wildlife Refuge Association (collectively, "conservation groups"), sued Eugene A. Conti, Jr., then-Secretary of the North Carolina Department of Transportation ("NCDOT"), and defendant NCDOT challenging a Record of Decision issued in 2010, ("2010 Phase I ROD"), which authorized construction of Phase I. Defenders of Wildlife v. North Carolina Department of Transportation,
Phase II, which has been further subdivided in Phases IIa and IIb, involves building improvements to NC-12 in two areas of the outer banks that defendant NCDOT has designated as "hot spots" where natural erosion and overwash regularly damage NC-12 requiring maintenance and road closures. Phase IIa embraces improvements in the area between the southern *602end of the Pea Island Wildlife Refuge's ("Refuge") South Pond and the northern end of the 2.1-mile section of NC-12 in the southern half of the Refuge that is not expected to be threatened by shoreline erosion prior to 2060. This area includes a breach caused by Hurricane Irene in August 2011 that temporarily opened an inlet between Pamlico Sound and the Atlantic Ocean, which inlet now is closed due to natural processes.
Phase IIb, which is the subject of this litigation, involves improvements to the area between the Emergency Ferry Dock in Rodanthe to approximately 1.8 miles north of the Refuge border. This area includes a breach in Rodanthe, also caused by Hurricane Irene, as well as the Rodanthe "S Curves Hot Spot" and two other areas identified in the 2008 Final Environmental Impact Statement ("2008 FEIS") as geologically susceptible to breaches.
On December 15, 2016, defendants NCDOT and James H. Trogdon, III ("Trogdon") (collectively, "state defendants") and defendant Federal Highway Administration ("FHWA") and John F. Sullivan, III ("Sullivan") (collectively, "federal defendants"), together with other interested agencies (collectively "the Agencies"), issued a Record of Decision ("2016 Phase IIb ROD"), which approved plans for Phase IIb. The 2016 Phase IIb ROD approves construction of a bridge that removes a section of NC-12 from the Refuge into the Pamlico Sound ("jug-handle bridge").
Plaintiffs initiated this action February 2, 2017, challenging the 2016 Phase IIb ROD under the National Environmental Policy Act ("NEPA"), Section 4(f) of the Department of Transportation Act ("Section 4(f)"), the North Carolina Environmental Policy Act, and the judicial review provisions of the Administrative Procedure Act ("APA").
The conservation groups, formerly plaintiffs in the settled Phase I litigation, moved to intervene on March 3, 2017. This court granted that unopposed motion. Plaintiffs then amended their complaint as a matter of right on March 7, 2017, abandoning their claims under North Carolina law. At the same time, plaintiffs moved for preliminary injunction, which motion this court initially stayed, and recently denied without prejudice rather than maintain indefinite stay, as the parties agreed that no ground-disturbing activities were scheduled to commence until March 2018, and further extended in the current schedule to June 6, 2018.
Federal defendants lodged the administrative record July 7, 2017, which consists of the prior administrative record underlying Phase I and additional documents generated since that time. Plaintiffs moved to compel completion of the administrative record, or, in the alternative, to compel production of agreement negotiation materials pertinent to the 2015 settlement agreement so that plaintiffs might assert them as extra-record evidence. This court denied that motion October 20, 2017. Also on October 20, 2017, plaintiffs moved for leave to file a second amended complaint, seeking to add claims arising under Section 106 of the National Historic Preservation Act ("Section 106"). On October 26, 2017, the court granted plaintiffs' request to withdraw the October 20, 2017, motion to amend the complaint and to assert, instead, a revised motion to amend. On December 5, 2017, the court granted in part the revised motion to amend allowing amendments related to a possible haul route located in the Rodanthe Historic District, but denied the motion as it pertained to claims related to a shipwreck off Pappy Lane in the Phase IIb project area. Plaintiffs moved for summary judgment on January 10, 2018. Defendants and intervenor-defendants *603cross-moved for summary judgment on February 21, 2018.
Plaintiff Save Our Sound OBX, Inc. ("Save Our Sound") is a non-profit corporation existing under the laws of North Carolina with its principal place of business in North Carolina. The individual plaintiffs are members of Save Our Sound. Each individual plaintiff claims non-economic injury arising from, among other things, regular use of the public lands, wetlands, and waters in and around the Refuge and the Rodanthe Historic District.
Defendant FHWA is a federal administrative agency within the United States Department of Transportation. Defendant Sullivan is administrator for the FHWA's North Carolina Division Office. FHWA administers various statutes pertaining to highway transportation, including statutes governing highway construction projects eligible for federal funding, projects involving construction over protected wildlife preserves, and environmental review of such projects pursuant to NEPA, Section 4(f), and Section 106.
Defendant NCDOT is a North Carolina administrative agency with authority over highway construction within North Carolina. Defendant Trogdon is NCDOT's Secretary. NCDOT is the state transportation department with responsibility to submit to the Secretary of Transportation any project requiring the Secretary's approval. For purposes of NEPA, FHWA and NCDOT are joint lead agencies, which designation, under pertinent federal regulations, charges FHWA and NCDOT with responsibility to supervise preparation of any environmental impact statement required under NEPA.
Plaintiffs contend that the Agencies approved construction of the jug-handle bridge without appropriate consideration of environmental consequences under NEPA, feasible alternatives under Section 4(f), and effects on historically significant property under Section 106. Plaintiffs seek judicial review pursuant to the APA.
Plaintiffs moved for summary judgment January 10, 2018. In support, plaintiffs rely on the administrative record, declarations from each individual plaintiff, and an e-mail transmission written by counsel for state defendants John Batherson. Each defendant cross-moved for summary judgment February 21, 2018. In support of their motions, defendants rely also on the administrative record.
STATEMENT OF THE UNDISPUTED FACTS
The undisputed facts may be summarized as follows. NC-12 runs north-to-south along the outer banks of North Carolina and connects Bodie Island in the North with Rodanthe in the South, and continues along the Outer Banks. AR 58326.2 The southern end of Bonner Bridge lies in the Refuge, which spans from the northern tip of Hatteras Island to Rodanthe.
FHWA and NCDOT formed a "NEPA/Section 404 Merger Team," ("Merger Team") consisting of representatives from FHWA, NCDOT, the U.S. Fish and Wildlife Service, the U.S. Army Corps of Engineers ("USACE"), the U.S. Environmental Protection Agency, the National Marine Fisheries Service, the National Park Service, the North Carolina Department of Cultural Resources, the North Carolina Wildlife Resources Commission, the North Carolina Department of Environmental and Natural Resources ("NCDENR")-Division of Water Quality, the NCDENR-Division of Coastal Management, and the NCDENR-Division of Marine Fisheries. RD 28988. Pursuant to a Memorandum of Understanding executed by the members of the Merger Team, once a member indicates "concurrence" at a given point in the overall project, that member of the Merger Team must abide by decision subject to concurrence absent circumstances warranting reevaluation. RD 16644-50.
In September 2008, the 2008 FEIS issued, which document included a Final Section 4(f) Evaluation, AR 58795, addressed seven alternatives plans for improvements to NC-12, and identified the "Parallel Bridge Corridor with Phased Approach/Rodanthe Bridge" as the preferred alternative. AR 58280-81. The 2008 FEIS assessed a proposal termed the Road North/Bridge South alternative that included a bridge in Pamlico Sound near Rodanthe in the current Phase IIb area, although the alignment of that bridge was different than the jug-handle bridge now under review. AR 58277. Also among the alternatives selected for detailed study were proposals involving beach nourishment and beach nourishment combined with a bridge within the existing NC-12 easement. The 2008 FEIS's analysis pertaining to beach nourishment was conducted in light of shoreline erosion projections based on modeling completed in 2004. AR 58277-78.
In October 2009, a Revised Final Section 4(f) evaluation issued, AR 75239, which added an alternative titled the "Parallel Bridge Corridor with NC-12 Transportation Management Plan." AR 75244. This alternative contemplates a phased approach to the overall B-2500 project with mixing and matching of components borrowed from other alternatives previously identified in the 2008 FEIS.
In August 2011, Hurricane Irene damaged NC-12 in the Rodanthe S Curves and within the Refuge approximately six miles south of Oregon Inlet, creating the Pea Island Inlet. RD 29249. In February 2013, an Environmental Assessment ("2013 Phase IIa EA") issued to account for these environmental changes.
*605As of issuance of the Phase IIa EA, improvements in the area around the Pea Island Inlet were designated "Phase IIa," RD 29247, while improvements near northern Rodanthe were designated "Phase IIb." RD 29248. The foregoing alternative for Phase IIa would have provided a long-term bridge over hot spots on Pea Island through 2060; however, it was not constructed for reasons described in more detail below.
In December 2013, the Agencies issued an Environmental Assessment pertinent to the Phase IIb area in northern Rodanthe ("2013 Phase IIb EA"), which updated previous NEPA documentation. RD 17805. The 2013 Phase IIb EA addresses plans to implement long-term improvements to NC-12 along the S Curves and in areas near Rodanthe damaged by Hurricane Irene. RD 17823. The 2013 Phase IIb EA identified four alternatives consisting of (1) the "Bridge on New Location [ (also, "jug-handle bridge") ]; (2) an "easement bridge" within the existing NC-12 easement ("easement bridge"); (3) beach nourishment; and (4) beach nourishment combined with a bridge within the existing easement. RD 17829. The latter two options were eliminated from detailed study at a Merger Team meeting held November 14, 2012. RD 17834. Thus, only the former options were assessed in the 2013 Phase IIb EA in detail, and the easement bridge was identified as the preferred alternative. RD 17849.
Neither the jug-handle bridge nor the easement bridge studied in the 2013 Phase IIb EA were entirely new alternatives. The jug-handle bridge assessed in the 2013 Phase IIb EA builds upon and incorporates changes to "the Bridge South component of the Road North/Bridge South Alternative that was assessed in the 2010 [Phase I] EA." RD 11573. In turn, the Road North/Bridge South alternative discussed in the 2010 Phase I EA constitutes a modified and more detailed version of the Road North/Bridge South alternative studied in the 2008 FEIS. AR 83408-08 ("Several modifications were made to the detailed study alternatives ... since the release of the [2008] FEIS ... These changes are: ... [m]odifications to the conceptual designs ... for the Road North/Bridge South [and other] alternatives."). Similarly, the easement bridge assessed in the 2013 Phase IIb EA incorporates "refinements from the Phased Approach/Rodanthe Bridge Alternative assessed in the 2008 FEIS and 2010 EA." RD 11574. In this manner, both alternatives assessed in the 2013 Phase IIb EA incorporate analysis from earlier NEPA documentation and further develop the record pertinent to those alternatives.
Following release of the 2013 Phase IIb EA, the Merger Team held a series of public meetings to "obtain public input on long-term improvements to NC 12 ...." RD 11789. The Merger Team accepted written comments. RD 11790. Following the comment period, NCDOT developed two new possible alignments for the Bridge on New Location Alternative designed to avoid areas of dense submerged aquatic vegetation in the southern half of the project area. RD 16946-47. Each alignment is described in the record as "nearly identical" to the alignment studied in the 2013 Phase IIb EA. RD 16947. These two new alignments are depicted below alongside the alignment identified in the 2013 Phase IIb EA and the original "2010 Bridge South" alignment identified in the 2008 FEIS:
*606RD 23455.
At a February 2014 meeting, National Marine Fisheries Service agreed that the proposed new alignment was preferable to the 2013 alignment, but requested more information regarding submerged aquatic vegetation. RD 16947. The proposed new alignments were presented at a March 6, 2014, Merger Team meeting. RD 14273. During that meeting, the Merger Team concurred that the jug-handle bridge and easement bridge would be evaluated further as possible alternatives for Phase IIb. RD 14278.
Also during 2014, defendants FHWA and NCDOT litigated the conservation groups' challenge to the 2010 Phase I ROD and related documents. See Defenders of Wildlife v. N.C. Dep't. of Transp., 2:11-cv-35-FL (E.D.N.C.). The conservation groups objected to two key components of the B-2500 project. First, the conservation groups objected to segmentation of the B-2500 project into phases, contending that defendants should have undertaken to plan and analyze environmental effects of the entire B-2500 project prior to any construction activity. See
*607The Fourth Circuit rejected the conservation groups' challenge to defendants' decision to plan the B-2500 project in phases. Defenders of Wildlife,
The parties to that action settled April 30, 2015. (DE 91-1). Under the terms of the 2015 settlement agreement, the conservation groups agreed to take dismissal of Defenders of Wildlife, which result allowed defendants to begin construction of a replacement for Bonner Bridge. (DE 96-1 ¶ 1.h). In exchange, defendants made two main concessions regarding later phases of the B-2500 project. First, defendants agreed to rescind the contract for Phase IIa, which, as noted, contemplated construction of a bridge, permanent through 2060, over the Pea Island Inlet and associated hot spots on Pea Island, and, instead, enter a contract to construct an interim bridge for the Phase IIa area. (Id. ¶ 1.a). The 2015 settlement agreement required that any interim solution for Phase IIa be designed to leave open possibility that NC-12 eventually will be moved outside the Refuge completely, with relevant sections relocated to a bridge in Pamlico Sound. (Id. ¶ 3.a).
Second, the 2015 settlement agreement provided that NCDOT must identify the jug-handle bridge "as its preferred alternative and seek Merger Team Concurrence ...." (Id. ¶ 1.c). The agreement provided also that "[n]othing in this Agreement requires or should be interpreted to predetermine the choice of the Phase IIb [jug-handle bridge] as the Selected Alternative." (Id. ). The 2015 settlement agreement further required that NCDENR, Division of Coastal Management "provide a written statement of its support and preference" and "otherwise ... use best efforts to help NCDOT attempt to secure Merger Team concurrence." (Id. ¶ 1.e). In the event that the Merger Team reached concurrence and concluded that the jug-handle bridge is the Least Environmentally Damaging Practicable Alternative ("LEDPA"), the 2015 settlement agreement required defendants FHWA and NCDOT to "promptly revise" the 2013 Phase IIb EA and Section 4(f) Evaluation to identify the Bridge on New Location as the preferred alternative, and to "[p]ropose to identify the Phase IIb ... Alternative as the 'least overall harm' alternative[.]" (Id. ¶ 3.c.i).
On June 17, 2015, the Merger Team identified the 2014B Bridge on New Location as the LEDPA. RD 16982. On May 24, 2016, FHWA and NCDOT issued the 2016 Revised Phase IIb EA, which document provided updates regarding any changed environmental circumstances occurring since issuance of the 2013 Phase IIb EA. RD 28978. The 2016 Revised Phase IIb EA addressed the same alternatives as the 2013 Phase IIb EA, and included also discussion of the two additional alignments for the Bridge on New Location alternative introduced following the 2013 Phase IIb EA comment period. RD 28983-86. On December 15, 2016, FHWA, with the Merger Team's concurrence, issued the 2016 Phase IIb ROD approving the Bridge on New Location 2014B alignment as the selected alternative. RD 28979-80. This action followed.
*608DISCUSSION
A. Standards of Review
1. Summary Judgment
Summary judgment is appropriate where "the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). On cross-motions for summary judgment, the court "consider[s] each motion separately on its own merits to determine whether [any] of the parties deserves judgment as a matter of law." Defs. ofWildlife,
Once the moving party has met its burden, the non-moving party must then "come forward with specific facts showing that there is a genuine issue for trial." Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp.,
"[A]t the summary judgment stage the [court's] function is not [itself] to weigh the evidence and determine the truth of the matter but to determine whether there is a genuine issue for trial."
Nevertheless, "permissible inferences must still be within the range of reasonable probability, ... and it is the duty of the court to withdraw the case from the [factfinder] when the necessary inference is so tenuous that it rests merely upon speculation and conjecture." Lovelace v. Sherwin-Williams Co.,
2. APA
"A person ... adversely affected by agency action within the meaning of a relevant statute[,]"
3. NEPA
NEPA "establishes a national policy to encourage productive and enjoyable harmony between man and his environment, and was intended to reduce or eliminate environmental damage and to promote the understanding of the ecological systems and natural resources important to the United States." Defs. ofWildlife,
NEPA mandates "a set of 'action-forcing' procedures that require that agencies take a 'hard look' at environmental consequences, ... and that provide for broad dissemination of relevant environmental information."
For every major federal action significantly affecting the quality of the human environment, the agency involved must prepare an Environmental Impact Statement ("EIS") "that discloses and evaluates, among other things, the environmental impact of the proposed action, unavoidable adverse effects of the proposed action, and alternatives to the proposed action."
Comparative evaluation of alternatives "is the heart of the environmental impact statement ..." Defs. ofWildlife,
"NEPA does not require agencies to adopt any particular internal decisionmaking structure[,] [b]ut NEPA does require agencies to follow a particular decisionmaking process." Defs. ofWildlife,
4. Section 4(f)
Section 4(f) "imposes substantive restraints on an agency's action." Defs. ofWildlife,
Therefore, Section 4(f) property "may not be put to non-park uses unless there is no feasible and prudent alternative to the non-park use of the land." Defs. ofWildlife,
5. Section 106
Congress enacted the National Historic Preservation Act ("NHPA") to "foster conditions under which our modern society and our historic property can exist in productive harmony."
B. Analysis
Plaintiffs assert various challenges to the 2016 Phase IIb ROD consisting of defendants' failure to consider effects of transporting construction materials to the construction site, failure to give sufficient consideration to environmental effects on the Refuge, failure to consider socio-economic effects of Phase IIb on the Rodanthe area, and premature elimination of options involving beach nourishment and failure to consider new information regarding the same. Plaintiffs contend also that the 2015 settlement agreement unlawfully predetermined the outcome of the administrative process pertinent to Phase IIb. The court addresses each claim in turn.
1. Haul Road Claims
Plaintiffs contend that defendants failed to consider environmental effects of transporting construction materials to the Phase IIb construction site, in violation of NEPA, Section 4(f), and Section 106.
The 2016 Phase IIb ROD states that "[c]onstruction activity would be primarily confined to the existing or new easement/right-of-way except at the northern end (in the Refuge), where a [0.63 acre] temporary construction easement east of the existing easement would be needed for a temporary traffic maintenance road to take traffic around the bridge approach." RD 28992. The 2016 Phase IIb ROD discusses "construction impacts" further in section 5.8. RD 29011-12. That section *611states that construction of the selected alternative will be governed by NCDOT's Standard Specifications for Roads and Structures and the American Association of State Highway and Transportation Officials' LRFD Bridge Design Specifications.
The foregoing is sufficient to rebut plaintiffs' suggestion that the Agencies failed entirely to consider the environmental impacts of construction and hauling. However, where the Phase IIb ROD does not undertake to compare environmental impacts due to construction as between alternatives under consideration, and where comparative analysis is the heart of NEPA review,
As noted in the 2016 Phase IIb ROD, the Revised 2016 Phase IIb EA states that construction activity for the jug-handle bridge "would be primarily confined to the existing or new easement/right-of-way except at the north end (in the Refuge), where a temporary construction easement east of the existing easement would be needed for a temporary traffic maintenance road to take traffic around the bridge approach. This temporary easement would be approximately 0.63 acre in size." RD 23465. Construction would last three to three and a half years.
Next, the 2016 Revised Phase IIb EA "updates the impact discussion presented in Chapter 4 of the 2008 FEIS and Section 2.3.3 of the 2010 EA" focusing on "updates relevant to Phase IIb of the Bonner Bridge Replacement Project (B-2500)." RD 23484. The 2016 Revised Phase IIb EA opens its analysis by distinguishing "direct impacts," consisting of community impacts, visual impacts, cultural resource impacts, parks and recreation impacts, natural systems impacts, noise impacts, and air quality impacts, from "indirect and cumulative impacts," which relate to anticipated effects on land development, potential loss of natural features, and other cumulative effects upon the project as whole.
*612RD 23484-85; see also
Following the foregoing preliminary observations, the 2016 Revised Phase IIb EA discusses updated direct impacts associated with construction, operation, and maintenance of the Phase IIb project for each category of direct impact in turn, and, within discussion of each category, the 2016 Revised Phase IIb notes differences, if any, arising from the selected alternative relative to the easement bridge alternative. See RD 23484-528. The section on construction noise impacts discusses hauling, noting that environmental effects related to noise would be greater should the Agencies build the easement bridge alternative, as that alternative requires a greater amount of construction in the downtown Rodanthe area where more humans are likely to pass in earshot of the project. RD 23523. That section notes also that noise impacts may be mitigated by selection of haul road locations.
The 2016 Revised Phase IIb EA hinges its assessment on analysis contained in the 2008 FEIS with assessment that the jug-handle bridge and the easement bridge alternatives "would be similar to what was defined in the 2008 FEIS as the Bridge South component of the Road North/Bridge South and as the Phased Approach/Rodanthe Bridge alternatives, respectively." RD 23484. Plaintiffs disagree with the Agencies' conclusion that the jug-handle bridge and easement bridge are similar to their counterparts in the 2008 FEIS; however, based upon diagrams of proposed paths and accompanying analysis of the differences between counterpart alternatives, the Agencies' assessments that alternatives presented in the 2016 Revised Phase IIb EA are similar in relevant respects to alternatives considered in the 2008 FEIS cannot be deemed arbitrary.3 See RD 23455 (diagram of jug-handle bride with Bridge South); RD 23456 (describing development of easement bridge as refinement of Phased Approach/Rodanthe Bridge alternative); RD 23485-86 (similarly of cumulative effects on habitat loss); RD 23488 (reduced takings required relative to those identified in the 2010 EA); RD 23499 (similar use of Refuge land use); RD 23499-503 (similar effects on recreational uses); RD 23508 (similar effects on biotic communities); RD 23518-20 (similar noise impacts). Accordingly, the court now turns its address to any comparative analysis *613of the Road North/Bridge South and Phased Approach/Rodanthe Bridge alternatives considered in the 2008 FEIS as an additional source of analysis pertinent to the 2016 Phase IIb ROD.
Section 2.10.1.3 of the 2008 FEIS discusses "Construction" of the Oregon Inlet bridge and includes discussion of construction methods. That section states, "[u]nless specified, the construction techniques of the Oregon Inlet bridge would apply to all five NC 12 Maintenance Alternatives." AR 58455. The five NC-12 Maintenance Alternatives include the Road North/Bridge South and Phased Approach/Rodanthe Bridge alternatives described above.
Construction of an Oregon Inlet bridge in the Parallel Bridge Corridor would involve primarily the assembly of large precast concrete units. Precast units, weighing up to 100 tons (90.7 metric tons), would be manufactured at a precast plant and shipped to the construction site.... Materials for the footings would be delivered by truck and/or barge. North Carolina highway regulations include a maximum allowable shipping length; parts exceeding this length would be shipped by barge. The least cost method for shipping all parts probably would be by barge.
AR 58455. Additionally, section 2.10.1.3 discusses the nature of a haul road that would run along the west side of the Oregon Inlet bridge, describing in detail its dimensions and method of construction. See
Based upon the foregoing, the Agencies' considered environmental effects of construction and transportation of construction materials. The record as summarized above supports conclusion that the Agencies comparatively evaluated effect of construction based upon assessment that methods of construction would be the same regardless of which alternative was chosen.
The 2016 Phase IIb ROD does not expressly compare environmental effects of alternatives in terms of effects attributable to hauling construction materials. However, NEPA does not require the Agencies to embark on a detailed analysis of a possible point of comparison where there is no basis to conclude that alternatives under consideration differ with respect to any environmental tradeoffs due to that point of comparison.
This analysis is bolstered by observation that NEPA's text nowhere identifies "hauling" as a category of analysis that agencies must consider separately from other environmental impact analysis. Rather, the only legal basis for plaintiffs' challenge to defendants' consideration of hauling impacts is the general principle of administrative law that agency action must not be arbitrary and capricious. As part of the APA's injunction against arbitrary administrative action, courts must not uphold a decision that "fails entirely to consider an important aspect of the problem." Defs.Of Wildlife,
Plaintiffs argue that two construction diagrams included in the administrative record demonstrate that Phase IIb involves construction of haul roads through the Rodanthe Historic District and adjacent wetlands. RD 26, 27. The 2016 Phase IIb ROD makes no reference to these diagrams; therefore, the Agencies were not required to analyze the diagrams as if they embodied the Agencies' construction plans. See
Plaintiffs argue further that, even if particular diagrams in the administrative record do not represent the agencies' plans for hauling construction materials, the agencies failed to consider the environmental impacts of hauling, whatever the hauling plan might be. However, this argument fails where, as noted above, the Agencies did consider hauling as part of analysis of construction methods. AR 58455. To be sure, the administrative record does not disclose the precise location of haul routes; however, it notes that all construction will remain with the existing *615NC-12 easement except where a temporary construction easement is required in north, RD 28992, that haul roads will not cross submerged aquatic vegetation, RD 23422, and that land used for haul roads will be restored after construction is complete. RD 29012.
Where the Fourth Circuit has held previously that challenges based upon missing information must not infringe upon agencies' discretion to determine what information is important to include in NEPA documents, including the "location and distance of access roads" to a construction site, the court will not second guess the Agencies' decision to omit the same information here. Webster v. U.S. Dept. of Agriculture,
2. Pea Island Wildlife Refuge Claims
Plaintiffs next contend that the Agencies failed to analyze environmental effects of the Phase IIb alternatives on the Refuge "as a refuge."
Sections 5.4.1.1 through 5.4.1.3 of the 2016 Revised Phase IIb EA set forth a number of administrative findings regarding environmental effects of the Phase IIb alternatives on the Refuge. RD 17902-05. Section 5.4.1.1 compares environmental effects on the Refuge in terms of "permanent incorporation of land" finding that while the easement bridge alternative "would be confined to the existing NC 12 easement" with no resulting permanent incorporation of land, the jug-handle bridge alternative would permanently incorporate 2.79 acres of Refuge land to accommodate that portion of the jug-handle bridge in the Northern end of the Refuge that turns toward Pamlico Sound to connect existing NC-12 with the new bridge over Pamlico Sound. RD 17902.
Section 5.4.1.2 discusses "temporary occupancy" in reference to Refuge land that will be used during the construction process to facilitate construction. RD 17902-04. The 2016 Revised Phase IIb EA concludes that, subject to agreement by officials with jurisdiction over management of the Refuge, namely, United States Fish and Wildlife Service and the North Carolina State Historic Preservation Officer, any temporary occupancies involved in either Phase IIb alternative would not constitute a Section 4(f) use, and plaintiffs present to the court no challenge to this conclusion. See 23 C.F.R. 774.13(d) ; RD 17902-04. Nonetheless, section 5.4.1.2 observes that while the easement bridge alternative would require a temporary construction easement 2.06 acres in area, the jug-handle bridge alternative would require a smaller 0.63 acre temporary construction easement. RD 17902.
Section 5.4.1.3 of the 2016 Revised Phase IIb EA discusses constructive uses of the Refuge that would result from construction of the easement alternative. RD 17904-05. That section observes also that where the jug-handle bridge alternative would permanently incorporate Refuge lands, there is no need to analyze that alternative as presenting a constructive use.
*616Section 5.6 of the 2016 Revised Phase IIb EA embodies the agencies' "Least Harm Analysis" wherein the Agencies conclude that the jug-handle bridge would cause the least overall harm to the Refuge. RD 17914-15. The Least Harm Analysis notes that both alternatives meet the needs of the project, RD 17911, use the same Section 4(f) property,
Finally, and arguably the most salient feature of the Least Harm Analysis, the Agencies conclude that while the jug-handle bridge alternative would incorporate permanently 2.79 acres of Refuge land, it would also return and restore 19.27 acres of Refuge land by removing the existing road that now traverses the Refuge, resulting in a net gain of 16.48 acres of restored Refuge land.
Plaintiffs argue that where the 2016 Revised Phase IIb EA notes that, if the jug-handle bridge is built, "[p]ermanent loss of wildlife habitat in the Refuge would be 0.01 acre of pile impact (0.30 acre if assuming the larger pile cap area)[,]" RD 11639, that this analysis is deficient because while it analyzes effects on the Refuge in terms of land area consumed, it fails to assess directly the effects of such loss of land on the wildlife that the Refuge is intended to protect. However, NEPA permits the Agencies discretion to make policy choices regarding the kinds of information to be viewed as environmentally significant. Hughes II,
3. Rodanthe Socio-Economic Effects Claims
Plaintiffs contend that defendants failed to consider socio-economic effects of *617the alternatives under consideration on the community of Rodanthe as a distinct unit, including effects upon property values, rental income streams, and kiteboarding tourism in the Rodanthe community.
Under CEQ regulations, "[w]hen an environmental impact statement is prepared and economic or social and natural or physical environmental effects are interrelated, then the environmental impact statement will discuss all of these effects on the human environment." 40 C.F.R. 1508.14. The Phase IIb ROD discusses impacts on "Recreational Use" with reference to analysis set forth in the 2008 FEIS. RD 28997. The 2016 Phase IIb ROD states "[l]ike the 2010 Bridge South ... the Selected Alternative would create an offshore obstruction for recreational users of the Pamlico Sound, such as wind surfers, kayakers, and kite boarders as the bridge moves out from shore in Rodanthe."
Similarly, the 2008 FEIS states that, for recreational users of Pamlico Sound, including "wind surfers, kayakers, and kite boarders," AR 57549, the Road North/Bridge South alternative, which, as noted, parallels the jug-handle bridge alternative, "would place an obstruction in the Sound as the Rodanthe area bridge moves out from shore in the Refuge to a point about 1,500 feet (480 meters) west of Hatteras Island .... Because of this bridge's close proximity to the shore, the impacts to recreational users would be more substantial. The Nourishment and the two Phased Approach alternatives would not affect the use of Pamlico Sound." AR 57550. In addition, the 2008 FEIS notes that, despite negative effects that the jug-handle bridge may have upon the activities of recreational users, "[n]umerous additional opportunities exist for these activities ..."
The 2016 Revised IIb EA echos and updates findings in the 2008 FEIS, noting that the selected jug-handle bridge would lie approximately 1,050 to 1400 feet from the island, leaving 356 acres of open water between bridge and shore. RD 23549. In response to comments to the 2016 Revised Phase IIb EA, the Agencies considered effects on kiteboarding and noted that "[w]ith the [s]elected [a]lternative the primary watersport recreational impact is expected to be kiteboarding." RD 29160. In this manner, it cannot be said that the Agencies failed to consider environmental effects on the Phase IIb project pertaining to recreational activities, including kiteboarding.
With respect to economic factors, Section 4.2.1 of the Revised Section 4(f) evaluation discusses "community impacts associated with the Phase IIb detailed study alternatives since the 2008 FEIS, as updated in the 2010 EA." RD 24153. That section notes the number of homes and businesses that would require relocation for both alternatives under consideration, concluding that the easement bridge would require relocating six homes and seven businesses, while the jug-handle bridge would require relocating two homes and five businesses. RD 21453. With respect to the Rodanthe area in particular, the studies determine that there would be minimal economic impact from displacement, with exception of possible relocation of the Liberty Service Station/Island Convenience Store, which relocation would be necessary only if the easement bridge alternative were selected. RD 24154.
The 2008 FEIS assesses economic impacts of the B-2500 project in Section 4.1.5, including economic effects of Parallel Bridge Corridor alternatives selected for detailed study, of which group both the Road North/Bridge South and Phased Approach/Rodanthe Bridge alternatives are *618members. AR 57511-22. Assessment of economic effects in section 4.1.5 embraces "displacement of businesses, lost tax base for Dare County associated with the land for the project right-of-way in Rodanthe, ... and the risk of a new breach opening within the Refuge, as well as the economic impact of such a breach." AR 57511. That section notes that the Phased Approach/Rodanthe Bridge would displace the Liberty service station, while the Road North/Bridge South alternative would displace no businesses. AR 57512. Regarding the Dare County tax base, section 4.1.5 concludes that "[w]ith the exception of the Parallel Bridge Corridor with Nourishment Alternative, the tax base of Dare County would be reduced by all of the replacement bridge corridor alternatives, because the land and building purchased for the project right-of-way in Rodanthe would be removed from the county tax base." AR 57512. The analysis notes also that any tax revenue lost would be only a small percentage of the overall tax base for Dare County, and the analysis proceeds to provide quantitative estimates of lost tax revenue for the various options.
Finally, section 4.1.5.3 analyzes "effect of changed access" which section addresses economic effects attributable to loss of paved road access to certain areas within Dare County caused by various alternatives. AR 57513-17. The analysis notes "[t]he Parallel Bridge Corridor would retain paved road access in the Refuge, although that access would be limited to three locations with the All Bridge Alternative and two locations with the two Phased Approach alternatives ..." AR 57513. In addition, the assessment discusses economic effects on Dare County of eliminating paved road access north of Rodanthe, finding that "[o]n average, these losses are not likely to have a major economic impact on the Outer Banks/Dare County area."
The foregoing analyses of effects on recreation and economic effects in the Dare County area attributable to the B-2500 project constitute discharge of the Agencies' duty under
Moreover, as noted in the 2008 FEIS, there are six other communities in the area south of the Refuge, and the Agencies did not act arbitrarily in considering their interests together, or in assessing that changed access to a certain recreational or economic activity would result in an economic "loss" only if the activity were otherwise unavailable in Dare County. See RD 23613 ("The economic study team concluded that a loss of tourism dollars would occur if a road that provides direct access to a recreational resource was eliminated, and this resource was unique (not available anywhere else in Dare County.)"); RD 23500 ("As indicated in the 2008 FEIS study, the key question in terms of the *619economic impact to the Outer Banks economy is what resource/activity is lost, or to which access is reduced or lost, and whether there is no other location on the Outer Banks to participate in the activity.") ). Where policy decisions, including decision as to the geographic scope of a relevant economic "area," are within the Agencies discretion to determine methodology to measure environmental harm, plaintiffs' challenge to the Agencies' decision to measure economic effects at the county level fails. See Hughes II,
4. Beach Nourishment/New Information Claims
Plaintiffs contend that defendants violated NEPA by failing to reevaluate beach nourishment as an alternative in light of new information obtained following an emergency beach nourishment project undertaken in 2014 to mitigate harm caused by Hurricane Sandy. See RD 23478.
When new information arises after preparation of an EIS, agencies may be required to produce a supplemental EIS to explore that information and incorporate it into the decision-making process. See Marsh v. Oregon Nat. Res. Council,
FHWA regulations provide additional guidelines for NEPA compliance in actions under FHWA jurisdiction.
The Agencies eliminated Phase IIb alternatives involving beach nourishment at a meeting held November 14, 2012. RD 17834. As part of the 2016 Phase IIb ROD, the Agencies responded to comments to the 2016 Revised Phase IIb EA submitted in support of beach nourishment. RD 29113-29212. The Agencies offered seven reasons for decision to reject commenters' suggestions that beach nourishment warranted reconsideration, consisting of: (1) nourishment would not adequately protect NC-12 from potential future breaches/inlets; (2) regular nourishment would not ensure that a severe storm would not break down a part of the dune causing overwash to cover NC-12 with sand or damage it; (3) nourishment would not allow natural island processes to occur in the Refuge; (4) a long-term nourishment plan is not likely to be found compatible with Refuge's mission; (5) high erosion may require importation of more sand than is available; (6) emergency nourishment accomplished in 2014 was premised upon *620nourishment as a temporary solution to an isolated problem, and, thus, analysis pertinent to that project is irrelevant to reasonableness of nourishment as a long term solution; and (7) nourishment is too costly. RD 29205-08.
Plaintiffs advance specific challenge to two of the foregoing rationales for rejecting beach nourishment alternatives. First, plaintiffs dispute the Agencies' conclusion that insufficient sand is available to meet the needs of nourishment alternatives on grounds that the emergency beach nourishment project in 2014 revealed a previously unknown source of sand and that updated erosion projections demonstrate that less sand is needed to accomplish beach nourishment through 2060 than originally thought. Second, plaintiffs contend that, when estimating costs of beach nourishment, the Agencies' failure to discount future costs to present value was arbitrary.
Plaintiffs' challenges fail from the outset because they do not embrace all the reasons that the Agencies' deemed beach nourishment inadequate to meet the needs of the B-2500 project. That is, where one of the stated purposes of the B-2500 project is to provide a transportation solution that minimizes NC-12 closures and associated losses due to shoreline erosion, overwash, and breaches and inlets, RD 28976, where nourishment options leave NC-12 subject to breaching and overwash resulting in road closures, RD 29140, the Agencies did not act arbitrarily in holding nourishment options inadequate relative to the goals of the B-2500 project. See Motor Vehicle Mfrs.,
As a separate and independent basis, the Agencies eliminated beach nourishment options on the ground that where they interfere with natural erosion in the Pea Island, such options are unlikely to be consistent with the purposes of the Refuge. RD 28628. Each of the foregoing considerations is supported by substantial evidence in the record and constitutes sufficient reason to conclude that beach nourishment is not an adequate solution in light of the goals of the B-2500 project. See
Plaintiffs advance a number of arguments that factors other than sand suitability, shoreline-erosion projections, and cost do not provide sufficient independent support to the Agencies' decision to eliminate beach nourishment. First, plaintiffs argue that minutes for a December 15, 2011 meeting where beach nourishment was discussed indicate that uncertainties regarding sand sources and shoreline-erosion projections were the main reasons for eliminating nourishment options. (RD 2888). However, this argument is inapposite where the 2016 Phase IIb ROD is the *621document that embodies the Agencies' decision, and, as such, it is the reasoning set forth in that document that is subject to review under § 704 of the APA (judicial review available for "final agency action"). Where, as described above, the 2016 Phase IIb ROD identifies independently sufficient reasons for elimination of beach nourishment other than uncertainties regarding sand suitability and erosion projections, plaintiffs' contrary argument fails.
Second, plaintiffs argue that changes in shoreline erosion projections undermine the Agencies' conclusion that the easement bridge and jug-handle bridge alternatives protect NC-12 from breaches while nourishment options do not. Specifically, plaintiffs argue that "[g]iven that the projected rate of erosion has been significantly reduced, RD 23478; RD 11576; RD 23459, it stands to reason that the S Curves vulnerability to breaches and inlets has been reduced." (DE 120 at 40-41). Although plaintiffs provide support in the administrative record for the proposition that updated shoreline erosion projections predict less erosion, plaintiffs' provide no support for any inference that susceptibility to breaching is a function of erosion rates. Indeed, the Agencies note expressly that storms, not gradual erosion, often cause breaches. RD 29140. Therefore, plaintiffs' arguments that breaches might be less likely under updated erosion projections do not find support in the administrative record. Thus, the Agencies did not act arbitrarily in reaching conclusion that a bridge over or around areas subject to breaching meets the needs of the B-2500 project while nourishment options do not. See
Third, plaintiffs object to the Agencies' conclusion that nourishment would not allow natural island processes to occur and, thus, likely is incompatible with the Refuge's purposes. Specifically, plaintiffs argue that the Agencies' apparent preference to promote "natural processes" fails to distinguish any alternative where any artificial bridge or road requires an unnatural use of land. However, this argument fails where the record discloses that the Agencies' reference to "natural processes," in this context, means "natural erosion" and related processes, which beach nourishment would bring to halt. See AR 58726-27 (discussing environmental benefits of allowing natural processes to occur in 2208 FEIS); RD 29140. Plaintiffs are correct that any artificial structure may be characterized as an "unnatural" use of land under a broad definition of that term. However, there is a distinction of workable clarity between building a bridge that allows geological processes to unfold around it and actively importing large quantities of sand to stop all erosion, such that the latter meaningfully may be deemed prohibitive of natural processes where the former need not be so deemed. Accordingly, the Agencies' decision to apply this distinction and eliminate beach nourishment options in an effort to allow natural processes to occur was not arbitrary. See
Relatedly, plaintiffs argue that where the Agencies' decision to eliminate beach nourishment rests on assessment that nourishment options are "likely" to be found inconsistent with the purposes of the Refuge, the Agencies failed to take the required "hard look" at nourishment options. In context, however, the Agencies assessment that beach nourishment options are "likely" to be found inconsistent with the Refuge's purposes simply constitutes acknowledgment that any construction in the Refuge requires a permit from USFWS, and, as part of that permitting process USFWS must make a determination that the B-2500 project would "fulfill ... the specific purposes for which [the Refuge] was established." 16 U.S.C. § 668dd. Where the administrative record *622indicates that beach nourishment can reduce available natural habitat for migratory birds and other wildlife for which the Refuge was established, see AR 58727; see also EO 7864, 3 FR 863 (Apr. 12, 1938) (defining Refuge purposes), it is indeed likely that long-term beach nourishment is inconsistent with the purposes of the Refuge.
Although NEPA requires the Agencies to assess all reasonable alternatives, NEPA does not require the Agencies to apply for a permit in spite of reasonable belief that such permit is likely to be denied nor include detailed analysis for a likely unsuccessful alternative in an EIS. See 40 C.F.R. 1502.2(b) ("[T]here should be only enough discussion to show why more study is not warranted."). Where the Agencies' conclusion that said permit was likely to be denied rests upon observation that beach nourishment options would prevent natural erosion processes from occurring, possibly harming habitat of protected wildlife, the Agencies decision to abandon beach nourishment was not arbitrary.
Fourth, plaintiffs argue that no case law holds specifically that all factors underlying an agency's decision must materially change in order to warrant a supplemental EIS. Nonetheless, as is plain in its text,
Plaintiffs' remaining arguments address the Agencies' analysis of changed erosion projections, which, as noted, the court does not view as material in light of presence of independent bases to reject beach nourishment as a reasonable option.
5. Predetermination
Plaintiffs contend that, in addition to any underlying failures to conduct sufficient analysis under pertinent statutory standards, the 2016 Phase IIb ROD is void because the Agencies' approval of the 2016 Phase IIb ROD unlawfully was predetermined by the 2015 settlement agreement that ended the conservation groups' challenge to the 2010 Phase I ROD.
In determining NEPA compliance, "[a] court should generally restrict its inquiry to the objective adequacy of the EIS, namely, thorough investigation of environmental effects and candid acknowledge of potential environmental harms." Nat. Audubon Soc., 422 F.3d at 198. "Courts should not conduct far-flung investigations into the subjective intent of an agency[,]" because such inquiries may "restrict the open exchange information within an agency, inhibit frank deliberations, and reduce the incentive to memorialize ideas in written form." Id. In addition, subjective inquiries "could also frustrate an agency's ability to change its mind or *623refocus its actions, the very effect that NEPA was designed to encourage." Id. Although "NEPA of course prohibits agencies from preparing an EIS simply to justify decisions already made" or committing resources prejudicing selection of alternatives before making a final decision, 40 C.F.R. 1502.2(f), the evidence of such post hoc rationalization "consists of the environmental analysis itself." Nat. Audubon Soc. v. Dep't. of Navy,
Plaintiffs' claims based upon predetermination fail because, for reasons set forth in previous sections, "the environmental analysis itself" discloses no basis to conclude that the Agencies selected the jug-handle bridge due to predetermination. See
Plaintiffs argue, under standards borrowed from the Ninth and Tenth Circuits, that predetermination invalidates any administrative decision upon proof of an "irreversible and irretrievable commitment of resources" prior to final administrative decision. Metcalf v. Daley,
These arguments fail, first, because, under Fourth Circuit precedent, the evidence of predetermination "consists of the environmental analysis itself[,]" Nat. Audubon Soc.,
Third, the facts of National Audubon Society indicate that it is a physical commitment of resources that implicates predetermination concerns. In that case, the Fourth Circuit expressed approval of preliminary activities during preparation of an EIS because none of the activities "include[d] cutting even a single blade of grass in preparation for construction" of the project.
Fourth, plaintiffs contend that the structure of Merger Team decision-making procedures demonstrates that the court should view the Agencies' unanimous concurrence that the jug-handle bridge is the LEDPA as a consequence of predetermination. Specifically, plaintiffs note that the Merger Team agreement provides that where the Agencies are unable to reach concurrence on a given point, the matter is decided by majority vote of a subset of the Agencies, consisting of defendant NCDOT, defendant FHWA, NCDENR, and USACE. RD 18093. Plaintiffs contend that where three out of four members of this dispute resolution board are parties to the 2015 settlement agreement any vote against the jug-handle bridge would have been futile, thus, unanimous concurrence that the jug-handle bridge was the LEDPA was essentially preordained. However, plaintiffs' conclusion does not follow from the premises. Rather, an equally plausible interpretation of a Merger Team member's incentives is that, where apprised that its vote cannot affect a decision nor otherwise impede the B-2500 project, such agency may as well vote its conscience, perhaps in hopes that its dissent will persuade this court. Accordingly, absence of any dissent to selection of the jug-handle bridge does not, as plaintiffs contend, establish that any decision was predetermined. Plaintiffs' claims on this basis fail.
Finally, this court is not at liberty to approve selection of an alternative that does not comply with NEPA and Section 4(f), see Coal. for Responsible Reg'l. Dev. v. Brinegar,
In sum, plaintiffs' challenges to the 2016 Phase IIb ROD fail. The Agencies adequately considered impacts of the construction *625process, effects on the Refuge, and socio-economic effects. Moreover, the Agencies did not eliminate beach nourishment options prematurely, nor was the 2016 Phase IIb ROD unlawfully predetermined.
CONCLUSION
For reasons noted, plaintiffs' motion for summary judgment, (DE 95), is DENIED, and defendants' and intervenor-defendants' motions for summary judgment, (DE 107, 108, 115), are GRANTED. The clerk is DIRECTED to close this case.
SO ORDERED, this the 4th day of June, 2018.
Related
Cite This Page — Counsel Stack
324 F. Supp. 3d 597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/save-our-sound-obx-inc-v-nc-dept-of-transp-nced-2018.