Hughes River Watershed Conservancy v. Johnson

165 F.3d 283, 29 Envtl. L. Rep. (Envtl. Law Inst.) 20451, 47 ERC (BNA) 2121, 1999 U.S. App. LEXIS 397, 1999 WL 11281
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 13, 1999
DocketNo. 98-2134
StatusPublished
Cited by84 cases

This text of 165 F.3d 283 (Hughes River Watershed Conservancy v. Johnson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hughes River Watershed Conservancy v. Johnson, 165 F.3d 283, 29 Envtl. L. Rep. (Envtl. Law Inst.) 20451, 47 ERC (BNA) 2121, 1999 U.S. App. LEXIS 397, 1999 WL 11281 (4th Cir. 1999).

Opinion

Affirmed by published opinion. Judge HAMILTON wrote the opinion, in which Judge NIEMEYER and Judge HERLONG joined.

OPINION

HAMILTON, Circuit Judge:

The Hughes Rivershed Water Conservancy and a number of other environmental groups (collectively referred to as HRWC) appeal the district court’s grant of summary judgment in favor of the Army Corps of Engineers and the Natural Resources Conservation Service (the Agencies), following our remand of the case with instructions to direct the Agencies to fully comply with the National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321-70d (NEPA). See Hughes River Watershed Conservancy v. Glickman, 81 F.3d 437 (4th Cir.1996) (HRWC I). For the reasons stated below, we affirm.

I.

The procedural and factual history of this case are extensively summarized in this court’s opinion in HRWC I. See id. Accordingly, only a brief synopsis of the facts and procedural history is set forth here.

Starting in 1975, the Agencies drafted a plan to construct a multipurpose dam on the North Fork of the Hughes River, thereby creating a 305-acre lake in the North Fork area of northwestern West Virginia (the Project). The Agencies, in compliance with NEPA and after conducting a series of public meetings, drafted an environmental impact statement (EIS) with respect to the Project. After the Agencies circulated the draft EIS for public comment, the Sierra Club, the Department of the Interior, and the Environmental Protection Agency (EPA) informed the Agencies that they considered the draft EIS deficient.

[286]*286In June 1994, the Agencies released a final environmental impact statement (FEIS) that contained the Agencies’ responses to the comments received on thé draft EIS. One month later, the Agencies issued a record of decision approving the Project. Thereafter, HRWC filed suit challenging the Agencies’ decision approving the Project. The parties agreed to stay the Project pending a decision by the district court. The ease was submitted to the district court on cross-motions for summary judgment based on the administrative record. The district court granted summary judgment in favor of the Agencies, holding that the EIS was not arbitrary and capricious. HRWC noticed a timely appeal. The district court continued the stay pending appeal.

On appeal, this court held that the Agencies had: (1) violated NEPA by failing to take a sufficient “hard look” at the problem of zebra mussel infestation1 resulting from the Project before deciding not to prepare a supplemental environmental impact statement (SEIS);2 and (2) violated NEPA because the EIS’s use of an inflated estimate of the Project’s economic benefits from recreational use of the Project impaired fair consideration of the Project’s adverse environmental effects.3 See id. at 437. Accordingly, this court vacated those parts of the district court’s judgment holding the Agencies had not violated NEPA in these respects and instructed the district court on remand to direct the Agencies to reevaluate the Project in light of our holdings. See id. at 450. Specifically, this court instructed the Agencies to take a “hard look” at the problem of zebra mussel infestation and to determine, based on that “hard look,” whether to prepare a SEIS addressing zebra mussel infestation. See id. at 445. Additionally, this court remanded the case for the Agencies to reevaluate the EIS’s estimate of recreational benefits based upon net benefits rather than gross benefits. See id. at 447. Further, we stated, “[pjending the [Agencies’] reevaluation of the [Pjrojec't in compliance with NEPA, further construction of the [P]roject is stayed.” Id. at 450-51.

After this court’s remand, the Agencies proceeded to reevaluate the Project by examining the specifically identified issues of potential zebra mussel infestation and projected recreational benefits. Among other things, the Agencies obtained Several studies and reports.4

[287]*287Briefly summarized, the results of the studies obtained by the Agencies concluded the following: (1) that zebra mussels are not expected to present a problem to the Project area because the pH and calcium levels in the proposed lake are not expected to be even marginally suitable for the growth of zebra mussels; and (2) that after a more detailed consideration of the Project, including an evaluation of all additional recreational benefits, the change in activity mix, and the consideration of non-use values, the estimated net recreational benefits resulting from the Project amount to $2,577,189 (1996 price base), which supports an overall positive benefit-cost ratio for the Project and, therefore, supports the Project’s economic feasibility.

The results of these studies and the Agencies’ reconsideration of the Project in light of this court’s decision were presented in a draft supplemental environmental impact statement (DSEIS) issued in early November 1997 and circulated for public comment. A locally advertised public meeting was held on November 17, 1997, to receive questions and address concerns about the DSEIS. Notice of the availability of the DSEIS was placed in the Federal Register and copies of it were mailed directly to a number of interested parties. Comments were received, including some from HRWC, and the Agencies responded to the comments.

The final supplemental environmental impact statement (FSEIS), which includes the comments received as a result of the circulation of the DSEIS and the Agencies’ responses, was issued in February 1998.5 Following publication of the FSEIS, the Supplemental Record of Decision (SROD) was issued on March 25, 1998. In the SROD, William J. Hartman of NRCS stated, “Having concluded that neither the zebra mussel nor recreation benefits issue would result in a change in the Recommended Plan for the North Fork Hughes River Watershed Project, I propose to implement the [Pjroject as described in the June 1994 FEIS and the July 26, 1994 [record of decision].” (J.A. 738).

Thereafter, the Agencies filed a motion requesting dissolution of the stay that had prohibited construction of the Project pending further study and analysis. HRWC opposed the request, contending that the Agencies still had not complied with NEPA. The district court entered summary judgment for the Agencies, finding that the Agencies had followed this court’s instructions on remand and fully complied with NEPA. First, the district court determined that the Agencies’ decision regarding the non-impact of zebra mussels was not arbitrary and capricious and was based upon sound scientific studies. Next, the district court found that the economic study commissioned by the Agencies supported the Agencies’ conclusion in the FSEIS that the adverse environmental effects were not distorted by the recreational benefits estimated in the FEIS. Accordingly, on July 9, 1998, the district court granted summary judgment for the Agencies and stayed construction of the Project for a period expiring August 8, 1998. This court declined to extend the stay pending appeal but did expedite the appeal.

HRWC noticed a timely appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Healthy Gulf v. Haaland
District of Columbia, 2025
CADLink America, Inc. v. Jaddou
W.D. North Carolina, 2023
Blair Coleman v. Frank Kendall
74 F.4th 610 (Fourth Circuit, 2023)
Chuncheng Ren v. USCIS
Fourth Circuit, 2023
Coleman v. Wilson
W.D. North Carolina, 2022
Xpress Group, Inc. v. Cuccinelli
W.D. North Carolina, 2022
Gulf Restoration Network v. Zinke
District of Columbia, 2020
Adams v. U.S. Dep't of Labor
360 F. Supp. 3d 320 (D. South Carolina, 2018)
Save Our Sound OBX, Inc. v. N.C. Dep't of Transp.
324 F. Supp. 3d 597 (E.D. North Carolina, 2018)
City of Rockingham v. Federal Energy Regulatory Commission
702 F. App'x 106 (Fourth Circuit, 2017)
Children's Hospital of the King's Daughters, Inc. v. Price
258 F. Supp. 3d 672 (E.D. Virginia, 2017)
Forestwatch v. Lint
135 F. Supp. 3d 477 (D. South Carolina, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
165 F.3d 283, 29 Envtl. L. Rep. (Envtl. Law Inst.) 20451, 47 ERC (BNA) 2121, 1999 U.S. App. LEXIS 397, 1999 WL 11281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hughes-river-watershed-conservancy-v-johnson-ca4-1999.