Savage v. E. R. Snell Contractor, Inc.

672 S.E.2d 1, 295 Ga. App. 319
CourtCourt of Appeals of Georgia
DecidedNovember 5, 2008
DocketA08A1368, A08A1369
StatusPublished
Cited by11 cases

This text of 672 S.E.2d 1 (Savage v. E. R. Snell Contractor, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Savage v. E. R. Snell Contractor, Inc., 672 S.E.2d 1, 295 Ga. App. 319 (Ga. Ct. App. 2008).

Opinion

RUFFIN, Presiding Judge.

Plaintiffs Reba Savage, Jack Savage, and Erin Glanton Savage (collectively, the “Savages”) sued the Georgia Department of Transportation (“DOT”) and E. R. Snell Contractor, Inc. (“Snell”), alleging that the defendants’ road widening project created flooding on the Savages’ property. Snell moved for summary judgment, and the trial court granted the motion. DOT filed a motion to dismiss, arguing that the Savages’ claims were barred based on their failure to give the requisite ante litem notice pursuant to OCGA § 50-21-20, and the trial court granted the motion in part and denied it in part. • The Savages appeal in Case No. A08A1368, alleging that the trial court erred in granting summary judgment to Snell. DOT appeals in Case No. A08A1369, contending that the trial court erred in failing to dismiss the Savages’ case in its entirety. For reasons that follow, we affirm.

Plaintiff Reba Savage owns property located adjacent to Highway 124 on Sunderland Drive in Snellville. She lives in the home on the property with her son and daughter-in-law, plaintiffs Jack Savage and Erin Glanton Savage. Shortly before she purchased the property, Reba Savage learned that DOT intended to widen Highway 124. On June 24, 1998, after the closing, Savage sold a portion of the property to DOT and granted them a temporary easement for purposes of the road widening project.

The State awarded Snell the contract for the expansion project, and they began construction sometime during 2004 or 2005. After Snell began clearing and grading the land, the Savages experienced *320 heavy flooding on their property. 1 According to Reba Savage, on multiple occasions, rainwater broke through silt fence barriers erected by Snell and pooled in her backyard, sometimes standing “for days.” The water also entered the house, flooding one of their bedrooms on at least 15 occasions. The Savages also had their septic tank pumped approximately five times during the course of construction after sewage erupted from their toilets, bathtubs, sinks, and flooring.

After repeated complaints to Snell and DOT, the Savages served ante litem notice of their claims on the State on July 25, 2006, pursuant to OCGA § 50-21-26 (a) (2). DOT did not respond, and the Savages filed suit against Snell and DOT, alleging that they were damaged by the defendants’ negligence and improper design and construction of the expansion project.

Snell moved for summary judgment, contending that it could not be held liable to the Savages because it constructed the roadway in accordance with the plans and specifications provided by DOT. The trial court agreed and granted Snell’s motion. DOT filed a motion to dismiss, alleging that the Savages’ claims against the State were barred because they failed to timely provide the requisite statutory ante litem notice. The trial court granted the motion in part and denied it in part, limiting the Savages’ claims to those for damages that occurred on or after July 25, 2005. We affirm in both cases, for reasons that follow.

Case No. A08A1368

1. The Savages contend that the trial court erred in granting Snell’s motion for summary judgment. We disagree.

“Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law.” 2 A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in a light most favorable to the nonmovant. 3

Georgia law provides that “a contractor for the State engaged in work on a public project is not liable for injury or damage to private property resulting from the work performed unless that damage or *321 injury results from the contractor’s negligence or wilful tort.” 4 However, “a contractor who is an expert in the design of the type of work being done may not ignore defects in the design.” 5 Therefore, Snell can be held liable to the Savages only if it performed its work on the roadway project negligently or if it held itself out as an expert in design. 6

DOT provided the roadway construction plans and specifications for the expansion project, including erosion and sedimentation plans. The DOT contract provided that Snell was responsible for, inter alia, “providing maintenance” on multiple temporary erosion and sediment control devices, including silt fencing, silt retention barriers, and sediment basins. Lloyd C. McNally, Jr., who surveyed Highway 124 after the roadway construction project was completed, determined that the construction and the storm water structures conformed to the DOT standards and specifications as shown on the construction plans issued fo.r the project. According to Snell’s project supervisor, Thomas Byrd, the erosion control devices were installed pursuant to DOT’s plans and specifications. Byrd also testified that Snell was not authorized to vary from the plans without approval from DOT.

The Savages have not provided any contrary evidence. Instead, they broadly contend that “Snell’s negligence in completing its DOT contract caused nuisance damages to the plaintiffs.” Their sole specific inference of negligence is that, on one occasion, a portion of the silt fencing was overrun with silt. But Byrd testified that the fencing was repaired thereafter. 7 Moreover, the Savages have failed to demonstrate that the single instance of the apparent failure of the silt fencing was a result of Snell’s negligence or, more importantly, that it caused the flooding and erosion problems from storm water run-off that they allege in their complaint. 8 Instead of pointing to specific evidence to support their contention, the Savages reason that “[if] the erosion control plans were adequate and the erosion controls failed numerous times over a year’s span, then the only *322 reasonable inference is that E. R. Snell negligently failed to maintain the controls entrusted by DOT.” This conclusory statement, unsupported by evidence, is insufficient to demonstrate negligent construction on the part of Snell. 9 Accordingly,, the trial court did not err in granting Snell’s motion for summary judgment. 10

2. In the argument portion of their brief, the Savages allege that “[the] plaintiffs are entitled to recover punitive damages and attorney’s fees.” But the Savages failed to enumerate this argument as error on appeal, and therefore, we cannot consider it. 11

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Greensboro v. Tony Rowland
778 S.E.2d 409 (Court of Appeals of Georgia, 2015)
S-D Rira, LLC v. Outback Property Owners' Ass'n
765 S.E.2d 498 (Court of Appeals of Georgia, 2014)
DeKALB COUNTY v. KIRKLAND Et Al.
764 S.E.2d 867 (Court of Appeals of Georgia, 2014)
Liberty County, Georgia v. Martha Eller
Court of Appeals of Georgia, 2014
Liberty County v. Eller
761 S.E.2d 164 (Court of Appeals of Georgia, 2014)
Myers v. Board of Regents of University System
751 S.E.2d 490 (Court of Appeals of Georgia, 2013)
Lawrence Defloria v. Rufus Walker
Court of Appeals of Georgia, 2012
DeFloria v. Walker
732 S.E.2d 121 (Court of Appeals of Georgia, 2012)
Board of Regents v. Canas
672 S.E.2d 471 (Court of Appeals of Georgia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
672 S.E.2d 1, 295 Ga. App. 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/savage-v-e-r-snell-contractor-inc-gactapp-2008.