Sagi Plumbing v. Chartered Construction Corp.

19 Cal. Rptr. 3d 835, 123 Cal. App. 4th 443
CourtCalifornia Court of Appeal
DecidedNovember 10, 2004
DocketB169468
StatusPublished
Cited by11 cases

This text of 19 Cal. Rptr. 3d 835 (Sagi Plumbing v. Chartered Construction Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sagi Plumbing v. Chartered Construction Corp., 19 Cal. Rptr. 3d 835, 123 Cal. App. 4th 443 (Cal. Ct. App. 2004).

Opinions

Opinion

HASTINGS, J.

INTRODUCTION

Appellant Sagi Plumbing is a plumbing contractor. Respondent Chartered Construction Corporation is a general contractor. Respondent hired appellant [445]*445to work as a subcontractor on several projects. Appellant filed suit against respondent for breach of contract based on respondent’s failure to pay on three unrelated projects. The parties agreed to bifurcate the action and to try first the cause of action arising out of one project. After that trial was completed, appellant did nothing to bring the other causes of action to trial other than to file a notice of trial and attend a status conference. The trial court granted respondent’s motion to dismiss the two remaining causes of action based upon appellant’s failure to bring them to trial within five years. (Code Civ. Proc., § 583.310.)1

On this appeal, the issue is whether there was a partial trial of the lawsuit for purposes of the five-year statute because trial had been conducted on the one unrelated cause of action. We conclude that the first trial did not constitute a trial for the purposes of the remaining causes of action because each concerned a different and unrelated construction project. We also find that no theory of “tolling” can excuse appellant’s failure to bring the two causes of action to trial within five years. We therefore affirm the order of dismissal.

FACTUAL AND PROCEDURAL BACKGROUND

On December 19, 1996, appellant filed suit against respondent for breach of contract. Appellant alleged three separate causes of action based upon different construction projects: the Hollywood Bowl project, the Inglewood High School project, and the Torrance High School project.

On June 16, 1997, the parties filed a stipulation that their case was related to and now consolidated with several other lawsuits filed against respondent by, inter alia, other subcontractors who had worked on the Hollywood Bowl project. The stipulation recites: “Each of the aforementioned actions involves common questions of law and fact, and separate proceedings would involve duplication of effort by the court and the parties involved.” The lead case in the consolidated action was the lawsuit filed by Ho-Bo Engineering, Inc., against respondent.

In March 2001, the superior court appointed a referee to hear evidence and make a report on various issues in the consolidated action. (§ 639.) The parties stipulated that the five-year statute would be tolled “for the period March 5, 2001, through the date of referee’s final report.”

On January 7, 2002, the referee filed his report.

On February 20, 2002, the parties executed a stipulation “to bifurcate” the two causes of action arising out of the Inglewood High School and Torrance [446]*446High School projects “from the remainder of this consolidated action.” They further stipulated that the two causes of action “may be tried after the remainder of this action and by bench trial.”

On March 5, 2002, trial commenced in the consolidated action. Trial concluded on June 11, 2002.

On September 25, 2002, the parties executed a stipulation which reads: “WHEREAS it has already been ordered by the Court upon stipulation of [the parties] that the second and third causes of action of the complaint ... are bifurcated from the remainder of this consolidated action; and, [|] WHEREAS the remaining portions of this consolidated case have been tried and judgment is to be entered; the parties to this stipulation further agree and stipulate that the second and third causes of action of the Sagi Plumbing action may be severed from the remainder of this action and tried separately.” At the subsequent hearing on the motion to dismiss, counsel for appellant gave this explanation for the severance: “After the main case [regarding the Hollywood Bowl project] went to verdict, the judgment—trying to get a judgment entered—but my part of the case prevented a judgment from being entered, and as a convenience to [respondent], the other parties, it was severed and set for a further trial date, a continued trial date.”

On October 22, 2002, the court ordered severance pursuant to the parties’ stipulation.

On October 30, 2002, appellant filed notice of trial.

On March 18, 2003, appellant attended a status conference. Trial on the two severed causes of action was set for July 29, 2003.

On June 10, 2003, respondent moved to dismiss for failure to commence trial within five years. In light of the parties’ March 2001 stipulation that the five-year statute would be tolled during the reference, the period to commence trial had expired in October 2002.

Appellant’s opposition urged that trial had commenced within five years because trial on the consolidated action arising out of the Hollywood Bowl project began in March 2002 before the two causes of action were formally severed from the lawsuit. Appellant offered no explanation as to why it had not yet commenced trial on those two causes of action. In particular, [447]*447appellant did not argue it had been impossible, impractical or futile to commence trial.

The trial court granted the motion to dismiss. Its minute order states: “Plaintiff has provided no authority for the argument that a bifurcated proceeding on separate causes of action for separate construction projects survives the five-year rule under Code of Civil Procedure Section 583.310. There is no showing, either, that the prosecution of these claims was tolled, stayed or otherwise rendered impossible, impractical or futile.”

DISCUSSION

Section 583.310 provides: “An action shall be brought to trial within five years after the action is commenced against the defendant.” Section 583.360, subdivision (a) provides: “An action shall be dismissed by the court ... on motion of the defendant ... if the action is not brought to trial within the time prescribed in this article.” The statute serves to “preventQ prosecution of stale claims where defendants could be prejudiced by loss of evidence and diminished memories of witnesses [and] to protect defendants from the annoyance of having unmeritorious claims against them unresolved for unreasonable periods of time. [Citations.]” (Lewis v. Superior Court (1985) 175 Cal.App.3d 366, 375 [220 Cal.Rptr. 594].)

“In reviewing the lower court’s dismissal of [an] action for failure to prosecute, the burden is on appellant to establish an abuse of discretion. [Citation.] We will not substitute our opinion for that of the trial court unless a clear case of abuse is shown and unless there is a miscarriage of justice. [Citation.]” (Mitchell v. Frank R. Howard Memorial Hospital (1992) 6 Cal.App.4th 1396, 1402 [8 Cal.Rptr.2d 521].)

Appellant’s opening brief frames the issue as follows: “The issue here is not whether trial was impossible, impracticable or futile, but whether a trial actually commenced.” Appellant therefore adheres to the position it advanced in the trial court: the five-year statute was satisfied when trial commenced on March 5, 2002, on the consolidated Hollywood Bowl action. Consistent with that approach, appellant concedes that the February 2002 bifurcation “did not in itself toll the five year statute. [Appellant] still was required to proceed within five years[.]” “[T]he commencement of trial of the Hollywood Bowl cases” satisfied the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trejo v. Johnson & Johnson Consumer CA2/4
California Court of Appeal, 2025
Steiner v. Thexton CA3
California Court of Appeal, 2016
Hernandez v. Tseheridis CA4/3
California Court of Appeal, 2013
Thurman v. Bayshore Transit Management, Inc.
203 Cal. App. 4th 1112 (California Court of Appeal, 2012)
Bruns v. E-Commerce Exchange, Inc.
172 Cal. App. 4th 488 (California Court of Appeal, 2009)
Sagi Plumbing v. Chartered Construction Corp.
19 Cal. Rptr. 3d 835 (California Court of Appeal, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
19 Cal. Rptr. 3d 835, 123 Cal. App. 4th 443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sagi-plumbing-v-chartered-construction-corp-calctapp-2004.