Saddlewood Downs, L.L.C. v. Holland Corp.

99 P.3d 640, 33 Kan. App. 2d 185, 2004 Kan. App. LEXIS 1122, 2004 WL 2414018
CourtCourt of Appeals of Kansas
DecidedOctober 29, 2004
Docket91,057
StatusPublished
Cited by7 cases

This text of 99 P.3d 640 (Saddlewood Downs, L.L.C. v. Holland Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saddlewood Downs, L.L.C. v. Holland Corp., 99 P.3d 640, 33 Kan. App. 2d 185, 2004 Kan. App. LEXIS 1122, 2004 WL 2414018 (kanctapp 2004).

Opinion

Pierron, J.:

In this construction contract case, Saddlewood Downs, L.L.C., (Saddlewood) appeals the judgment entered in favor of Holland Corporation, Inc. (Holland). Saddlewood argues the trial court erred in finding that Holland was entitled to money for fly ash stabilization work required by the City of Olathe (City) prior to Holland’s completion of streets in the Saddlewood Downs subdivision (subdivision). Saddlewood also claims the trial court erred in not finding Holland liable for slander of title for maliciously filing a mechanic’s lien. We find the trial court was correct and affirm.

With a few exceptions, the significant facts in this case are undisputed. The central question revolves around Holland’s entitlement to money for fly ash stabilization work required by the City. Saddlewood was the owner and developer of the subdivision. Holland’s principal business is the construction of asphalt streets as part of new commercial and residential developments.

In March 2000, Holland submitted a bid for the construction of street improvements for the subdivision. Holland was awarded the contract, wherein tire parties agreed Holland would “provide all the necessaiy materials, tools, labor and equipment to construct the [street construction project] in accordance with the approved plans.” The contract did not include any line item for fly ash stabilization or mention it directly. The contract also provided that variations of tire listed items were not cause for adjustment of the contract, “unless the scope of work [was] changed by written authorization of the Owner.” There were two other contracts entered into by Saddlewood and Holland and a third party, Town & Country Manor, L.C., involving street construction on an adjacent development and shared passageways, but those two contracts are not at issue.

There were three written changes made to the contract between Saddlewood and Holland: (1) In May 2000, the parties agreed to *187 an amendment for the addition of sidewalks; (2) in July 2000, the parties agreed to an amendment for the addition of street lights and gas and electric lines; and (3) in March 27, 2001, the parties consented to Saddlewood’s agreement to pay interest on late payments.

In June 2000, after Holland had completed the site grading for the street construction, the City determined that additional stabilization of the subgrade material was necessary to pass inspection and the application of fly ash was required. Fly ash is a mining byproduct that is applied to, and mixed with, existing expansive sub-grade soil to create a subbase for the asphalt pavement that is stable and nonexpansive. There is no dispute that specifications by the City provide that fly ash could be required in order to provide proper stabilization to the soil under the streets. Holland did not include a line item for fly ash stabilization (or its potential) in its bid, nor did it expressly exclude fly ash from the bid.

Upon being notified that fly ash was required, Holland stopped work and Jeff Shoemaker, Holland’s vice-president in charge of the subdivision project, contacted the project engineer, David Scott of Green Engineering, advising of the fly ash requirement. Shoemaker sent Scott a proposal of costs associated with the fly ash work and called a meeting with Scott, Don Virgin (principal member of Saddlewood), Crow (a representative of Town & Country), and Jim Green (Green Engineering).

Shoemaker testified that at the meeting, the parties discussed and negotiated the price for fly ash stabilization and Holland agreed to reduce the price per square yard from $4.95 to $4.45. Scott’s testimony confirmed the negotiated lower price, but Virgin testified no agreement was reached as to who would pay for the fly ash stabilization work. Following the meeting, Shoemaker sent Green a revised price quote for the fly ash work per the negotiations at the meeting. Shoemaker testified Virgin contacted him by telephone and instructed him to proceed with the fly ash stabilization work and that Saddlewood would pay for the work at the negotiated price. Virgin disputes that he ever said Saddlewood would pay for the fly ash work, that there was never any agreement reached concerning the fly ash issue, and that he had left the meet *188 ing with the understanding that once the project was complete they would “hassle over” the problem if Holland requested additional payment. The fly ash was applied in August 2000.

During the course of construction, Holland delivered several invoices to Saddlewood in support of periodic progress payments. Shoemaker testified that invoices as early as September 2000 included a specific line item under change orders for the fly ash stabilization work. Saddlewood never objected to any of the invoices on the basis that costs for fly ash were included in the project cost. After Saddlewood fell behind in its payments, the parties negotiated the third written amendment previously mentioned concerning Saddlewood’s agreement to pay interest.

Upon Saddlewood’s refusal to pay the additionally billed sums, on November 29, 2001, Holland filed a mechanic’s hen against the Saddlewood property in the amount of $75,312.82. The lien stated that materials and services were last furnished on July 29, 2001, exactly 4 months prior to filing the lien. On December 11, 2001, Holland filed an amended mechanic’s lien against the Saddlewood property stating the materials and services were last furnished on October 24, 2001.

Gary Gassen, Holland’s treasurer and signatoiy on both mechanics’ liens testified that no work occurred on the project on July 29, 2001, because that date was a Sunday. He said the error occurred as a result of the ending of the pay period on July 29, 2001, and Holland employees had clocked work on the Saddlewood project sometime during the days of the prior week. He said he filed the amended mechanic’s hen shortly thereafter because Holland employees still registered time on the project through October 24, 2001.

Despite Holland’s mechanic’s lien, on December 4, 2001, Saddlewood filed a petition for money had and received alleging overpayment to Holland in the amount of $82,156.50. During tire summer of 2002, Saddlewood arranged to sell the subject property. In order to clear title for the sale, Saddlewood paid Holland the amount of the mechanic’s hen out of the proceeds of the sale. However, Saddlewood reserved the right to challenge Holland’s *189 mechanic’s lien. On December 4, 2002, Saddlewood filed an amended petition adding a claim of slander of title.

The trial court conducted a bench trial in the matter. The court granted judgment in favor of Holland. The court found the fly ash stabilization work was not part of the original contract and that it constituted extra work by Holland for which it was entitled to compensation. The court stated that although there was no written authorization for the fly ash stabilization, Saddlewood’s actions or inactions constituted an authorization for the extra work and a waiver of tire requirement in the original contract that extra work required written authorization. Holland also reasonably relied on Saddlewood’s actions or inactions to its detriment in performing the fly ash stabilization work.

The trial court rejected Saddlewood’s claim for slander of title.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellis v. Popular Bank
D. Kansas, 2024
Store Six, LLC v. Shannon Valley Ventures, LLC
Court of Appeals of Kansas, 2018
White v. Security State Bank
Court of Appeals of Kansas, 2017
Kape Roofing & Gutters, Inc. v. Chebultz
Court of Appeals of Kansas, 2016
Douglas Landscape & Design, L.L.C. v. Miles
355 P.3d 700 (Court of Appeals of Kansas, 2015)
Southern Star Central Gas Pipeline, Inc. v. Cline
754 F. Supp. 2d 1257 (D. Kansas, 2011)
Law Co., Inc. v. Mohawk Const. & Supply Co.
702 F. Supp. 2d 1304 (D. Kansas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
99 P.3d 640, 33 Kan. App. 2d 185, 2004 Kan. App. LEXIS 1122, 2004 WL 2414018, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saddlewood-downs-llc-v-holland-corp-kanctapp-2004.