Owens v. City of Bartlett

528 P.2d 1235, 215 Kan. 840, 1974 Kan. LEXIS 579
CourtSupreme Court of Kansas
DecidedDecember 7, 1974
Docket47,488
StatusPublished
Cited by14 cases

This text of 528 P.2d 1235 (Owens v. City of Bartlett) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Owens v. City of Bartlett, 528 P.2d 1235, 215 Kan. 840, 1974 Kan. LEXIS 579 (kan 1974).

Opinion

The opinion o£ the court was delivered by

Fromme, J.:

An. action was brought by the plaintiff, Albert Owens, to recover a balance due on a construction contract awarded to him by the City of Bartlett. The contract was for a water distribution system and the contract price was $21,303.00 to be paid in periodic payments as the work progressed. Suit was brought after completion of the project to recover a balance due of $2,751.30. Judgment for the amount claimed was entered after a trial to the court. The city appeals.

The contract entered into by the parties called for installation of underground water lines as well as the installation of certain fire hydrants and meter hookups. The contractor was required to provide and pay for all materials, labor, tools, equipment, water, light, power, transportation, superintendence, and all other services and facilities necessary to complete the work. The contract when executed contained the following provision to cover extra or additional work and changes:

“16. Extra and/or Additional Work and Changes. — Without invalidating the contract, the Owner may order extra work or make changes by altering, adding to or deducting from the work, the contract sum being adjusted accordingly. All the work of the kind bid upon shall be paid for at the price stipulated in the proposal (unless such prices were rejected at the time the proposal was accepted), or at the lump sum price agreed upon between the Owner and the Contractor, and no claims for any extra work or materials shall be *842 allowed unless it is ordered in writing by the Owner or its authorized representative. If the extra work shall be of the kind for which no price was stipulated in the Proposal, and the Owner and the Contractor cannot agree as to the fair value of such work prior to its performance, such work shall be performed and the Contractor will be paid the reasonable cost of the labor and materials entering permanently into the work as determined by the Owner’s Engineer, plus 15 percent to cover the general expenses, including, without limiting, the cost of superintendence, overhead, insurance and bond; but no claim, for such extra work will be allowed unless the same was done pursuant to a written order as aforesaid. The Contractor shall, when requested by the Engineer, furnish itemized statements of the cost of all extra work ordered and give the Engineer access to accounts, bills and vouchers relating thereto.” (Emphasis added.)

As the work progressed extra work and materials were orally-requested by the mayor including an extra fire hydrant, 600 feet of two inch pipe, and footings and lines to connect a water tower.

Both the city and contractor encountered difficulties in the course of the project. The contractor encountered rock which had to be broken up and removed from the ditches. Dirt or sand had to be hauled in to put under the water lines. The city ran short of money after issuing the maximum amount of revenue and general obligation bonds. It fell behind in the periodic payments required for work completed under the contract. The contractor held up work on the contract for three weeks. It was at this time that some discussion took place between the mayor and contractor concerning the payments and the removal of the rock.

The contractor testified that it was agreed the city would rent and furnish special equipment to remove the rock, that the labor for rock removal was to be paid for as an extra under the contract, but that the extras were not to be paid for until completion and final billing. The mayor, on the other hand, testified he never agreed “as mayor” that the city would pay for rock removal and he was never authorized by the city to do so. The city did, however, authorize him to rent the special equipment, an air compressor and jackhammer, in order to get the contractor back to work. This equipment was furnished to the contractor and used to complete the job.

It is clear that itemized statements were furnished covering labor for rock removal and $412.70 was paid by the city thereon. The original contract called for payments totaling $21,303.00. The amount to be paid at completion included an additional sum of $4,657.38 for extras of which amount $3,164.00 was for removal of *843 rock and $1,493.38 was for other extras about which there is no dispute. Accordingly the total amount due under the contract as claimed by the contractor was $25,960.38 of which $23,209.08 was paid. This left the balance claimed for which judgment was entered in the amount of $2,751.30.

After the water distribution system had been completed and all bills had been submitted to the city, the city attorney wrote a letter to the contractor Owens. The letter advised that the city was short of funds with which to pay its creditors for the project. A check for $6,919.18 was enclosed representing 71.55% of the total balance due the contractor including that claimed for rock removal. By implication at least the amount claimed by the contractor for rock removal was acknowledged as a debt of the city. The contractor did not agree to the reduction and this suit followed.

The entire thrust of the city’s appeal is based upon the binding effect of the provision in the contract that no claim for extra work would be allowed unless done pursuant to a written order. It was admitted that no written order was received by the contractor as to any of the extras furnished.

Generally a stipulation in a public construction contract that claims for extra work or materials shall be allowed only if ordered in writing by the public entity is valid and binding upon the parties, and therefore, so long as such a provision remains in effect, no recovery can be had for extra work or materials furnished without a written order in compliance therewith. (Hutchinson v. White, 80 Kan. 37, 101 Pac. 458. See also Burke v. Allegheny County, Aplnt., 336 Pa. 411, 9 A. 2d 396.) The stipulation in a public construction contract that extra work or materials must be ordered in writing can be avoided by the parties to the contract where their words, acts, or conduct would amount to a waiver or modification of such provision, or where the public entity by the acts or conduct of its proper officer or representative is estopped to rely on it. (Watkins v. Carrig, 91 N. H. 459, 21 A. 2d 591, 138 A. L. R. 131.) The cases which have recognized these rules of avoidance have been collected and may be found in 1 A. L. R. 3d, § 11, p. 1295, in the annotation, Public Construction Contract — Extras. See also Anno.— Consideration for Additional Pay, 12 A. L. R. 2d 78.

Under the doctrine of promissory estoppel a promise is binding and will be enforced when it is a promise which the promisor should reasonably expect to induce action or forbearance of a definite and substantial character on the part of the promisee and *844 which does induce such action or forbearance and if injustice can be avoided only by enforcement of the promise. (Kirkpatrick v. Seneca National Bank, 213 Kan. 61, Syl. ¶ 1, 515 P. 2d 781. See also Marker v. Preferred Fire Ins. Co., 211 Kan. 427, 506 P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thoroughbred Assoc. v. Kansas City Royalty Co.
Court of Appeals of Kansas, 2020
Store Six, LLC v. Shannon Valley Ventures, LLC
Court of Appeals of Kansas, 2018
Douglas Landscape & Design, L.L.C. v. Miles
355 P.3d 700 (Court of Appeals of Kansas, 2015)
Hill v. Ricoh Americas Corp.
603 F.3d 766 (Tenth Circuit, 2010)
Saddlewood Downs, L.L.C. v. Holland Corp.
99 P.3d 640 (Court of Appeals of Kansas, 2004)
Wiese v. Wiese
699 P.2d 700 (Utah Supreme Court, 1985)
State v. First National Bank of Ketchikan
629 P.2d 78 (Alaska Supreme Court, 1981)
Blakesley v. Johnson
608 P.2d 908 (Supreme Court of Kansas, 1980)
Brinson v. School District 431
576 P.2d 602 (Supreme Court of Kansas, 1978)
Crow v. City of Wichita
566 P.2d 1 (Supreme Court of Kansas, 1977)
State v. Childers
563 P.2d 999 (Supreme Court of Kansas, 1977)
Coonrod & Walz Construction Co. v. Motel Enterprises, Inc.
535 P.2d 971 (Supreme Court of Kansas, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
528 P.2d 1235, 215 Kan. 840, 1974 Kan. LEXIS 579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/owens-v-city-of-bartlett-kan-1974.