Sabal Trail Transmission, LLC v. 3.921 Acres of Land in Lake County Florida

947 F.3d 1362
CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 22, 2020
Docket18-11836
StatusPublished
Cited by17 cases

This text of 947 F.3d 1362 (Sabal Trail Transmission, LLC v. 3.921 Acres of Land in Lake County Florida) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sabal Trail Transmission, LLC v. 3.921 Acres of Land in Lake County Florida, 947 F.3d 1362 (11th Cir. 2020).

Opinion

Case: 18-11836 Date Filed: 01/22/2020 Page: 1 of 23

[PUBLISH]

IN THE UNITED STATES COURT OF APPEALS

FOR THE ELEVENTH CIRCUIT ________________________

No. 18-11836 ________________________

D.C. Docket No. 5:16-cv-00178-JSM-PRL

SABAL TRAIL TRANSMISSION, LLC,

Plaintiff - Appellant,

versus

3.921 ACRES OF LAND IN LAKE COUNTY FLORIDA, SUNDERMAN GROVES, INC, UNKNOWN OWNERS, IF ANY,

Defendants - Appellees.

________________________

Appeal from the United States District Court for the Middle District of Florida ________________________

(January 22, 2020) Case: 18-11836 Date Filed: 01/22/2020 Page: 2 of 23

Before WILLIAM PRYOR and JILL PRYOR, Circuit Judges, and ROBRENO,* District Judge.

JILL PRYOR, Circuit Judge:

The federal Natural Gas Act (“NGA”), 15 U.S.C. §§ 717-717z, allows

natural gas companies to acquire through eminent domain private property on

which to construct and operate natural gas pipelines. See 15 U.S.C. § 717f(h).

After plaintiff Sabal Trail Transmission, LLC, received approval from the Federal

Energy Regulatory Commission (“FERC”) to construct an underground natural gas

pipeline from Alabama to Florida, it needed to acquire easements to build and

operate the pipeline across property owned by various landowners.

Sabal Trail brought this condemnation action to acquire permanent and

temporary easements that would allow it to build and operate a portion of the

pipeline on property owned by defendant Sunderman Groves, Inc. Sunderman

Groves stipulated in the action that Sabal Trail was entitled to the easements,

leaving the appropriate amount of compensation as the only remaining issue. At

trial, a jury awarded Sunderman Groves $309,500 as compensation for the

easements. The district court then entered a final judgment, awarding Sunderman

Groves $309,500 and providing that as part of the compensation award,

* Honorable Eduardo C. Robreno, United States District Judge for the Eastern District of Pennsylvania, sitting by designation.

2 Case: 18-11836 Date Filed: 01/22/2020 Page: 3 of 23

Sunderman Groves was entitled to recover its attorney’s fees and costs in an

amount to be set by the court.

Sabal Trail raises two separate issues on appeal. First, it argues that it is

entitled to a new trial because the district court abused its discretion in allowing

Jan Sunderman, who owned Sunderman Groves, to give speculative lay opinion

testimony about the remaining property’s value after the pipeline was built.

Second, Sabal Trail challenges the district court’s decision to award Sunderman

Groves its attorney’s fees and costs. We conclude that the district court did not

abuse its discretion in allowing Sunderman to testify about the value of the

property and that we lack jurisdiction to review whether Sunderman Groves is

entitled to attorney’s fees and costs. Accordingly, we affirm in part and dismiss in

part.

I. FACTUAL BACKGROUND

This case arises from Sabal Trail’s construction of a 500-plus mile

underground pipeline to transport natural gas from Alabama to Florida. FERC

issued Sabal Trail a certificate of public convenience and necessity authorizing the

construction and operation of the pipeline. The certificate authorized Sabal Trail to

build the pipeline along a route where Sabal Trail held existing rights-of-way to

much of the land needed for construction of the pipeline. For the remaining more

than 200 miles of the route, Sabal Trail needed to acquire easements from

3 Case: 18-11836 Date Filed: 01/22/2020 Page: 4 of 23

landowners to build the pipeline across the landowners’ properties. Although

Sabal Trail was able to negotiate agreements with most landowners to purchase the

necessary easements, some landowners would not agree.

A portion of the pipeline’s route ran across property owned by Sunderman

Groves, a company owned by Charles and Jan Sunderman, who did not agree to

allow Sabal Trail to purchase easements on their company’s property. Sunderman

Groves owns approximately 500 acres of land spread across various parcels in

Lake County, Florida. Sabal Trail sought to lay approximately 1,335 feet of

pipeline in a diagonal path across a 40-acre parcel of Sunderman Groves’s

property.

To build the pipeline across the parcel, Sabal Trail sought a permanent

easement that would allow it to install and maintain the underground pipeline and

related equipment. The permanent easement also would guarantee Sabal Trail the

right to bar the Sundermans and any successive owner of the property from

building any structure in the permanent easement area, allow Sabal Trail to remove

any vegetation in the permanent easement area, and permit Sabal Trail to enter the

remainder of the parcel to access the pipeline and related equipment. The total

area Sabal Trail sought to condemn for the permanent easement was 1.535 acres.

In addition, Sabal Trail also sought a larger, temporary easement to allow for the

construction of the pipeline; the temporary easement covered 2.386 acres.

4 Case: 18-11836 Date Filed: 01/22/2020 Page: 5 of 23

When Sunderman Groves would not agree to sell the easements, Sabal Trail

sought to obtain the easements by exercising the power of eminent domain. See

15 U.S.C. § 717f(h) (allowing the holder of a certificate of public convenience and

necessity to exercise the right of eminent domain to obtain an easement to

construct and operate a natural gas pipeline). Pursuant to the NGA, Sabal Trail

filed this condemnation action against Sunderman Groves.1 Sunderman Groves

stipulated that Sabal Trail was entitled to the easements under the NGA. The

parties continued to litigate about the amount of compensation Sabal Trail would

pay Sunderman Groves for the easements. Because the parties could not agree on

the amount, the district court held a jury trial on this issue. 2

During the course of a four-day trial, the jury heard evidence about the value

of the land affected by the pipeline and the appropriate amount of compensation

for the taking of the land. The parties agreed that Sunderman Groves was entitled

to compensation for the value of the land taken for the permanent easement, the

value of the land taken for the temporary easement, and severance damages to

1 Sabal Trail filed other similar condemnation actions to obtain easements in district courts in the Middle District of Alabama, Northern District of Florida, Middle District of Florida, and Middle District of Georgia. 2 By the time of the trial, Sabal Trail had completed construction of the section of pipeline crossing Sunderman Groves’s property.

5 Case: 18-11836 Date Filed: 01/22/2020 Page: 6 of 23

compensate Sunderman Groves for the diminution in value of the remainder of the

parcel after the condemnation. 3 The parties disagreed about each of these values.

At trial, both Sabal Trail and Sunderman Groves presented expert testimony

from real estate appraisers. Sabal Trail’s appraiser, Richard Parham, opined that

the total compensation owed to Sunderman Groves for the condemnation was

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
947 F.3d 1362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sabal-trail-transmission-llc-v-3921-acres-of-land-in-lake-county-florida-ca11-2020.