S & W INVESTMENT COMPANY v. Otis W. Sharp & Son, Inc.

170 So. 2d 360, 247 La. 158, 1964 La. LEXIS 2851
CourtSupreme Court of Louisiana
DecidedDecember 14, 1964
Docket47261
StatusPublished
Cited by4 cases

This text of 170 So. 2d 360 (S & W INVESTMENT COMPANY v. Otis W. Sharp & Son, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S & W INVESTMENT COMPANY v. Otis W. Sharp & Son, Inc., 170 So. 2d 360, 247 La. 158, 1964 La. LEXIS 2851 (La. 1964).

Opinion

HAMITER, Justice.

In this suit S & W Investment Company, Inc., seeks to recover a sum expended by it for completing a swimming pool which the defendant, Otis W. Sharp and Son, Inc., had originally contracted to build but later abandoned.

The district court’s judgment in favor of plaintiff for $2174.95 was reversed by the Court of Appeal, and the suit was dismissed. 162 So.2d 171. We granted cer-tiorari. 246 La. 371, 164 So.2d 359.

The swimming pool was to be built by the defendant, at a contracted price of $4725, in the patio area of a motel proposed to be constructed by plaintiff. It was understood by the parties that, in order to permit the use of plaintiff’s heavy equipment nearby and to avoid the risk of damaging the pool tiling and appurtenances during erection of the buildings, the concrete shell of the pool would be provided first and the remaining work (including the installing of tiling, filter, ladders, trim, etc.) would be undertaken following the buildings’ completion.

The written contract dated September 12, 1961 provided in part:

“ARTICLE I. SCOPE OF WORK— The Contractor shall furnish all of the material and perform all of the work for the construction of a Swimming Pool as described below.

“ ‡ % %

“ARTICLE 3. PROGRESS PAYMENTS — * * * Upon completion of shell (which is all but tile, brick, filter, deck eqpt., plum, line to building, and interior finish), amt. due $3000.00. Remainder due upon completion of pool.”

Also, the contract obligated the owner to excavate the pool site, to move the excavated material, and to place the backfill around the shell.

The excavation was performed by a construction company paid by plaintiff, but the work was under the direction and supervision of the defendant. The shell was completed about October 17, 1961, and on October 22, 1961 plaintiff gave to the defendant the $3000 progress payment then due (more particularly hereinafter discussed).

Prior to leaving the job temporarily an employee of the defendant closed a hydrostatic pressure relief valve (which had been installed in the shell as a safety device) by *164 inserting a plug in it, and he then commenced filling the shell with water by means of a garden hose. He was sent back to the site at least two more days for the purpose of continuing the water filling and (to quote his testimony) “to watch that our plumbing, pipes and the shell of the pool wasn’t damaged by the equipment being used to back-fill.” (Italics ours.)

The evidence is to the effect that the safest method of protecting the shell was to fill it with water rather than to depend on the valve. However, before a sufficient amount of water was placed therein the filling operation was discontinued and the hose was removed from the site by defendant’s employee.

A heavy rainfall that occurred in early November, 1961 caused the uprooting or “floating” of one end of the shell. Defendant’s initial salvage attempts were unsuccessful, and it disclaimed any further obligation when plaintiff refused to augment the contract price.

Plaintiff, thereupon, employed the services of J. Stanley Middleton, d/b/a Family Pools, to malee the necessary repairs and to bring the work to operational status for the price of $3899.95. Plaintiff’s claim in this suit of $2174.95 represents the difference between the amount paid to Middleton and the balance remaining under the contract with the defendant.

Plaintiff cites and relies on Revised Civil Code Article 2758 which states: “Builder furnishing materials — Destruction of work before delivery — Bearing of loss. — When the undertaker furnishes the materials for the work, if the work be destroyed, in whatever manner it may happen, previous to its being delivered to the owner, the loss shall be sustained by the undertaker, unless the proprietor be in default for not receiving it, though duly notified to do so.”

Plaintiff contends that this defendant had obligated itself to construct a complete swimming pool — an indivisible obligation; that the progress payment of $3000, made for the benefit of the undertaker, did not relieve the latter of the responsibility of preserving the entire work until it was finished, delivered and accepted; and that, consequently, under the aforequoted codal provisions any damage thereto occurring before that time must be borne by the defendant contractor.

The defendant apparently recognizes that generally, in the absence of an agreement of the parties, the risk of loss in a building contract is on the contractor until he has completed and delivered the work. This can hardly be gainsaid in view of the provisions of Article 2758.

It urges, however, that this particular contract was one “for work composed of detached pieces”, to wit: (1) a shell and *166 (2) the completion of a shell into a finished pool, all as is contemplated by Revised Civil Code Article 2761 which reads: “Delivery of work in separate parts. — If the work be composed of detached pieces, or made at the rate of so much a measure, the parts may be delivered separately; and that delivery shall be presumed to have taken place, if the proprietor has paid to the undertaker the price due for the parts of the work which have already been completed.” It argues that under the provisions of this article there arose a presumption of delivery to and acceptance by the owner when the latter paid for that “piece” (the shell) already completed; and that, therefore, following such payment, and pending the finishing of the entire work, the risk of loss of such “piece” was on the owner.

The Court of Appeal (as did the district court) found that, within the contemplation of the parties, the obligation undertaken by this defendant was an indivisible one; and it was inclined to the view that, under the circumstances, the provisions of Article 2758 placed the loss on the undertaker. However, a majority of its members determined that two prior decisions, N. Levy and Son v. Paquette et al., 144 La. 244, 80 So. 269 and Industrial Homestead Association v. Charles A. Junker et al., Orleans Appeal, No. 7402, Unreported (February 13, 1919, cert. den. May 9, 1919— 2 Peltier’s Orleans Appeals 80) required a different holding, and they felt constrained to follow their interpretation of those decisions which was to the effect that when stage or progress payments are provided for in an otherwise indivisible building contract, and when the owner makes such payments, there arises a presumption of delivery and acceptance of the then completed portion of the work so as to place on the owner the risk of loss thereof pending performance of the entire contract.

We agree with the Court of Appeal’s conclusion that the obligation here was an indivisible one and that it did not constitute two obligations to do two different things. Under it, for a stipulated price, the contractor was obliged to construct and deliver a completed swimming pool — not to build a shell for a price and to finish a shell at another price.

Divisible and indivisible contracts are dealt with in the Revised Civil Code Articles 2108-2116. Specifically, the first two of these articles provide: “Divisible or indivisible — Distinguishing features.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kirshner v. Johnson
521 So. 2d 697 (Louisiana Court of Appeal, 1988)
Jefferson Parish School Bd. v. Rowley Company, Inc.
305 So. 2d 658 (Louisiana Court of Appeal, 1974)
Moak v. Link-Belt Company
229 So. 2d 395 (Louisiana Court of Appeal, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
170 So. 2d 360, 247 La. 158, 1964 La. LEXIS 2851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-w-investment-company-v-otis-w-sharp-son-inc-la-1964.