Jefferson Parish School Bd. v. Rowley Company, Inc.

305 So. 2d 658
CourtLouisiana Court of Appeal
DecidedDecember 30, 1974
Docket6460
StatusPublished
Cited by18 cases

This text of 305 So. 2d 658 (Jefferson Parish School Bd. v. Rowley Company, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jefferson Parish School Bd. v. Rowley Company, Inc., 305 So. 2d 658 (La. Ct. App. 1974).

Opinion

305 So.2d 658 (1974)

JEFFERSON PARISH SCHOOL BOARD
v.
ROWLEY COMPANY, INC., and Louisiana Joint Underwriters of the Audubon Insurance Co.

No. 6460.

Court of Appeal of Louisiana, Fourth Circuit.

December 30, 1974.
Rehearings Denied January 14, 1975.

*659 Jack A. Grant, Gretna, for Jefferson Parish School Board, plaintiff-appellant.

Rene R. Nicaud, Nicaud, Justrabo & Rousset, New Orleans, for Rowley Co., *660 Inc., defendant-appellee; Hugh H. Brister, New Orleans, of counsel.

William A. Porteous, III, William W. Miles, Porteous, Toledano, Hainkel & Johnson, New Orleans, for Louisiana Joint Underwriters of the Audubon Ins. Co., defendant-appellant.

Before SAMUEL, REDMANN and BOUTALL, JJ.

BOUTALL, Judge.

The Jefferson Parish School Board brought suit against Rowley Co., Inc. under terms of a contract wherein Rowley was to furnish and install science equipment in West Jefferson High School. After the equipment was delivered, but before it was installed, a fire destroyed a portion of the equipment worth $36,148.15. The School Board seeks recovery of this amount alleging that Rowley has refused to replace the damaged science equipment at no cost to plaintiff, and that Rowley failed to provide any builder's risk and fire insurance, all as provided for in the contract between them. Alternatively, the School Board sues to recover the amount from Louisiana Joint Underwriters of the Audubon Insurance Company, the fire insurer of the School Board under a policy covering the buildings and contents of all of the schools in Jefferson Parish. Both defendants answered denying liability, and additionally Rowley Co., Inc. sought a judgment in reconventional demand against the School Board for the balance due it under the contract as well as for other equipment sold by it to the School Board unrelated to this matter, for which the School Board withheld payment. These sums withheld equal the amount sought by plaintiff.

Each of the three parties have filed motions for summary judgment, and all of the motions were taken up at the same time. The School Board sought summary judgment against both Rowley and Audubon; Rowley sought judgment against the School Board dismissing its suit and granting Rowley's reconventional demand; Audubon sought dismissal of the School Board's suit. The trial court granted summary judgment to the School Board against Audubon for the amount prayed, and also granted summary judgment to Rowley against the School Board dismissing plaintiff's suit and awarding Rowley the sum prayed for in reconventional demand. The motion for summary judgment (together with an exception of no right or cause of action on the same basis) of Audubon was dismissed. The decree does not make specific adjudication of the School Board's motion for summary judgment against Rowley although the Reasons for Judgment indicate that it was intended that that motion should be dismissed. Suspensive appeals were subsequently taken by the School Board and by Audubon.

Under the procedural posture in which this appeal reaches us, we cannot arrive at a final adjudication of the rights of the parties. Although we are informed by all of the parties that there is no dispute as to essential facts, we find a serious dispute as to essential facts in this record and conclude that summary judgment is not appropriate herein.

The undisputed facts are these. The Jefferson Parish School Board was in the process of making alterations at West Jefferson High School, and in accordance with these intentions advertised publicly for bids as required by R.S. 38:2211 for the furnishing and installation of certain science equipment specified for certain science laboratory classrooms. Both detailed and general specifications were provided. Three bids were received. The lowest was the Hamilton Manufacturing Company whose bid was rejected because it qualified the delivery dates required. The next lowest bid of Rowley was accepted. The bid of Rowley was as follows:

"BASE BID:

"For all Science Equipment, and Furnishings for West Jefferson High *661 School, Complete, in accord with the DRAWINGS, SPECIFICATIONS, and CONTRACT DOCUMENTS for the LUMP SUM of Sixty-Nine thousand, eight hundred two and 00/100 DOLLARS ($69,802.00) Drexel as specified.

Although the contract documents furnished include a formal contract proposed to be signed, no contract was signed. Instead, the School Board issued a signed Purchase Order to Rowley containing the following inscriptions:

"Science Equipment and Furnishings as per bid of June 19, 1972. $69,802.00 ========== *Completion of all work required between September 1, 1972 and September 15, 1972."

Thereafter Rowley delivered the equipment and was in the process of installing the equipment in the school. On November 15, 1972, it forwarded its invoice of $52,820.00 to the School Board as its first request for payment on the contract. On November 17, 1972, there was a fire in the school, the cause of which is unknown, and some of the equipment furnished was damaged and destroyed. For some unexplained reason, the School Board later paid the invoice in question. This suit followed.

It is apparent that the plaintiff School Board is entitled to recover the amount of its loss, either from the defendant Rowley or from the defendant Audubon Insurance Company, or perhaps both. Audubon had in full force and effect a policy of fire insurance covering all of the contents of West Jefferson High School, as well as other schools, and if it is determined that the School Board is indeed the owner of the equipment delivered therein by Rowley, then Audubon must pay under its policy provisions. On the other hand, the contract documents require Rowley to bear the risk of loss.

The trial court accepted the contention of Rowley, and the alternate contention of the School Board, that the contract between Rowley and the School Board was a contract of sale, hence the title to the property had passed to the School Board upon its delivery by Rowley to the School Building. L.C.C. Art. 2456. However, we do not consider that the labeling of the agreement between the parties as that of a sale or that of a construction contract or other contract is the controlling issue between the parties. The controlling issue is that, whatever it may be called, if there was a binding contract between the parties, did that contract provide for risk of loss in the factual circumstances here?

It has been argued to us that the general law pertaining to sales provides that under the factual circumstances related above, the School Board became the owner and thus bore the risk of loss. Louisiana Civil Code Articles 2467, 2468, 2475, 2477, 2478, 1908; Hunt v. Suares, 9 La. 434 (1836); Vico Concrete Company, Inc. v. Antley, 283 So.2d 830 (La.App. 2d Cir. 1973). As opposed to this the appellants contend that this is a contract of construction and thus governed under the provisions of L.C.C. Arts. 2756, 2757, 2758, with the risk of loss being borne by the contractor. Kegler's, Inc. v. Levy, 239 So.2d 450 (La.App. 4th Cir. 1970). See also S & W Investment Co. v. Otis W. Sharp & Son, Inc., 247 La. 158, 170 So.2d 360 (1964). We do not attempt in our consideration to decide which of these two principles should be applied here because of the procedural status.

This matter comes before us on appeal from motion for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Trahan v. Morton International, Inc.
493 F. App'x 571 (Fifth Circuit, 2012)
Lebovitz v. Sheraton Operating Corp.
868 So. 2d 164 (Louisiana Court of Appeal, 2004)
In re Medical Review Panel of Morris
802 So. 2d 999 (Louisiana Court of Appeal, 2001)
Coates v. Anco Insulations, Inc.
786 So. 2d 749 (Louisiana Court of Appeal, 2001)
Hebert v. St. Paul Fire and Marine Ins.
757 So. 2d 814 (Louisiana Court of Appeal, 2000)
Gordon v. Southern United Fire Ins. Co.
679 So. 2d 582 (Louisiana Court of Appeal, 1996)
Osborne v. Vulcan Foundry, Inc.
675 So. 2d 837 (Louisiana Court of Appeal, 1996)
Bailey v. United Gas Pipe Line Co.
665 So. 2d 664 (Louisiana Court of Appeal, 1995)
Davidson v. Pan American Life Insurance Co.
637 So. 2d 1276 (Louisiana Court of Appeal, 1994)
Downtown Parking Service, Inc. v. Hyman
635 So. 2d 282 (Louisiana Court of Appeal, 1994)
Dibos v. Bill Watson Ford, Inc.
622 So. 2d 677 (Louisiana Court of Appeal, 1993)
Conrad v. Doe
545 So. 2d 677 (Louisiana Court of Appeal, 1989)
Hare v. Ganaway Construction Co.
536 So. 2d 722 (Louisiana Court of Appeal, 1988)
Thibodeaux v. Southwest La. Hosp. Ass'n
488 So. 2d 743 (Louisiana Court of Appeal, 1986)
Sharpe v. Claiborne Enterprises, Inc.
461 So. 2d 591 (Louisiana Court of Appeal, 1984)
Watson v. Cook
427 So. 2d 1312 (Louisiana Court of Appeal, 1983)
Adam G. Nunez v. The Superior Oil Company
572 F.2d 1119 (Fifth Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
305 So. 2d 658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jefferson-parish-school-bd-v-rowley-company-inc-lactapp-1974.