S. & W. Investment Co. v. Otis W. Sharp & Son, Inc.

162 So. 2d 171, 1964 La. App. LEXIS 1454
CourtLouisiana Court of Appeal
DecidedMarch 2, 1964
DocketNo. 1279
StatusPublished
Cited by2 cases

This text of 162 So. 2d 171 (S. & W. Investment Co. v. Otis W. Sharp & Son, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. & W. Investment Co. v. Otis W. Sharp & Son, Inc., 162 So. 2d 171, 1964 La. App. LEXIS 1454 (La. Ct. App. 1964).

Opinions

REGAN, Judge.

Plaintiff, the S. & W. Investment Co., Inc., instituted this suit against the defendant, Otis W. Sharp & Son, Inc., endeavoring to recover the sum of $2,174.95, representing the cost to repair and complete a damaged swimming pool located in the patio of plaintiff’s motel. Plaintiff explained therein that the shell of the pool floated and cracked following a heavy rainfall as a result of the defendant’s negligence in installing a defective hydrostatic relief valve that failed to permit underground water to enter the empty shell, which in turn caused the external water pressure to push the shell out of the ground.

The defendant answered and asserted that the shell was properly constructed, accepted and paid for by the plaintiff and it was ultimately damaged because plaintiff, as the owner of the partially completed work, omitted to fill the pool with water in conformity with its instructions. Defendant asserted that the pool was to be constructed in two stages. Initially, the shell was to be completed, and after plaintiff had erected the surrounding motel buildings, the contract then required the defendant to complete the pool.

From a judgment awarding plaintiff $2,-174.95, the defendant has prosecuted this appeal.

On September 12, 1961, the defendant contracted to build a swimming pool in the patio of the plaintiff’s motel, which was then under construction, for $4,725.00. The agreement provided in part:

“ARTICLE 1 — SCOPE OF WORK — The Contractor shall furnish all of the material and perform all of the work for the construction of a swimming pool * * *.
* * *
“ARTICLE 3 — PROGRESS PAYMENTS 1 * * * Upon completion [173]*173of shell (which is all but filter, deck equipment, tile brick, plumb line to building, and interior finish) amt. due $3,000. Remainder due upon completion of pool.”

It was noted in the contract that the owner was obligated to excavate the pool site, remove the excavated material and place backfill around the completed shell.

The reason for the two-stage construction of the pool was to permit heavy equipment access to the site thereof before buildings were erected around the pool. In addition thereto, the plaintiff did not wish to risk damaging the decorative tiling and other pool appurtenances when the buildings were in the process of being erected; therefore, the parties agreed that the finishing touches would be added when the buildings were Completed.

On October 12, 1961, the shell was completed; therefore, the defendant’s workmen and equipment were removed from the job. During the next five days, the plaintiff’s workmen installed the backfill between the top of the shell and the excavation remaining around its sides. While the backfilling was in progress, Robert Choppin, one of defendant’s workmen, returned to the job site in order to ascertain that the bulldozer being used would not damage the water line which extended from the pool to the building. On this occasion he closed the hydrostatic relief valve, connected a garden hose and began filling the pool with water. He estimated that the pool would require two or three days to fill if the water was permitted to run continuously. He stated that he left, returned later and found that the water had been turned off and the hose disconnected. He again connected the hose and resumed filling the shell. Before he left the job, he said he informed the plaintiff’s agents to fill the pool before disconnecting the hose.

On October 20, 1961, defendant sent an invoice for $3,000.00 to Dave Wolzinger, plaintiff’s chairman of the board, which was paid a short time thereafter.

On November 13, 1961, following a heavy rainfall, a large quantity of water found its way under the shell of the pool, causing it to float and crack. The underground water exerted excessive pressure on the empty shell, ultimately uprooting the shallow end of the pool, which caused the shell to appear similar to a large tilted bathtub.

The testimony is conflicting as to whether the defendant’s agents instructed plaintiff’s chairman of the board, Dave Wol-zinger, and its construction superintendent, to fill the shell in order to prevent the floating thereof. Roger Sharp, the defendant’s secretary-treasurer, and Choppin both testified that Wolzinger and Justin Spiehler, construction superintendent, had been informed to fill the shell with water to prevent the possible floating thereof. Both Wol-zinger and Spiehler deny they were so advised ; however, Spiehler admitted he knew it was necessary to keep the shell filled with water, but he failed to explain why this was not done.

It is also disputed whether the pool would have floated had the shell remained empty with the valve open. George Legardeur, Jr., an expert in the field of civil engineering, related that the pool was a floating type with a hydrostatic valve installed in the base. Had the valve been open, he explained, the ground water along the exterior walls possibly would have entered the pool through the valve, thus equalizing the interior and exterior pressure. However, he did concede that the best method for insuring against floating of the pool was to fill the shell thereof with water.

A. C. Cross, president of A. C. Cross Pool Service, Inc., which is a company engaged in repair and maintenance service, testified that he had encountered instances where pools had floated despite the fact that the hydrostatic relief valve was permitted to remain open. In those instances, he explained, the underground water did [174]*174not flow into the interior rapidly enough to relieve the greater external pressure. He concluded that the defendant’s method of filling the pool was the safest way of preventing it from floating. Defendant’s agent, Roger Sharp, testified substantially to the same effect.

Therefore, while the experts disagree on the effectiveness of an open hydrostatic valve, they all did agree that the most foolproof method to avoid floating was to fill the shell with water.

In any event, the defendant was called to salvage the shell on the day it floated. His efforts were unsuccessful and plaintiff finally employed the services of Family Pools to repair the shell and complete the pool at a cost of $3,899.95. When the shell was damaged plaintiff was still obligated for an additional $1,725.00, if the defendant had completed the pool without incident. Therefore, the plaintiff deducted this amount from the total contract price with Family Pools.

The whole tenor of the record leads us to the inevitable conclusion that the plaintiff’s agent was fully aware of the fact that the pool should have been filled with water, whether he knew it of his own knowledge or was so informed by the defendants; therefore, the ultimate question posed for our consideration is who must bear the loss of this partially completed work.

Plaintiff’s counsel argues primarily that the parties had contracted for the construction of a swimming pool. He insists that the payment of $3,000.00 upon completion of the shell of the pool did not relieve the contractor of the responsibility of preserving the work until the entire pool was completed, and the risk of loss, therefore, must be borne by the contractor until the pool was finally completed and accepted by the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S & W INVESTMENT COMPANY v. Otis W. Sharp & Son, Inc.
170 So. 2d 360 (Supreme Court of Louisiana, 1964)
S. & W. Investment Co. v. Otis W. Sharp & Son, Inc.
164 So. 2d 359 (Supreme Court of Louisiana, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
162 So. 2d 171, 1964 La. App. LEXIS 1454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-w-investment-co-v-otis-w-sharp-son-inc-lactapp-1964.