N. Levy & Son v. Paquette

80 So. 269, 144 La. 244, 1918 La. LEXIS 1731
CourtSupreme Court of Louisiana
DecidedDecember 2, 1918
DocketNo. 23138
StatusPublished
Cited by4 cases

This text of 80 So. 269 (N. Levy & Son v. Paquette) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N. Levy & Son v. Paquette, 80 So. 269, 144 La. 244, 1918 La. LEXIS 1731 (La. 1918).

Opinion

Statement of the Case.

MONROE, C. J.

This ease has been brought up for the review of a judgment rendered by the Court of Appeal, First circuit, maintaining a seizure, by attachment, of some 2,500 concrete piles which had been manufactured by J. J. Paquette and O. R. Mongeau, and by them delivered on the lake shore front of the town of Mandeville, where all save about 50 of them were accepted by the town council (the 50 thus mentioned having been accepted at another place and subsequently delivered on the lake front); which council had thereupon made a payment to Paquette & Mongeau, and their subrogee, of $10,000, with the understanding and intention that the piles so delivered and accepted Mongeau) had contracted with the town to were to be used in the construction of a sea wall on said front, which they (Paquette & construct, and which, at the time of the seizure, they had partly constructed.

The attachment was issued at the instance of plaintiff herein, a commercial firm composed of Mrs. N. Levy and H. H. Levy, who sued J. J. Paquette and the town of Mandeville, for $356.28, as a balance alleged to be due for goods, wares, and merchandise sold to Paquette, and by him used in the construction of the wall and the carrying on of the contract above mentioned; it being alleged that the town became liable in solido with Paquette by reason of its' failure to record the contract and to execute a bond, “as required by law,” and that plaintiff is entitled, as a "furnisher of supplies,” to a lien and privilege on the wall; also that the town has released Mongeau, and that Paquette has become “the sole principal under said contract”; upon which allegations (as to the lien and privilege) plaintiff caused a writ of sequestration to issue, and the piles, together with certain implements, used in the execution of the contract were seized under both writs. The sequestration was thereafter dissolved, in a proceeding by rule, and plaintiff, acquiescing, has abandoned its claim to any lien or privilege, save such as may have resulted from the seizure by attachment, as also its claim for a judgment in money against the town. The affidavit for the attachment was made on December 3, 1915, and sets forth, among other things, that Paquette had left the state permanently, and resides in Mississippi, and that he is concealing himself to avoid being cited and forced to answer to the suit intended to be brought against him. The seizure Was made on December 4, 1915. The sole question here presented for decision is whether the piles in question were subject to seizure, at the suit of Paquette’s ordinary creditor, to the prejudice of the right therein which is asserted by the town.

It appears from the evidence that the contract between Paquette and Mongeau (hereafter called contractors) and the town of Mandeville (hereafter called town) was entered into on May 1, 1914, and that the contractors thereby agreed as follows:

“To provide all the material and perform all the work for the building and completion of a 7,000-foot sea wall along the beach front of the town,” according to certain specifications and under the direction of a superintend* ent to be named by the town.
“Art. 5. Should the contractors, at any time, refuse or neglect to supply a sufficiency of [247]*247properly skilled workmen, or of materials of the proper quality, or fail ip any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, the town shall be at liberty, after three days’ written notice to the contractors, to provide such labor and material, and to deduct the cost [from the amount] then due, or to become due thereafter, to the contractors * * «; and if the superintendent shall certify that such refusal, neglect, or failure is sufficient ground for such action, the town shall be [authorized] to terminate the employment of the contractors for the work, and enter upon the premises and take possession, for the purpose of completing' the work included in this contract, of all material, tools, and appliances thereon, and to employ any other person to finish the work, and. to provide the materials therefor; and, in case of such discontinuance of the employment of the contractors, they shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the town in finishing the work, such excess shall be paid by the town to the contractors, but, if such expense shall exceed such unpaid balance, the contractors shall pay the difference to the town. The expense incurred by the town, as herein provided for, cither for furnishing materials or for finishing the work, and any damage incurred through such default, shall bo audited and certified by the superintendent, whose certificate thereof shall he conclusive upon the parties.
“Art. 6. The contractors shall complete the several portions of the work comprehended in this agreement by and at the times hereinafter stated, to wit, the whole work under this contract shall be completed on or by January 1, 1915 ” (subsequently extended to January 1, 1916).
Article 8 fixes the price to be paid by the town at $28,000, “less $1.60 per lineal foot, for which the contractors are to look to the property holders, but which amount is to he paid by the town for all streets crossed; all payments by the town to be made in current funds, upon the certificates of the superintendent, as follows: Ton thousand ($10,000.00) dollars to be paid when the piles are made; $1,000.00 at the completion of each block of 550 feet, more or less, less the $1.60 per lineal foot frontage, which the contractors are to collect from the property holder or holders and town, as hereinabove specified. The final payment shall be made within ten days after the completion of. the work included in this contract ; provided, that the contractors shall furnish proper certificates that all claims for material and labor or damage arising out of the contract, for which, the contractors are sought to be made liable, have been paid, or their claims satisfied; otherwise final payment to be held up, or a sufficient portion thereof as may be necessary to satisfy such outstanding claims.
“Art. 9. It is further agreed * * * that no certificates given in payment under this contract, except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, and that no payment shall be construed to (be) an acceptance of defective work or improper materials.
“Art. 10. The contractors shall, during the progress of the work, maintain cyclone or storm insurance on said work, the policies to cover all the work incorporated and all materials for the same on or about the ground, and shall be made payable to the parties hereto as their interests may appear,’’ etc.

On October 24, 1914, the contractors, by a written instrument, to which the mayor of the town and Peter Jung were parties, agreed that, in consideration of advances made and to be made by Jung for the making of the piles and the payment and liquidation of pressing bills and obligations contracted in connection therewith, Jung should be, and was, subrogated to their rights with respect to the $10,-000 which, according to the contract, were to be paid upon the making of the piles.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moak v. Link-Belt Company
229 So. 2d 395 (Louisiana Court of Appeal, 1970)
S & W INVESTMENT COMPANY v. Otis W. Sharp & Son, Inc.
170 So. 2d 360 (Supreme Court of Louisiana, 1964)
S. & W. Investment Co. v. Otis W. Sharp & Son, Inc.
162 So. 2d 171 (Louisiana Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
80 So. 269, 144 La. 244, 1918 La. LEXIS 1731, Counsel Stack Legal Research, https://law.counselstack.com/opinion/n-levy-son-v-paquette-la-1918.