S & D Mechanical Contractors, Inc. v. Enting Water Conditioning Systems, Inc.

593 N.E.2d 354, 71 Ohio App. 3d 228, 1991 Ohio App. LEXIS 921
CourtOhio Court of Appeals
DecidedMarch 4, 1991
DocketNo. 12272.
StatusPublished
Cited by38 cases

This text of 593 N.E.2d 354 (S & D Mechanical Contractors, Inc. v. Enting Water Conditioning Systems, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S & D Mechanical Contractors, Inc. v. Enting Water Conditioning Systems, Inc., 593 N.E.2d 354, 71 Ohio App. 3d 228, 1991 Ohio App. LEXIS 921 (Ohio Ct. App. 1991).

Opinion

Wolff, Judge.

This case involves an appeal and a cross-appeal. Defendant-appellant and cross-appellee, Enting Water Conditioning Systems, Inc. (“Enting”), appeals from the judgment rendered in favor of plaintiff-appellee and cross-appellant, S & D Mechanical Contractors, Inc. (“S & D”), on S & D’s breach of contract claim against Enting. S & D cross-appeals from the trial court’s refusal to grant it certain damages to which S & D claims it is entitled as part of its compensatory damages.

S & D is a mechanical contractor which entered into a general contract on February 4,1983, with the Veterans Administration Medical Center (“VA”) to replace the boiler system at the VA’s Indianapolis facility. S & D then entered into a subcontract with Enting on February 25, 1983, under which Enting was to provide all water softening and dealkalizer equipment for the VA project.

The purpose of the dealkalizer was to remove alkaline impurities, which caused the equipment to rust, from the water before it was fed to the boiler. The impurities were removed by a resin exchange process. During this process, water would flow into the dealkalizer and over a resin. The resin would then trap the alkaline materials before the water would flow into the boiler. The resin would then be flushed from the dealkalizer by a regeneration process.

As part of the general contract, the VA provided S & D with a set of written specifications which set out the requirements for the dealkalizer system. These specifications, contained in section 323 of the contract, were accompanied by a set of architect’s drawings. Section 323 contained both performance requirements and system requirements. The performance requirements pertained to the dealkalizer equipment itself and required the contractor to assure that the equipment would properly function under the designated operating conditions. The system requirements related to the operating conditions under which the dealkalizer had to perform. At issue herein are two of the system requirements: one, that the dealkalizer had to be capable of delivering 28,000 gallons of water to the boiler between regenerations; two, that the system had to provide no less than seventeen cubic feet of exchange resin. The system needed at least this amount of resin in order to have the capacity to remove 20,000 grams of alkaline substance per cubic foot. *232 This removal rate would then enable the dealkalizer to deliver the requisite 28,000 gallons of water between regenerations.

The architect’s drawings provided a floor plan of the entire VA facility, in addition to a schematic of the boiler system. That portion of the floor plan pertinent to the dealkalizer diagrammed three circles which were identified on the floor plan under the general heading of dealkalizer. There was no other information in the floor plan which related to the dealkalizer other than the general heading above the circles. Both section 323 and the architectural drawings were incorporated into the terms of Enting’s subcontract.

Although the written specifications did not so require, Enting designed a two tank system. Each tank had a resin capacity of seventeen cubic feet, yielding a total resin capacity of thirty-four cubic feet. Notwithstanding the fact that Enting’s system had twice the minimum resin capacity required, the system was incapable of satisfying the 28,000 gallon requirement. Enting’s system was undersized by one-third. This caused the dealkalizer to regenerate every 18,000 gallons. Moreover, the dealkalizer failed to provide the minimum resin removal exchange capacity of 20,000 grams per cubic foot. It was undisputed that there was no manufactured resin on the market that could satisfy this removal requirement. In fact, there was no resin on the market that could satisfy more than two-thirds of the requirement. Thus, any dealkalizer would at least be one-third undersized with respect to this requirement. Therefore, a portion of the written specifications was faulty and incapable of being satisfied.

Because of the system’s deficiencies, the VA refused to accept the system. S & D eventually contracted with Peck Water Systems to replace the system installed by Enting with a system satisfactory to the VA.

S & D sued Enting for breach of contract. The matter was heard by the referee who found in favor of Enting on the basis that the contract created a design specification which imposed responsibility for the system’s shortcomings upon the VA. The referee determined that since the contract was design in nature, Enting could not be liable for the system’s deficiencies which were due in part to the faulty written specifications. The referee further found that Enting had no contract liability since it had, in all other respects, substantially complied with the contract requirements which it had undertaken to meet under its subcontract with S & D.

S & D objected to the referee’s report. The trial court refused to adopt the referee’s report. The court found that rather than creating a design specification, the contract created a performance specification which placed the design responsibility upon S & D, and Enting, by virtue of Enting’s subcontract with S & D to install the system, and not upon the VA. By so determining, the *233 liability for the system’s deficiencies was placed on S & D vis-a-vis the VA, and on Enting vis-á-vis S & D. Accordingly, the court found for S & D, awarding it over $40,000 in damages it incurred in curing the system’s deficiencies. Enting advances the following assignments of error:

“I. The referee properly concluded that the agreement between the parties more closely resembled a ‘design’ than a ‘performance’ specification. The trial court erred in finding otherwise.

“II. The trial court’s assessment of $40,111.89 for damages was excessive.”

In its first assignment, Enting argues that the trial court erred by construing the terms of the contract as creating a performance specification instead of a design specification, thereby making Enting liable to S & D (who was in turn liable to the VA) for the system’s deficiencies. This assignment presents us with a question of whether the finding of performance specification was against the manifest weight of the evidence.

The trial court held that the determination of the type of specification called for in the contract between the VA and S & D, i.e., performance or design, was critical in assessing liability for the dealkalizer's deficiencies. We agree because the characterization of the specification dictated whether S & D was obligated to the VA to produce a satisfactory system. If S & D was so obligated to the VA, S & D’s subcontractor, Enting, was liable to S & D if the system it installed was unsatisfactory.

If a specification provides explicit instructions which tell the contractor exactly how the contract is to be performed and no deviation from the instructions is permissible, then the specification is design in nature. Dewey Electronics Corp. v. United States (Fed.Cir.1986), 803 F.2d 660, 658. If, on the other hand, the specification seeks an end result and leaves the determination as to how the result is to be obtained to the contractor, then the specification is performance in nature. Stuyvesant Dredging Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dornette v. Green Bldg. Consulting, L.L.C.
2025 Ohio 4944 (Ohio Court of Appeals, 2025)
FabMetals, Inc. v. Stratacache, Inc.
2024 Ohio 2006 (Ohio Court of Appeals, 2024)
Estate of Cruz v. Peffley
2023 Ohio 2081 (Ohio Court of Appeals, 2023)
Horn v. Cherian
2023 Ohio 931 (Ohio Court of Appeals, 2023)
Rayco Mfg., Inc. v. Murphy, Rogers, Sloss & Gambel
2019 Ohio 3756 (Ohio Court of Appeals, 2019)
Ineos USA L.L.C. v. Furmanite America, Inc.
2014 Ohio 4996 (Ohio Court of Appeals, 2014)
DeVries Dairy, LLC v. White Eagle Cooperative Ass'n
25 F. Supp. 3d 1039 (N.D. Ohio, 2014)
Dollar Bank Leasing Co. v. Elms Country Club
2013 Ohio 2974 (Ohio Court of Appeals, 2013)
Shelly Co. v. Karas Properties, Inc.
2012 Ohio 5416 (Ohio Court of Appeals, 2012)
Boyd v. Cogan
2012 Ohio 1604 (Ohio Court of Appeals, 2012)
Abroms v. Synergy Bldg. Sys.
2011 Ohio 2180 (Ohio Court of Appeals, 2011)
Lucky Discount Lumber Co. v. MacHine Tools of America
907 N.E.2d 1222 (Ohio Court of Appeals, 2009)
Chase Home Finance v. Smith, 2007-P-0097 (10-17-2008)
2008 Ohio 5451 (Ohio Court of Appeals, 2008)
Mildred Hine Trust v. Buster, 07ap-277 (12-27-2007)
2007 Ohio 6999 (Ohio Court of Appeals, 2007)
American Zurich Insurance v. Cooper Tire & Rubber Co.
465 F. Supp. 2d 827 (N.D. Ohio, 2006)
King v. Hazen, Unpublished Decision (9-15-2006)
2006 Ohio 4823 (Ohio Court of Appeals, 2006)
Griffiths v. Airko, Unpublished Decision (6-22-2006)
2006 Ohio 3152 (Ohio Court of Appeals, 2006)
Chang v. Brethren Mutual Insurance
897 A.2d 854 (Court of Special Appeals of Maryland, 2006)
Warne v. Bamfield, Unpublished Decision (2-23-2006)
2006 Ohio 850 (Ohio Court of Appeals, 2006)
Midam Bank v. Dolin, Unpublished Decision (6-30-2005)
2005 Ohio 3353 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
593 N.E.2d 354, 71 Ohio App. 3d 228, 1991 Ohio App. LEXIS 921, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-d-mechanical-contractors-inc-v-enting-water-conditioning-systems-ohioctapp-1991.