Dornette v. Green Bldg. Consulting, L.L.C.

2025 Ohio 4944
Ohio Court of Appeals·Decided October 29, 2025·No. C-240689·Published

Opinion

[Cite as Dornette v. Green Bldg. Consulting, L.L.C., 2025-Ohio-4944.]

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

DAVID DORNETTE, : APPEAL NO. C-240689 TRIAL NO. 24/CV/06262 Plaintiff-Appellant, :

vs. :

JUDGMENT ENTRY

GREEN BUILDING CONSULTING LLC, :

Defendant, :

and : REDKNOT HOLDINGS, LLC, :

Defendant-Appellee. :

This cause was heard upon the appeal, the record, the briefs, and arguments.

For the reasons set forth in the Opinion filed this date, the judgment of the trial court is affirmed.

Further, the court holds that there were reasonable grounds for this appeal, allows no penalty, and orders that costs be taxed under App.R. 24.

The court further orders that (1) a copy of this Judgment with a copy of the Opinion attached constitutes the mandate, and (2) the mandate be sent to the trial court for execution under App.R. 27.

To the clerk: Enter upon the journal of the court on 10/29/2025 per order of the court.

By:_______________________ Administrative Judge

[Cite as Dornette v. Green Bldg. Consulting, L.L.C., 2025-Ohio-4944.]

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

DAVID DORNETTE, : APPEAL NO. C-240689 TRIAL NO. 24/CV/06262 Plaintiff-Appellant, :

vs. :

OPINION

GREEN BUILDING CONSULTING LLC, :

Defendant, :

and : REDKNOT HOLDINGS, LLC, :

Defendant-Appellee. :

Civil Appeal From: Hamilton County Municipal Court Judgment Appealed From Is: Affirmed Date of Judgment Entry on Appeal: October 29, 2025

Taft Stettinius & Hollister LLP, Nicholas J. Pieczonka and William E. Braff, for Plaintiff-Appellant,

Schwander Law Firm LLC and Nicholas W. Schwandner, for Defendant-Appellee.

MOORE, Judge.

{¶1} Plaintiff-appellant David Dornette appeals the trial court’s judgment denying his motion for summary judgment and granting the cross-motion for summary judgment in favor of defendant-appellee Redknot Holdings, LLC (“Redknot”), arguing that his claim for replevin against Redknot was not barred by the parties’ previous settlement agreement. The settlement agreement, however, explicitly provided that each party released the other from future claims.

{¶2} Dornette also challenges the trial court’s judgment granting Redknot’s request for attorney’s fees on Redknot’s crossclaim against Dornette for breaching the settlement agreement, arguing that the American Rule requires each party to cover their own attorney’s fees. The trial court, however, awarded the fees as compensatory damages, not as costs.

{¶3} We, therefore, affirm the trial court’s judgment.

I. Factual and Procedural History

{¶4} Dornette contracted (the “Construction Contract”) with Redknot to build a house (the “Property”). Redknot then hired defendant Green Building Consulting LLC (“GBC”) to perform work on the Property to obtain a certification for a “platinum LEED for Homes Rating” (“LEED”). The section of the Construction Contract pertaining to this certification stated that there was a consulting fee that covered payment for the LEED registration fee, necessary documentation services, payment of the certification fee, and “ordering and delivery of certificates.” It also stated that the price to build the home did not include the cost for making modifications to the Property that may be required to obtain the LEED certification. The section further stated: “While [Redknot] will work diligently to obtain the LEED [Redknot] makes no guarantees that the desired LEED certification level will be

obtained.”

A. The Dispute, Arbitration, and the Settlement Agreement

{¶5} A dispute arose between the parties. Dornette asserted the construction of the Property was defective. Redknot, in turn, claimed that Dornette stopped paying for its work.

{¶6} In April 2023, Dornette filed a demand for arbitration. Redknot responded by filing a counterclaim in the arbitration. In May 2023, Redknot recorded a mechanic’s lien against the Property. Prior to the arbitration hearing, the parties engaged in mediation.

{¶7} The mediation was successful, and in January 2024, Redknot and Dornette executed a settlement agreement that “resolve[d] all disputes between them related to or arising from the Contract, Property, Project, Dispute, Lien, and Arbitration,” and the parties agreed to dismiss their respective arbitration actions with prejudice. The settlement agreement contained a release clause, which provided that the parties bore no further financial responsibility to one another, and each were to bear their own attorney’s fees, costs, and expenses. Dornette agreed to release Redknot of all “claims, demands . . . breaches of contract, litigation, causes of action, warranties, breaches of duty or any relationship . . . whether sounding in law, equity, contract . . . past, present and future.” Likewise, Redknot agreed to release Dornette of the same. Redknot, however, was not released “from any latent defects or latent warranty items on the Property.”

{¶8} The release applied to the parties’ respective partners, employees, agents, representatives, subsidiaries, affiliated business entities, etc. The agreement provided, “This release shall not apply to any breach of this Agreement, which claims are reserved.” The agreement also contained an integration clause that stated that the

document constituted the entire agreement between the parties, and any amendments to the agreement must be made in a separate writing.

{¶9} Prior to the conclusion of the arbitration, Dornette requested the LEED materials from GBC. Dornette received an e-mail from GBC in August 2023, which stated:

Good afternoon Dan!

Apologies for the delay in response. I think I may have already mentioned, but Redknot has authorized us to use/share the information we already have on file to close out this project, including the data from the pre-drywall inspection. Are you still intending to hit Platinum?

Please fill out and send back this info sheet so Accounting (copied) can get the revised contract out and set up the new billing party in our system.

I’ve also copied Kristi O’Conner, who will be managing the remainder of this project. Upon receipt of the updated agreement, we will release all of the relevant project documentation and set up a quick call to run through the current path on the checklist, then we should schedule the final inspection to see where the project stands for corrections or points needed.

B. Dornette files a claim for replevin.

{¶10} After the settlement agreement was executed, Dornette again requested the LEED materials—this time from Redknot, which refused the request. In March 2024, Dornette filed a claim in the Hamilton County Municipal Court for replevin against Redknot and GBC regarding the LEED materials. On July 15, 2024, Dornette voluntarily dismissed his complaint against GBC without prejudice.

{¶11} Dornette asserted in his complaint against Redknot that he paid for the LEED materials, and thus, he was entitled to them. Paragraph 18 of the complaint listed the materials Dornette sought:

[GBC] performed this work and is in possession of the LEED certification materials, including but not limited to: registration documents, preliminary sustainable design strategy evaluations, design investigation and strategy development documents, confirmed sustainable design strategy documents, sustainable design integration documents, design documents, LEED inspection reports, LEED progress reports, LEED checklists, LEED certifications, LEED energy modeling, and energy modeling-reports.

{¶12} Redknot filed an answer and counterclaim against Dornette, alleging that Dornette breached the settlement agreement by filing his claim for replevin, which was a failure to act in good faith and fair dealing and caused Redknot to incur attorney’s fees, costs, and expenses.

The parties file cross-motions for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Dornette v. Green Bldg. Consulting, L.L.C., 2025 Ohio 4944 (Ohio Ct. App. 2025).

2025 Ohio 4944 (Dornette v. Green Bldg. Consulting, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Griffith v. Chelsea Condominimum
2026 Ohio 928 (Ohio Court of Appeals, 2026)
In re Q.R.
2026 Ohio 341 (Ohio Court of Appeals, 2026)