Ryan Companies US, Inc. v. FDP WTC, LLC

Court of Appeals of Iowa·Decided October 6, 2021·No. 20-1366·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 20-1366 Filed October 6, 2021

RYAN COMPANIES US, INC., Plaintiff-Appellee,

vs.

FDP WTC, LLC, Defendant-Appellant. ________________________________________________________________

Appeal from the Iowa District Court for Black Hawk County, David P.

Odekirk, Judge.

FDP WTC, LLC appeals a ruling in favor of Ryan Companies US, Inc.

awarding damages on breach-of-contract claims, foreclosing mechanic’s liens,

and awarding attorney fees, costs, and interest. AFFIRMED IN PART,

REVERSED IN PART, AND REMANDED.

Philip S. Bubb and Brandon R. Underwood of Fredrikson & Byron, P.A., Des

Moines, for appellant.

Bradley D. Fisher and Brian D. Steffes of Fisher Bren & Sheridan, LLP,

Minneapolis, MN and Stephen D. Marso of Whitfield and Eddy, P.L.C., Des

Moines, for appellee.

Heard by Mullins, P.J., and May and Ahlers, JJ. 2

AHLERS, Judge.

Contracts mean what they say. Here, a party that failed to follow what a

contract said in terms of the procedure to change the scope of the contract seeks

to avoid the consequences of that failure. We decline to allow such avoidance.

I. Background Facts and Proceedings

In 2016, FDP WTC, LLC (FDP) and Ryan Companies US, Inc. (Ryan)

entered into a pair of owner-contractor contracts in which Ryan—the contractor—

and FDP—the owner—agreed to terms for the construction of a hotel in Waterloo.

The parties entered into the first contract (Courtyard Contract) with a guaranteed

maximum price (GMP) of $22,626,869. The parties entered into the second

contract (Sitework Contract) with a GMP of $2,501,864.1 For purposes of this

appeal, the terms of the Courtyard Contract and Sitework Contract are identical.

Ryan’s senior project executive testified that, before executing the

contracts, FDP sought to reduce the contractual scope of the project to reduce the

GMP for financing purposes. Nevertheless, Ryan’s project manager testified that

designs issued by FDP’s architect did not match assumptions in the contracts,

which required modifications in the GMP. To that end, the parties executed a

series of change orders to modify the scope and GMP of the project. Ryan also

submitted to FDP many more requests for change orders—known as Cost Events

(CEs)—for additional work consistent with the architect’s designs that would

increase the GMP. FDP did not sign these CEs to increase the GMP. However,

1 The parties later entered into a third related contract. The third contract is not at issue on appeal. 3

the project manager testified Ryan performed the work under the CEs after FDP

requested or otherwise orally approved such work.

In 2018, Ryan petitioned to foreclose its mechanic’s liens against FDP for

the project. Ryan later amended its petition to add breach-of-contract claims. FDP

answered and counterclaimed with its own breach-of-contract claims.2 The claims

proceeded to a bench trial. The district court found for Ryan on its breach-of-

contract and mechanic’s lien foreclosure claims and denied FDP’s breach-of-

contract claims. The court entered judgment in Ryan’s favor for $452,817 on the

Courtyard Contract, $224,086 on the Sitework Contract, interest, attorney fees,

and costs.

FDP appeals the district court’s ruling for Ryan on the parties’ contract

claims. FDP argues the court erred in awarding Ryan damages, foreclosing on

Ryan’s mechanic’s liens, denying FDP credits for reductions in the scope of the

parties’ contracts, and awarding Ryan attorney fees, costs, and interest. We

reverse the district court’s finding FDP breached the parties’ contracts, foreclosure

of Ryan’s mechanic’s liens, and award to Ryan of attorney fees, costs, and interest.

We affirm the finding that FDP did not prove Ryan breached the contracts.

II. Standard of Review

The parties agree the contract claims were tried at law below and our review

is for correction of errors at law. See NevadaCare, Inc. v. Dep’t of Human Servs.,

783 N.W.2d 459, 465 (Iowa 2010). “If substantial evidence in the record supports

2 The district court granted partial summary judgment to Ryan on its mechanic’s liens related to the parties’ third contract. FDP appealed, and we affirmed those liens related to the third contract. See Ryan Cos. US, Inc. v. FDP WTC, LLC, No. 19-1698, 2021 WL 211156, at *1 (Iowa Ct. App. Jan. 21, 2021). 4

a district court’s finding of fact, we are bound by its finding. Iowa Mortg. Ctr., L.L.C.

v. Baccam, 841 N.W.2d 107, 110 (Iowa 2013). “However, a district court’s

conclusions of law or its application of legal principles do not bind us.” 3 Id. We

review actions to enforce mechanic’s liens de novo. See Flynn Builders, L.C. v.

Lande, 814 N.W.2d 542, 545 (Iowa 2012). “Review of a district court’s grant of

attorney fees is for an abuse of discretion.” Homeland Energy Sols., LLC v.

Retterath, 938 N.W.2d 664, 684 (Iowa 2020).

III. Analysis

A. Ryan’s Breach-of-Contract Claims

1. Express contract

a. Error preservation

Even though breach of an express contract was one of the primary issues

in dispute before the district court, Ryan asserts FDP failed to preserve error on its

arguments. As shown below, interpretation of section 6.4 of the contracts is key

to the parties’ dispute. Ryan asserts that because FDP did not specifically address

section 6.4 before the district court, it preserved no argument on section 6.4 for

3 FDP notes the district court largely adopted Ryan’s proposed findings of fact and conclusions of law on the breach-of-contract and mechanic’s lien foreclosure claims, and thus FDP asks us to scrutinize the court’s ruling. See NevadaCare, 783 N.W.2d at 465 (“[W]here a district court adopts a prevailing counsel’s proposed findings of fact and conclusions of law verbatim, we must scrutinize the record more carefully when conducting our appellate review.”). At the court’s invitation after trial, both parties submitted proposed findings of fact and conclusions of law. On our review of the record, the court clearly based its ruling on Ryan’s proposal, though the court also edited Ryan’s language and added findings including explicit credibility findings. While the facts on appeal are mostly undisputed and the court’s conclusions of law are not binding, we are mindful the court adopted much of Ryan’s proposal, and we will scrutinize the court’s ruling accordingly. 5

appeal. See Meier v. Senecaut, 641 N.W.2d 532, 537 (Iowa 2002) (“It is a

fundamental doctrine of appellate review that issues must ordinarily be both raised

and decided by the district court before we will decide them on appeal.”). However,

FDP extensively argued before the district court that Ryan performed work outside

the scope of the contracts and failed to obtain proper change orders to modify the

scope to include this work. While FDP’s trial filings do not address section 6.4,

section 6.4 was an issue at trial and the court’s ruling squarely addressed its

language.

Free access — add to your briefcase to read the full text and ask questions with AI

Ryan Companies US, Inc. v. FDP WTC, LLC, (iowactapp 2021).

Ryan Companies US, Inc. v. FDP WTC, LLC (Ryan Companies US, Inc. v. FDP WTC, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Chariton Feed and Grain, Inc. v. Harder
369 N.W.2d 777 (Supreme Court of Iowa, 1985)
Molo Oil Co. v. River City Ford Truck Sales, Inc.
578 N.W.2d 222 (Supreme Court of Iowa, 1998)
Tupelo Redevelopment Agency v. Gray Corp.
972 So. 2d 495 (Mississippi Supreme Court, 2007)
NevadaCare, Inc. v. Department of Human Services
783 N.W.2d 459 (Supreme Court of Iowa, 2010)
Smith v. Stowell
125 N.W.2d 795 (Supreme Court of Iowa, 1964)
Meier v. SENECAUT III
641 N.W.2d 532 (Supreme Court of Iowa, 2002)
Central Iowa Grading, Inc. v. Ude Corp.
392 N.W.2d 857 (Court of Appeals of Iowa, 1986)
Hartig Drug Co. v. Hartig
602 N.W.2d 794 (Supreme Court of Iowa, 1999)
Ida Grove Roofing v. City of Storm Lake
378 N.W.2d 313 (Court of Appeals of Iowa, 1985)
Iowa Waste Systems, Inc. v. Buchanan County
617 N.W.2d 23 (Court of Appeals of Iowa, 2000)
KATSURA v. City of San Buenaventura
65 Cal. Rptr. 3d 762 (California Court of Appeal, 2007)
Bouten Construction Co. v. M & L Land Co.
877 P.2d 928 (Idaho Court of Appeals, 1994)
Seneca Valley, Inc. v. Village of Caldwell
808 N.E.2d 422 (Ohio Court of Appeals, 2004)
Ridley Elec. Co., Inc. v. Dormitory Auth. of The State of New York
2017 NY Slip Op 5907 (Appellate Division of the Supreme Court of New York, 2017)
Iowa Mortgage Center, L.L.C. v. Lana Baccam and Phouthone Sylavong
841 N.W.2d 107 (Supreme Court of Iowa, 2013)
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Professional Service Industries, Inc. v. J. P. Construction, Inc.
491 N.W.2d 351 (Nebraska Supreme Court, 1992)