Ryan Companies US, Inc. v. FDP WTC, LLC

Court of Appeals of Iowa·Decided August 30, 2023·No. 22-0925·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 22-0925

Filed August 30, 2023

RYAN COMPANIES US, INC., Plaintiff-Appellee,

vs.

FDP WTC, LLC, Defendant-Appellant.

Appeal from the Iowa District Court for Black Hawk County, David P. Odekirk, Judge.

A defendant challenges the district court’s award of attorney fees and costs on remand. AFFIRMED.

Philip S. Bubb, Brandon R. Underwood, and Sarah B. Golwitzer of Fredrickson & Byron, P.A., Des Moines, for appellant.

Bradley D. Fisher and Brian D. Steffes of Fisher Bren & Sheridan, LLP, Minneapolis, Minnesota, and Stephen D. Marso and Anna E. Mallen of Whitfield & Eddy, P.L.C., Des Moines, for appellee.

Considered by Bower, C.J., and Badding and Buller, JJ.

BADDING, Judge.

In its third go-around on appeal, FDP WTC, LLC challenges the district court’s award of attorney fees and costs on remand. We find no abuse of discretion and affirm. I. Background Facts and Proceedings Beginning in 2016, FDP entered into a series of three contracts with Ryan Companies US, Inc., a general contractor, to renovate a factory building into a hotel. The parties called the first contract the “Courtyard Contract”; the second was the “Sitework Contract”; and the third was the “John Deere Contract.”

Two years later, Ryan petitioned to foreclose its mechanic’s liens against FDP for the project and claimed FDP breached the Courtyard and Sitework contracts. An amended petition broadened Ryan’s claims to include the John Deere Contract, as well as claims based on implied-in-fact and implied-in-law contracts. FDP counterclaimed for breach of all three contracts. Ryan successfully moved for partial summary judgment on the John Deere Contract and was awarded $340,238.16. We affirmed that award on appeal. See Ryan Co. US, Inc. v. FDP WTC, LLC, No. 19-1698, 2021 WL 211156, at *2 (Iowa Ct. App. Jan. 21, 2021).

Following a bench trial on the other two contracts, the district court entered judgment in September 2020 for Ryan on its breach-of-contract and mechanic’s lien foreclosure claims, denied its implied-in-fact and implied-in-law contract claims, and dismissed FDP’s counterclaims. The court awarded Ryan $452,817.00 in damages for the Courtyard Contract and $224,086.00 for the

Sitework Contract, for a total of $676,903.00, plus interest, costs, and $116,876.43 in attorney fees.

On FDP’s appeal from this ruling, we reversed the district court’s decision to award Ryan damages for work it performed without valid change orders that was above the two contracts’ guaranteed maximum prices. See Ryan Co. US, Inc. v. FDP WTC, LLC, No. 20-1366, 2022 WL 469336, at *4 (Iowa Ct. App. Jan. 12, 2022). This reduced Ryan’s total judgment on the Courtyard and Sitework contracts from $676,903.00 to $427,319.00—a difference of $249,584.00. We otherwise affirmed the court’s judgment for Ryan, including its dismissal of FDP’s counterclaims. Id. at *4–5.

Because Ryan prevailed on the breach-of-contract and mechanic’s lien foreclosure claims, we found the company was “entitled to recover attorney fees by statute and contract.” Id. at *5 (discussing the contracts’ provision requiring FDP to pay Ryan “all costs reasonably incurred by [Ryan] in the collection of amounts payable to Contractor hereunder, including reasonable attorney’s fees”); see also Iowa Code § 572.32(1) (2018) (allowing “a prevailing plaintiff” to recover “reasonable attorney fees”). But our court recognized

that the district court’s award of attorney fees was based on its ruling that Ryan succeeded on all of its claims. As this opinion modifies the district court’s ruling to vacate part of Ryan’s judgment, we believe reconsideration of the attorney fee award is appropriate to take into account Ryan’s only partial success. As a result, we vacate the attorney fee award and remand to the district court to determine an appropriate attorney fee award in light of the partial success and partial lack of success by Ryan in this suit.

Ryan, 2022 WL 469336, at *5. We did not include the court’s award of costs in the scope of our remand, and we assessed costs on appeal “two-thirds against Ryan and one-third against FDP.” Id.

Back before the district court on remand, Ryan requested an additional $78,106.00 in attorney fees and $872.15 in costs that it incurred after the court’s judgment entry in September 2020, plus the full amount of attorney fees that it had originally been awarded—$116,876.43. Ryan referred to the initial award of attorney fees as “prejudgment fees,” the fees incurred after the judgment as “post- judgment fees,” and the costs incurred after the judgment as “post-judgment costs.”

In a thorough ruling, the court found that the

case involved three separate, complicated construction contracts.

Ryan’s petition, as amended, set out 13 separate counts addressing numerous construction issues and bringing claims against FDP on the three contracts for damages totaling $1,017,141.16: Courtyard—

$452,817; Sitework—$224,086; and John Deere—$340,238.16.

FDP’s answer and counterclaims, as amended, alleged numerous affirmative defenses together with a counterclaim alleging three separate counts of breach of contract—one count for each of the aforementioned contracts also involving numerous issues—for damages totaling $1,387,476. Ultimately, the combined claims/counterclaims of both parties concerning all three contracts involved alleged damages totaling $2,404,617.16.

Examining the case “as a whole in light of Ryan’s success and/or failure,”

rather than “sift[ing] out specific minutes and hours billed as they relate[d]” to that success or failure, the court found the “combined value of the claims and counterclaims Ryan prevailed on or successfully defended” against totaled $2,155,033.16—an approximate ninety-percent success rate. The court accordingly found “a reduction of 10% should be made to both the pre-judgment

fees and post-judgment fees requested by Ryan to reflect its partial success.” That resulted in an award of $105,188.79 in prejudgment attorney fees and $69,911.00 in post-judgment attorney fees. The court made the same ten-percent reduction to the requested amount of post-judgment costs, for an award of $785.31, although it did not disturb the prejudgment costs, which it found were left “unchanged by the appellate decision” and “final as the law of the case for the purposes of remand.”

Free access — add to your briefcase to read the full text and ask questions with AI

Ryan Companies US, Inc. v. FDP WTC, LLC, (iowactapp 2023).

Ryan Companies US, Inc. v. FDP WTC, LLC (Ryan Companies US, Inc. v. FDP WTC, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vaughan v. Must, Inc.
542 N.W.2d 533 (Supreme Court of Iowa, 1996)
Schaffer v. Frank Moyer Construction, Inc.
628 N.W.2d 11 (Supreme Court of Iowa, 2001)
Meier v. SENECAUT III
641 N.W.2d 532 (Supreme Court of Iowa, 2002)
Lynch v. City of Des Moines
464 N.W.2d 236 (Supreme Court of Iowa, 1990)
Boyle v. Alum-Line, Inc.
773 N.W.2d 829 (Supreme Court of Iowa, 2009)
Baumhoefener Nursery, Inc. v. a & D Partnership, II
618 N.W.2d 363 (Supreme Court of Iowa, 2000)
Tina Elizabeth Lee v. State of Iowa and Polk County Clerk of Court
874 N.W.2d 631 (Supreme Court of Iowa, 2016)