Ridley Elec. Co., Inc. v. Dormitory Auth. of The State of New York

2017 NY Slip Op 5907, 152 A.D.3d 1129, 60 N.Y.S.3d 551
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 27, 2017
Docket524214
StatusPublished
Cited by7 cases

This text of 2017 NY Slip Op 5907 (Ridley Elec. Co., Inc. v. Dormitory Auth. of The State of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ridley Elec. Co., Inc. v. Dormitory Auth. of The State of New York, 2017 NY Slip Op 5907, 152 A.D.3d 1129, 60 N.Y.S.3d 551 (N.Y. Ct. App. 2017).

Opinion

Garry, J.

Appeal from an order of the Supreme Court (Platkin, J.), entered February 23, 2016 in Albany County, which, among other things, granted defendant’s cross motion for summary judgment dismissing the complaint.

In May 2006, plaintiff entered into a contract with defendant to act as the prime contractor for electrical work in the construction of the New York State Veteran’s Home, for a base price of approximately $5 million. Plaintiff had difficulty completing the work due to certain issues related to the ceiling design, and defendant made various adjustments to assist in resolving these issues. Plaintiff’s work was substantially complete by September 2008, and the entire project was substantially complete by October 2008. In March 2009, plaintiff requested additional compensation for “extra work” that it allegedly performed related to the ceiling and other specified problems. In February 2010, defendant advised plaintiff that following a preliminary review, it had concluded that plaintiff was due some additional funds for labor costs incurred in performing extra work related to the ceiling, but *1130 denied plaintiff’s other claims. Change orders allowing the proposed additional funds were attached to the February 2010 correspondence. Plaintiff refused to sign these, and instead submitted two proposed change orders requesting additional sums. In response, defendant again issued change orders for the original sum.

Plaintiff then commenced this breach of contract action seeking damages representing the unpaid contract balance and delay damages. 1 Defendant answered and asserted affirmative defenses claiming, among other things, that plaintiff had failed to comply with the contractual notice and reporting requirements. Plaintiff moved for summary judgment as to liability, and defendant cross-moved for summary judgment dismissing the complaint. Supreme Court denied plaintiff’s motion, granted defendant’s cross motion, and dismissed the complaint. Plaintiff appeals.

The parties’ contract authorizes defendant to order a contractor to perform “extra work,” defined as “[a]ny work in addition to the [w]ork” that the contractor was initially required to perform under the contract, and to use change orders to make appropriate adjustments in the contractor’s consideration. If a contractor believes that it has been ordered to perform a task that should be considered extra work within the meaning of these provisions, the contractor is required to notify defendant of its extra work claim by filing a written notice within 15 days after being ordered to perform the work or beginning performance, whichever is earlier, and to submit documentation of, among other things, the anticipated cost of the extra work within 30 days. Failure to comply with these notice and reporting requirements is deemed to be “[a] conclusive and binding determination on the part of the [contractor that [the work in question] does not involve extra work and is not contrary to the terms and provisions of the [c]ontract” and, also, “[a] waiver ... of all claims for additional compensation or damages as a result of [the work].”

Notice and reporting requirements of this nature are “common in public works projects, provide public agencies with timely notice of deviations from budgeted expenditures . . . and allow them to take early steps to avoid extra or unnecessary expense, make any necessary adjustments, mitigate dam *1131 ages and avoid the waste of public funds” (A.H.A. Gen. Constr. v New York City Hous. Auth., 92 NY2d 20, 33-34 [1998]). Because of these important public policy considerations, such an expressly agreed-upon notice provision “must be literally performed,” and a party who has failed to do so cannot prevail on a breach of contract claim (Phoenix Signal & Elec. Corp. v New York State Thruway Auth., 90 AD3d 1394, 1396-1397 [2011] [internal quotation marks and citation omitted]; see Fahs Constr. Group, Inc. v State of New York, 123 AD3d 1311, 1311 [2014], lv denied 25 NY3d 902 [2015]; Fahs Rolston Paving Corp. v County of Chemung, 43 AD3d 1192, 1194 [2007]).

Plaintiff claims that it performed extra work, first, by having to install cable trays and run wires inside them in ceiling spaces that were too small to accommodate them, 2 and second, by performing certain cleanup work. The parties agree that plaintiff became aware of the ceiling issue soon after it commenced work in May 2007, and the record reveals that defendant advised plaintiff in writing in April 2008 that it considered the cleanup work to fall within the scope of the contract. Plaintiff concedes that it did not provide defendant with timely notice of these claims as required by the contract, but contends that Supreme Court nevertheless erred in dismissing the complaint because defendant knew that plaintiff was performing extra work and waived the notice and reporting requirements by offering to make partial payment in response to plaintiff’s belated request.

Turning first to defendant’s cross motion for summary judgment, defendant submitted the affidavits and deposition testimony of two managerial employees familiar with the project. They acknowledged that the difficulty of plaintiff’s work was increased to some extent by ceiling space limitations that plaintiff could not have anticipated, but asserted that the difficulties were considerably less than plaintiff claimed, and could have been partly ameliorated if plaintiff had properly coordinated its work with other contractors. Defendant’s employees further asserted that the cleanup work was plaintiff’s responsibility under the contract. Their testimony and the record evidence established, as plaintiff concedes, that plaintiff did not submit extra work claims for either issue until March 2009, after the project had been substantially completed and almost two years after construction commenced. As Supreme Court found, this showing that plaintiff failed to comply with the notice and reporting requirements of the contract was suf *1132 ficient to meet defendant’s prima facie burden to establish its entitlement to summary judgment (see Tougher Indus., Inc. v Dormitory Auth. of the State of N.Y., 130 AD3d 1393, 1397 [2015]; Fahs Constr. Group, Inc. v State of New York, 123 AD3d at 1311-1312; Kingsley Arms, Inc. v Sano Rubin Constr. Co., Inc., 16 AD3d 813, 814 [2005]).

The burden thus shifted, and plaintiff submitted testimony and affidavits of defendant’s employees acknowledging that defendant knew of the ceiling issue, and stating their belief that plaintiff was entitled to some related compensation. However, despite defendant’s conceded knowledge of the ceiling space issue, actual notice does not suffice to excuse lack of compliance with a strict contractual notice requirement such as that at issue here (see Phoenix Signal & Elec. Corp. v New York State Thruway Auth., 90 AD3d at 1397; Kingsley Arms, Inc. v Sano Rubin Constr. Co., Inc., 16 AD3d at 815).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cyprium Therapeutics, Inc. v. Curia Global, Inc.
2022 NY Slip Op 51426(U) (New York Supreme Court, Albany County, 2022)
Ryan Companies US, Inc. v. FDP WTC, LLC
Court of Appeals of Iowa, 2021
MLB Constr. Servs., LLC v. Dormitory Auth. of the State of N.Y.
2021 NY Slip Op 02852 (Appellate Division of the Supreme Court of New York, 2021)
Framan Mech., Inc. v. State Univ. Constr. Fund
2020 NY Slip Op 2510 (Appellate Division of the Supreme Court of New York, 2020)
Redwing Constr. Co., Inc. v. Sexton
2020 NY Slip Op 1538 (Appellate Division of the Supreme Court of New York, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2017 NY Slip Op 5907, 152 A.D.3d 1129, 60 N.Y.S.3d 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ridley-elec-co-inc-v-dormitory-auth-of-the-state-of-new-york-nyappdiv-2017.