Ryan Companies US, Inc. v. FDP WTC, LLC
This text of Ryan Companies US, Inc. v. FDP WTC, LLC (Ryan Companies US, Inc. v. FDP WTC, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
IN THE COURT OF APPEALS OF IOWA
No. 19-1698 Filed January 21, 2021
RYAN COMPANIES US, INC., Plaintiff-Appellee,
vs.
FDP WTC, LLC, Defendant-Appellant. ________________________________________________________________
Appeal from the Iowa District Court for Black Hawk County, George L.
Stigler, Judge.
A defendant appeals following an adverse ruling on a motion for partial
summary judgment in favor of a plaintiff. AFFIRMED.
Philip S. Bubb and Brandon R. Underwood of Fredrikson & Byron, P.A., Des
Moines, for appellant.
Stephen D. Marson of Whitfield & Eddy, P.L.C., Des Moines, and Bradley
D. Fisher and Brian D. Steffes of Fisher Bren & Sheridan, LLP, Minneapolis,
Minnesota, for appellee.
Considered by Doyle, P.J., and Mullins and Greer, JJ. 2
MULLINS, Judge.
In September 2018, Ryan Companies US, Inc. (Ryan) filed a petition to
foreclose mechanic’s liens against FDP WTC, LLC (FDP). Ryan’s amended
petition and attachments alleged the following. In January 2016, the parties
entered into the Courtyard Contract, pursuant to which Ryan agreed to furnish
labor and materials relating to building improvements, and FDP agreed to pay for
the same. Allegedly, Ryan provided services, but FDP failed to pay. The parties
entered the Sitework Contract in November 2016, under which Ryan again agreed
to provide labor and materials relating to building improvements, and FDP agreed
to pay for the same. Ryan allegedly met its obligations under the contract, but
FDP did not compensate Ryan in accordance with the contract. In March 2018,
the parties entered the John Deere Contract, under which Ryan agreed to provide
materials and labor in return for compensation from FDP. Again, Ryan allegedly
provided the agreed-to services, but FDP failed to pay.
Ryan’s November 2018 amended petition forwarded thirteen claims against
FDP, including a claim for foreclosure of a mechanic’s lien relating to the John
Deere Contract in the amount of $340,238.16. In its amended answer, FDP
alleged Ryan failed to fully perform its obligations under the three contracts
because, among other things, labor and materials provided by Ryan were defective
or otherwise of poor quality. FDP counterclaimed for breach of each of the three
contracts.
In May 2019, Ryan moved for summary judgment on its claim for
foreclosure of a mechanic’s lien relating to the John Deere Contract. FDP resisted,
claiming, among other things, “Even if the material facts establishing liability on the 3
John Deere Contract are undisputed,” given the various contracts, claims, and
counterclaims, FDP should be allowed to set off of damages because “the parties
agreed by contract to allow setoff of claims and counterclaims.” Ryan responded
it never contractually agreed to allow set off of damages. The matter proceeded
to hearing, at which FDP agreed it was liable for the amount requested under the
John Deere Contract but essentially argued it expected to succeed on its
counterclaims and it should be entitled to set off damages when the claims under
the other two contracts were adjudicated.
Ultimately, the court granted the motion for summary judgment, relying on
Iowa Rule of Civil Procedure 1.957, which provides: “A claim and counterclaim
shall not be set off against each other, except by agreement of both parties or
unless required by statute.” The court entered judgment in favor of Ryan in the
amount of $340,238.16. FDP appeals.
On appeal, FDP argues “the district court erred in ruling that the parties did
not agree to setoffs under Iowa Rule of Civil Procedure 1.957.” FDP notes, “Like
the other two contracts between the parties,” the John Deere Contract “allowed
FDP to withhold payment because of . . . ‘defective Work not remedied,’ ‘damage
to the Owner,’ or ‘repeated failure to carry out the Work in accordance with the
Contract Documents.’” FDP also notes the “John Deere Contract defined ‘the
Work’ to include ‘the construction and services required by the Contract
Documents’ and ‘all other labor, materials, equipment and services provided or to
be provided by the Contractor to fulfill the Contractor’s obligations.’” FDP claims
the “contract’s text and the construction’s context compel the conclusion that the 4
residual phrase captures Ryan’s obligations to FDP under the other two contracts”
and “Ryan and FDP thus agreed to setoff claims and counterclaims.”
We find the answer to this appeal by a simple reading of the John Deere
Contract. The very first provision states, “The Contract represents the entire and
integrated agreement between the parties hereto.” And “the Work” is limited to
“the construction and services required by the Contract Documents” making up the
John Deere Contract, not the other two contracts. “The Work [] constitue[s] the
whole or part of the Project.” “The Project is . . . the Work performed under the
Contract Documents” of the John Deere Contract, not the other two. Thus, we
interpret “all other labor, materials, equipment and services,” to be limited to that
performed and provided under the John Deere Contract, not the other contracts.
Upon our plain reading of the contract, we find no contractual agreement to
setting off of claims and counterclaims across the three contracts. As such, set off
is prohibited by Iowa Rule of Civil Procedure 1.957. We affirm entry of judgment
in favor of Ryan.
AFFIRMED.
Free access — add to your briefcase to read the full text and ask questions with AI
Cite This Page — Counsel Stack
Ryan Companies US, Inc. v. FDP WTC, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryan-companies-us-inc-v-fdp-wtc-llc-iowactapp-2021.