RSM Production Corporation v. Gaz du Cameroun, S.A.

District Court, S.D. Texas·Decided November 4, 2023·No. 4:22-cv-03611·Unknown

Opinion

UNITED STATES DISTRICT COURT November 06, 2023 SOUTHERN DISTRICT OF TEXAS Nathan Ochsner, Clerk HOUSTON DIVISION RSM PRODUCTION CORP., § § Plaintiff, § § v. § Civil Action No. 4:22-CV-03611 § GAZ DU CAMEROUN, S.A., § § Defendant. § MEMORANDUM OPINION AND ORDER

This case centers on an arbitration award issued in favor of Plaintiff RSM Production Corporation (“RSM”) against Defendant Gaz du Cameroun, S.A. (“GdC”). While RSM prevailed in arbitration, it seeks to vacate the Tribunal’s modification of the award, which lowered what was originally a $10,578,123.28 award to $6,566,497.38. GdC previously filed a Motion to Dismiss for Lack of Personal Jurisdiction, (Dkt. No. 16), which this Court denied, (Dkt. No. 29). The Court now turns to the merits of RSM’s Motion to Partially Vacate and Partially Confirm Arbitration Award, (Dkt. No. 2). After careful consideration, the Motion is GRANTED. I. BACKGROUND1 RSM and GdC entered into a contract in connection with a natural gas production and distribution project. (Dkt. No. 1 at 2). A dispute formed over the timing of when RSM was entitled to receive payment. (Id. at 4). RSM argued that GdC had claimed costs

1 The Court makes the following factual findings for the sole purpose of this Memorandum Opinion and Order. that it should not have. (Id.). RSM states that that the payout date was supposed to be February 1, 2016, but that GdC’s improper inclusion of additional costs artificially

delayed payout until June 1, 2016, thereby decreasing RSM’s cut of the production. (Id.). In accordance with their contractually agreed-upon arbitration clause, the Parties arbitrated their multiple accounting and breach-of-contract disputes before a Tribunal of three arbitrators in accordance with the International Chamber of Commerce (“ICC”) Rules. (Id. at 3–4). The Tribunal ruled in RSM’s favor on most claims, including a finding that GdC had wrongfully included certain royalties in its expenses. (Dkt. No. 4-1 at 56).

RSM was awarded $10,578,123.28. (Id.). After the Partial Final Award was issued, the Parties jointly applied to correct two errors that resulted in a net increase of $47,710 to RSM, and the Tribunal agreed and made these corrections.2 (Dkt. No. 4-8 at 8–9). However, GdC also separately filed a contested Rule 36 “Application to Correct Award and Address Omitted Claims.” (Dkt. No. 4-5).

After briefing and oral argument, the Tribunal agreed with GdC that it had miscalculated RSM’s damages, and reduced RSM’s recovery by more than $4 million. (Dkt. No. 4-8 at 20). The Tribunal issued a revised Addendum Award, citing its authority to correct “computational” errors. (Id. at 16–18). RSM now requests that the Court vacate the portion of the Addendum Award that

reduced its recovery by roughly $4 million and confirm the remaining portions of the

2 The Parties agreed that RSM was entitled to an additional $200,000 as the prevailing party, and that $152,290 previously paid to RSM by GdC in the form of an overriding royalty should be deducted from the damages. (Dkt. No. 4-8 at 9). These agreements resulted in a net increase of $47,710. (See id.). Addendum Award and Partial Final Award. (Dkt. No. 2 at 28). RSM argues that the arbitrators exceeded their power under the Federal Arbitration Act (“FAA”), namely

their power to correct computational errors, and impermissibly “conduct[ed] [a] do- over[] of their substantive relief or reasoning.” (Id. at 18); (see generally id. at 15–26). In response, GdC argues that judicial review of the Tribunal’s decision is very limited, and this case is no exception, because it simply corrected a computational error when issuing the Addendum Award. (See Dkt. No. 33 at 11–17). With briefing complete, the Court turns to the merits of the Motion.

II. LEGAL STANDARD “In light of the strong federal policy favoring arbitration, judicial review of an arbitration award is extraordinarily narrow.” Rain CII Carbon, LLC v. ConocoPhillips Co., 674 F.3d 469, 471–72 (5th Cir. 2012) (quoting Brook v. Peak Int'l, Ltd., 294 F.3d 668, 672 (5th Cir. 2002)). Indeed, this standard has been described as “one of the most deferential standards known to the law.” Commc’ns Workers of Am., AFL-CIO v. Sw. Bell Tel. Co., 953

F.3d 822, 826 (5th Cir. 2020) (cleaned up). Vacatur of an arbitration award cannot be based on the merits of the award, even if it is shown that the arbitrator committed a “serious error.” Oxford Health Plans LLC v. Sutter, 569 U.S. 564, 569, 133 S.Ct. 2064, 2068, 186 L.Ed.2d 113 (2013). “Because the parties bargained for the arbitrator’s construction of their agreement, an arbitral decision even arguably construing or applying the contract

must stand, regardless of a court’s view of its (de)merits.” Id. (internal quotations omitted); see id. at 572–73, 133 S.Ct. at 2070–71 (explaining that “an arbitrator’s error— even his grave error—is not enough” and that “the price for agreeing to arbitration” is that “[t]he arbitrator’s construction holds, however good, bad, or ugly”).

Section 10 of the FAA “provides ‘the only grounds upon which a reviewing court may vacate an arbitrative award.’” Rain CII Carbon, 674 F.3d at 472 (quoting Brook v. Peak Int’l, Ltd., 294 F.3d 668, 672 (5th Cir. 2002)); see also 9 U.S.C. § 10. An award may be vacated: (1) where the award was procured by corruption, fraud, or undue means; (2) where there was evident partiality or corruption in the arbitrators, or either of them; (3) where the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced; or (4) where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made. 9 U.S.C. § 10(a). When a party seeks to vacate an arbitration award, that party bears the burden of proving that one of these grounds applies, and “any doubts or uncertainties must be resolved in favor of upholding [the award].” Cooper v. WestEnd Cap. Mgmt., L.L.C., 832 F.3d 534, 544 (5th Cir. 2016). III. DISCUSSION RSM primarily argues (1) that the Tribunal impermissibly revisited the merits of the arbitration award after the award was issued, and (2) that this renewed process was not the type of “computational error” that the Tribunal was permitted to fix. (See Dkt. No. 2 at 17–26). These two points are closely intertwined, so the Court will consider them before turning to the remaining portions of the Partial Final Award. A. THE PARTIAL FINAL AWARD AND ADDENDUM AWARD

The Court will first summarize the relevant dispute and the Tribunal’s two rulings. The Court begins by outlining RSM’s claims against GdC relevant to this Motion before turning to the Tribunal’s holdings on those claims. 1. RSM’s Claims 1–3 Against GdC RSM and GdC entered into multiple agreements with respect to a natural gas production and distribution project. (Dkt. No. 2 at 7). Under those agreements, GdC was

Free access — add to your briefcase to read the full text and ask questions with AI

RSM Production Corporation v. Gaz du Cameroun, S.A., (S.D. Tex. 2023).

RSM Production Corporation v. Gaz du Cameroun, S.A. (RSM Production Corporation v. Gaz du Cameroun, S.A.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brook v. Peak Intl Ltd
294 F.3d 668 (Fifth Circuit, 2002)
Brown v. Witco Corporation
340 F.3d 209 (Fifth Circuit, 2003)
Apache Bohai Corp. LDC v. Texaco China BV
480 F.3d 397 (Fifth Circuit, 2007)
Bayne v. Morris
68 U.S. 97 (Supreme Court, 1863)
Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
RAIN CII CARBON, LLC v. ConocoPhillips Co.
674 F.3d 469 (Fifth Circuit, 2012)
Oxford Health Plans LLC v. Sutter
133 S. Ct. 2064 (Supreme Court, 2013)
Chase v. Cohen
519 F. Supp. 2d 267 (D. Connecticut, 2007)
CWA v. Southwestern Bell Telephone Co
953 F.3d 822 (Fifth Circuit, 2020)
Cooper v. Westend Capital Management, L.L.C.
832 F.3d 534 (Fifth Circuit, 2016)