Brook v. Peak Intl Ltd

294 F.3d 668
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 9, 2002
Docket01-50339
StatusPublished
Cited by22 cases

This text of 294 F.3d 668 (Brook v. Peak Intl Ltd) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brook v. Peak Intl Ltd, 294 F.3d 668 (5th Cir. 2002).

Opinion

294 F.3d 668

Richard BROOK, Plaintiff-Appellee,
v.
PEAK INTERNATIONAL, LTD., Defendant-Appellant.

No. 01-50339.

United States Court of Appeals, Fifth Circuit.

June 13, 2002.

As Modified on Grant of Rehearing July 9, 2002.

Thomas M. Lipovski (argued), Lawrence Alan Waks, Jackson Walker, Austin, TX, for Plaintiff-Appellee.

John N. McCamish, Jr. (argued), David R. Montpas, McCamish, Socks & Montpas, San Antonio, TX, for Defendant-Appellant.

Appeal from the United States District Court for the Western District of Texas.

Before JONES, WIENER and PARKER, Circuit Judges.

EDITH H. JONES, Circuit Judge:

Brook and Peak International, Ltd., Brook's former employer, arbitrated their contractual dispute before an arbitrator selected by the American Arbitration Association ("AAA"). The arbitrator's award favored Peak. Brook filed a motion to vacate the arbitration award in the district court. The district court held that the arbitrator selected by the AAA was without power to decide the dispute because the AAA did not follow the selection procedure outlined in Brook's Employment Agreement. The district court vacated the arbitration award pursuant to 9 U.S.C. § 10(a)(4). Peak has appealed. Although we agree that AAA seriously erred by deviating from the parties' contractual selection process, we conclude that Brook never timely objected to the selection process on the ground he now espouses, hence, the objection was waived.

BACKGROUND

On January 1, 1998, Richard Brook entered into an employment agreement (the "Employment Agreement") with Peak International to become its president and chief operating officer. Less than a year later, he was terminated. A dispute arose regarding Brook's severance benefits. On May 7, 1999, pursuant to the terms of the Agreement, Brook filed a demand for arbitration with the AAA alleging breach of his Employment Agreement.1

This appeal concerns the arbitrator selection process. The process began on May 18, 1999, when the AAA submitted a list of nine prospective arbitrators and instructed the parties to follow the procedure outlined in the Employment Agreement to select the arbitrator. On May 28, Brook struck one individual from the list. Brook's counsel also stated:

[Peak's] counsel [ ] has agreed to Austin as the site of the arbitration hearing and hence it strikes us that perhaps an arbitrator from Austin would be more efficient and economical for all concerned. To that end, [Peak's counsel] and I will try to come up with a mutually acceptable Austin-based arbitrator from your AAA-Austin list, if this is acceptable to the association.

Peak, citing its understanding that a new list of arbitrators from Austin was to be provided by the AAA, did not submit a strike to the AAA's first list of arbitrators.

On June 9, the AAA informed the parties that "there were no mutual choices [from the previously provided list of arbitrators] who were able to accept the appointment." The AAA then advised: "[the AAA is] enclosing a second list of names from our panel. We ask that this list be considered supplemental to the list previously provided and every consideration be given to releasing names struck from that list." The AAA's June 9 letter did not refer to Brook's May 28 letter or Brook's request for selection of an arbitrator from the AAA's Austin list, and it did not direct the parties to employ the selection process outlined in the Employment Agreement. Rather, the letter instructed the parties to strike the names of unacceptable arbitrators and indicate their order of preference by number. The letter also provided that "[i]f this list is not received by the [AAA] on or before Monday, June 21, 1999, or if there are no mutual choices, the appointment will be made per Section 12 of the [AAA] Rules." If the parties failed to submit their strikes by June 21, the letter warned, "all names submitted may be deemed acceptable."

Complying with the June 9 letter, Brook submitted his strike list and ranked the remaining arbitrators in order of preference.2 Peak did not submit a list of strikes before June 21.

On July 14, Peak's counsel informed the AAA that he was withdrawing and that Peak intended to substitute John McCamish as counsel. Peak also advised the AAA of ongoing discussions with Brook's counsel regarding the possible mutual selection of Judge Joe Hart as arbitrator. On July 16, Mr. McCamish requested a seven-day extension of time from Brook's counsel to review the file before advising whether his client would agree to the selection of Judge Joe Hart. Brook's counsel rejected the request for extension of time.

On July 26, the AAA notified the parties that Professor David Sokolow had been selected as arbitrator. Peak immediately protested the appointment of Professor Sokolow, citing concerns regarding Professor Sokolow's potential conflicts with counsel and his inexperience with employment-related disputes. Peak also submitted its strikes to the list of arbitrators. On August 5, Peak sent a second letter of objection to the AAA, arguing that "the entire appointment process violates the parties' written agreement." Peak requested that the AAA comply with the terms of the Employment Agreement by providing a list of nine, rather than seven, potential arbitrators and by allowing the parties to alternately remove names from the list until only one remained. Brook filed no objection to the selection of Professor Sokolow or the process used by the AAA and did not respond to Peak's objections.

On August 11, the AAA withdrew the appointment of Professor Sokolow and appointed Judge Chuck Miller as arbitrator. The AAA's letter appointing Judge Miller refers neither to Peak's objections to the selection process nor to its demand for compliance with the selection process outlined in the Employment Agreement.

On August 13, Brook registered "his protest to the process used by the [AAA] in the selection of the arbitrator." In a letter to the AAA and opposing counsel, Brook objected to the appointment of Judge Miller "because the appointment [was] not made in compliance with AAA rules and procedures." Brook also requested that the AAA reinstate "the properly appointed individual, Professor David Sokolow," as arbitrator. However, Brook's August 13 letter does not mention the Employment Agreement or the AAA's failure to follow the contractual selection process.

On August 26, Peak notified the AAA that it was "willing to forego its complaints of procedural irregularities that have occurred and proceed forward if Brook agrees to Mr. Miller as arbitrator." Peak also stated that "if Brook is unwilling to agree to [the appointment of Judge Miller]... then Peak would continue to assert its complaint, outlined in [its] letter of August 4, 1999, that the entire appointment process to date has violated the terms of Brook's employment agreement...." The record contains no response from Brook, and no further objection by Brook to the appointment of Judge Miller. The parties proceeded to arbitrate their dispute before Judge Miller.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

YPF S.A. v. Apache Overseas, Incorporated
924 F.3d 815 (Fifth Circuit, 2019)
Light-Age, Incorporated v. Clifford Ashcroft-Smith
922 F.3d 320 (Fifth Circuit, 2019)
T3 Enters., Inc. v. Safeguard Bus. Sys., Inc.
435 P.3d 518 (Idaho Supreme Court, 2019)
Soaring Wind Energy, LLC v. Catic United States, Inc.
333 F. Supp. 3d 642 (N.D. Texas, 2018)
Bain v. Whitney Bank
919 F. Supp. 2d 735 (E.D. Louisiana, 2013)
Lexington Insurance Co. & Chartis v. Southern Energy Homes, Inc.
101 So. 3d 1190 (Supreme Court of Alabama, 2012)
RAIN CII CARBON, LLC v. ConocoPhillips Co.
674 F.3d 469 (Fifth Circuit, 2012)
Volanda Woods v. Pam Transport Inc-Lu
440 F. App'x 265 (Fifth Circuit, 2011)
McVay v. Halliburton Energy Services, Inc.
688 F. Supp. 2d 556 (N.D. Texas, 2010)
Royce Homes, L.P. v. Bates
315 S.W.3d 77 (Court of Appeals of Texas, 2010)
Raitport v. Salomon Smith Barney, Inc.
57 A.D.3d 904 (Appellate Division of the Supreme Court of New York, 2008)
Apache Bohai Corp. LDC v. Texaco China BV
480 F.3d 397 (Fifth Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
294 F.3d 668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brook-v-peak-intl-ltd-ca5-2002.