Rosebud Enterprises, Inc. v. Idaho Public Utilities Commission

951 P.2d 521, 131 Idaho 1, 1997 Ida. LEXIS 133
CourtIdaho Supreme Court
DecidedNovember 7, 1997
DocketNo. 23641
StatusPublished
Cited by7 cases

This text of 951 P.2d 521 (Rosebud Enterprises, Inc. v. Idaho Public Utilities Commission) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rosebud Enterprises, Inc. v. Idaho Public Utilities Commission, 951 P.2d 521, 131 Idaho 1, 1997 Ida. LEXIS 133 (Idaho 1997).

Opinion

JOHNSON, Justice.

This public utilities ease is a sequel to Rosebud Enterprises v. Idaho Pub. Util. Comm’n, 128 Idaho 624, 917 P.2d 781 (1996) (Rosebud I). We conclude that the Idaho Public Utilities Commission (IPUC) was correct in refusing to order Idaho Power Company (Idaho Power) to purchase electric capacity and energy from Rosebud Enterprises (Rosebud) at avoided cost rates that have been superseded.

I.

THE BACKGROUND AND PRIOR PROCEEDINGS

Rosebud is a developer of a small power production plant (the qualified facility) that is [4]*4classified as a “qualified facility” under the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. § 2601 through § 2645. Under PURPA and the rules of the Federal Energy Regulatory Commission (FERC) implementing PURPA, Idaho Power is required to purchase energy and capacity (power) from qualified facilities at the rates of its avoided costs (the avoided cost rates). In 1992, Rosebud requested that IPUC require Idaho Power to provide Rosebud the avoided cost rates for the qualified facility.

In early 1994, Idaho Power applied to IPUC for a change in the methodology for avoided cost rate negotiations for all but very small qualified facilities, which are not at issue in this case. In January 1994, IPUC suspended the avoided cost rates it had previously established. IPUC specifically exempted from this suspension Rosebud’s 1992 request for a determination of avoided cost rates for the qualified facility, stating that these rates would be determined independently.

In April 1994, IPUC ordered Idaho Power to follow the established “surrogate avoided resource” avoided cost methodology (the SAR methodology) and to calculate and provide Rosebud with avoided cost rates. In September 1994, IPUC required Idaho Power to recalculate and offer avoided cost rates in accordance with the SAR methodology and adjustments specified in the order. In October 1994, Idaho Power offered to purchase the output of the qualified facility at specified avoided cost rates (the 1994 rates) over a twenty-year period. In November and December 1994, IPUC ruled that Idaho Power’s October 1994 offer to purchase the output of the qualified facility complied with IPUC’s prior orders. Rosebud appealed to this Court in an attempt to obtain higher avoided cost rates than the 1994 rates.

In December 1994, while its appeal (the Rosebud I appeal) was pending, Rosebud declared that the parties were at an impasse and presented Idaho Power with a letter proposing to double the size of the qualified facility. In January 1995, Idaho Power responded to Rosebud’s letter, stating that it appeared to be a rejection by counteroffer but that Idaho Power would keep its October 1994 offer open until January 13, 1995, in order to allow Rosebud to reconsider whether to accept the offer.

Rosebud did not respond by January 13, 1995. On January 20, 1995, Rosebud wrote to Idaho Power stating that although the 1994 rates were substantially less than Rosebud believed were appropriate, Rosebud was willing to take a contract with complete terms, conditions, and avoided cost rates to its fuel suppliers, financiers, and vendors to determine whether the contract as a whole would support a project. On January 23, 1995, Idaho Power notified Rosebud that it withdrew its October 1994 offer and left it open for Rosebud to propose a contract with rates, terms, and conditions that Rosebud would accept.

On January 31, 1995, during the pendency of the Rosebud I appeal, IPUC determined that Idaho Power’s avoided costs for qualified facilities, other than very small ones that are not at issue in this case, would be based on “integrated resource planning” avoided cost methodology (IRP methodology). In September 1995, IPUC set five years as the standard contract length for purchase by utilities of power from qualified facilities.

In May 1996 this Court issued its opinion in Rosebud I upholding IPUC’s 1994 rulings approving the 1994 rates. 128 Idaho at 632, 917 P.2d at 789. Rosebud then requested a contract from Idaho Power at the 1994 rates. Idaho Power rejected Rosebud’s request and requested Rosebud to provide Idaho Power with current information concerning the qualified facility. In August 1996, Rosebud requested IPUC to require Idaho Power to purchase the output of the qualified facility at the 1994 rates. IPUC denied Rosebud’s request on the ground that the 1994 rates had been superseded by IPUC’s new IRP methodology and shortened five-year contract term. IPUC granted Rosebud’s request that IPUC reconsider its decision. On reconsideration, IPUC again denied Rosebud’s request that IPUC require Idaho Power to purchase the output of the qualified facility at the 1994 rates. Rosebud appealed.

Preliminarily, we consider Rosebud’s contention that its right to appeal has been [5]*5rendered illusory because following its appeal in Rosebud I, IPUC refused to enforce the 1994 rates. We disagree. Certainly Rosebud’s appeal in Rosebud I would not have been meaningless if it had prevailed. Apparently Rosebud means that its appeal was meaningless because it did not prevail, and it was then precluded from taking advantage of the 1994 rates because IPUC changed the avoided cost methodology. This did not make the appeal meaningless, but merely a risky course of action.

II.

ROSEBUD I DOES NOT REQUIRE IDAHO POWER TO PURCHASE POWER FROM THE QUALIFIED FACILITY AT THE 1994 RATES.

Rosebud asserts that IPUC violated the mandate of Rosebud I by not requiring Idaho Power to purchase power from the qualified facility at the 1994 rates. We disagree.

What Rosebud describes as the direct mandate of the Court in Rosebud I is only part of the introduction to the opinion, describing in general terms what IPUC had ordered: “The orders of the IPUC establish an avoided cost rate to be paid by Idaho Power Company (Idaho Power) for the purchase of electric capacity and energy from Rosebud.” 128 Idaho at 626, 917 P.2d at 783. This is not a ruling by the Court that Idaho Power is required to purchase power from the qualified facility at the 1994 rates. The Court’s ruling in Rosebud I was that “[t]he factors considered by the IPUC are consistent with the FERC regulations in determining avoided costs” and that “[t]he record establishes that the IPUC regularly pursued its authority and that its findings are supported by substantial and competent evidence.” Id. at 632, 917 P.2d at 789. The Court did not mandate that Idaho Power was required to purchase power from the qualified facility at the 1994 rates.

III.

IPUC DID NOT VIOLATE I.C. § 61-625.

Rosebud asserts that IPUC’s refusal to require Idaho Power to purchase power from the qualified facility at the 1994 rates constitutes a collateral attack on the validity of the IPUC orders approving the 1994 rates in violation of section 61-625 of the Idaho Code. We disagree.

I.C. § 61-625 states: “All orders and decisions of the commission which have become final and conclusive shall not be attacked collaterally.” IPUC’s refusal to require Idaho Power to purchase the output of the qualified facility at the 1994 rates is not a collateral attack on the IPUC 1994 orders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Eaton
Idaho Supreme Court, 2025
Whitehall Wind, LLC v. Montana Public Service Commission
2015 MT 119 (Montana Supreme Court, 2015)
Idaho Power Co. v. Idaho Public Utilities Commission
316 P.3d 1278 (Idaho Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
951 P.2d 521, 131 Idaho 1, 1997 Ida. LEXIS 133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rosebud-enterprises-inc-v-idaho-public-utilities-commission-idaho-1997.