Rosebud Enterprises, Inc. v. Idaho Public Utilities Commission

917 P.2d 790, 128 Idaho 633, 1996 Ida. LEXIS 63
CourtIdaho Supreme Court
DecidedMay 30, 1996
DocketNo. 20910
StatusPublished

This text of 917 P.2d 790 (Rosebud Enterprises, Inc. v. Idaho Public Utilities Commission) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rosebud Enterprises, Inc. v. Idaho Public Utilities Commission, 917 P.2d 790, 128 Idaho 633, 1996 Ida. LEXIS 63 (Idaho 1996).

Opinion

SCHROEDER, Justice.

This is an appeal from Idaho Public Utilities Commission (IPUC) Orders No. 25160 and 25021. In these orders the IPUC accepted Idaho Power Company’s (Idaho Power) offer of an estimated upgrade cost for its Twin Falls hydroelectric plant and permitted the estimate to serve as a cap for the amount Idaho Power may include in its future rate-base. The IPUC also recognized that Idaho Power will be allowed to recover in its revenue requirement its prudently incurred investment in the Twin Falls upgrade. Rosebud Enterprises, Inc. (Rosebud) appeals the orders of the IPUC, asserting that placing the Twin Falls project in Idaho Power’s rate-base is unfair to ratepayers because the Company could obtain the same energy from Rosebud at a much lower cost: the avoided cost for Rosebud’s proposed facility.

I.

BACKGROUND AND PRIOR PROCEEDINGS

On March 25, 1991, Idaho Power filed an Application with the IPUC seeking ratemak-ing assurance of Idaho Power’s investment in the upgrade of its 9 megawatt (MW) Twin Falls hydroelectric project. The upgrade is estimated to increase the total output of the Twin Falls plant to 52.5 MW. Idaho Power’s license for the Twin Falls project, issued by the Federal Energy Regulatory Commission (FERC), expired in 1984. Idaho Power operated under annual renewals until January 18, 1991, when FERC renewed Idaho Power’s license for the Twin Falls project for an additional 50 years.

On November 25, 1992, Idaho Power filed a “commitment estimate” with the IPUC. Idaho Power’s estimate ranged from $42,-866,000.00 to $50,839,000.00 plus 20 percent for specified contingencies as a cost ceiling on the amount of investment it would ultimately seek to include in the ratebase. If the final cost were less than the offered estimate, the actual costs would be used in ratemaking; if the actual cost exceeds the commitment estimate, Idaho Power would absorb the excess and would seek to include only the amount of the commitment estimate. The project has in fact been completed below the cost ceiling, and the costs of the project have now been included in Idaho Power’s ratebase.

On March 17, 1993, Rosebud filed a petition to intervene. Rosebud is an independent power developer proposing to construct a 40 MW petroleum coke-fired1 generating plant near Mountain Home, Idaho, and is a self-certified “Qualifying Facility” (QF) under the Public Utility Regulatory Policies Act of 1978, 16 U.S.C. § 824a-l, et seq. (PURPA). The IPUC issued Order No. 24820 granting Rosebud’s Petition to Intervene, finding that Rosebud had “a direct and substantial interest in Idaho Power’s request to obtain ratebase preapproval of a base load generating plant.”

Idaho Power argued that the Twin Falls upgrade was “nondeferrable” and that it had to optimize the use of the resource to obtain a renewed license from FERC within a time certain or face the possibility of losing its license and the project to another entity. IPUC Order No. 22299 had expressed the IPUC’s support of FERC relicensing:

Because existing hydroelectric plants could be lost to competing companies if FERC relicensing requirements are not aggressively pursued, relicensing alternatives require special consideration. For example, if hydroelectric plant relicensing upgrades are proposed, their costs should be presented both as a function, of increased plant output and of total plant output to recognize the potential for losing the entire site . . .

Rosebud maintained that allowing the Twin Falls upgrade to be included in Idaho Power’s rates would discriminate against Ro[635]*635sebud’s Mountain Home QF project, because Idaho Power is allegedly refusing to purchase the power from that project.2 Rosebud also contended that Idaho Power’s own calculations showed no need for new resources until the year 2006, and, therefore, the Twin Falls project is unnecessary.

On July 22, 1993, the IPUC issued Order No. 25021 granting Idaho Power the following assurance:

[W]e find that, in the ordinary course of events, the Company may expect its investment in the Twin Falls project to be recognized in its revenue requirement, barring unforeseen circumstances of a kind not characteristic of hydroelectric facilities. The ultimate decision determining the appropriate amount of the Twin Falls investment to include in revenue requirement will, of course, be made during the course of a general rate proceeding or a tracker proceeding initiated for that purpose.

The IPUC recognized the inherent value of hydropower, noting that Idaho Power’s ratepayers enjoy some of the lowest rates in the nation and that they “have been fortunate to avoid the economic and environmental consequences associated with a predominantly thermal based electric utility.” The IPUC rejected Rosebud’s contention that the Twin Falls project must be compared to whatever rates Rosebud ultimately receives from Idaho Power for the Mountain Home project.

Rosebud petitioned the IPUC for reconsideration of Order No. 25021. The IPUC issued Order No. 25160 affirming all aspects of its ruling, determining that Rosebud failed to prove that the assurance granted to Idaho Power by the IPUC violates PURPA. The IPUC concluded that there is no justification for holding utility constructed and owned projects to rules set for QF contracts. Rosebud did not seek to enjoin or restrain the enforcement of the IPUC Orders pursuant to section 61-633 of the Idaho Code (1994). Rosebud appealed the IPUC Orders to this Court.

II.

APPEAL IS MOOT DUE TO FAILURE TO COMPLY WITH I.C. §§ 61-633 & 61-634

If a party seeks to suspend the operation of an IPUC order, that party must comply with the statutory requirements set forth by the legislature. Idaho Code section 61-633 sets forth the procedure which must be utilized to a stay an IPUC order.3 In determining an applicant’s right to an injunction, restraining order or other order suspending or staying the operation of an order, a court must determine if the applicant has proven that there would be “great and irreparable damage” if the stay were not granted. I.C. § 61-633. Idaho Code section 61-634 (1994) states that in ease the order or decision of the Commission is stayed or suspended, the order shall not become effective until a suspending bond has been executed and filed with and approved by the Commission, or by the court of review.4 In essence, I.C. § 61-[636]*636634 is a bond-posting requirement to effect a stay.

This appeal process is not a stay of the IPUC orders. The Idaho Code section 61-635 reads:

Stay of order on appeal. — The pendency of an appeal shall not of itself stay or suspend the operation of the order of the commission, but during the pendency of such appeal, the Supreme Court may stay or suspend, in whole or in part, the operation of the commission’s order.

Since this Court has not issued a stay, and the filing of an appeal does not constitute a stay, Orders No. 25021 and 25160 have not been stayed.

In Utah Power & Light v. Idaho Pub. Util. Comm’n, 107 Idaho 47, 685 P.2d 276 (1984), this Court addressed the Public Utility Law:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
917 P.2d 790, 128 Idaho 633, 1996 Ida. LEXIS 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rosebud-enterprises-inc-v-idaho-public-utilities-commission-idaho-1996.