Idaho Power Co. v. Idaho Public Utilities Commission

316 P.3d 1278, 155 Idaho 780, 2013 WL 6658554, 2013 Ida. LEXIS 360
CourtIdaho Supreme Court
DecidedDecember 18, 2013
Docket39151-2011
StatusPublished
Cited by1 cases

This text of 316 P.3d 1278 (Idaho Power Co. v. Idaho Public Utilities Commission) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho Power Co. v. Idaho Public Utilities Commission, 316 P.3d 1278, 155 Idaho 780, 2013 WL 6658554, 2013 Ida. LEXIS 360 (Idaho 2013).

Opinions

EISMANN, Justice.

This is an appeal from an order of the Idaho Public Utilities Commission denying approval of contracts between an electric utility and two wind farms on the ground that the contract rate for purchasing the power was contrary to public policy because it exceeded the utility’s avoided costs. We affirm.

I.

Factual Background.

The Public Utility Regulatory Policies Act of 1978 (PURPA) was enacted to require electric utilities to purchase electricity from qualifying small power production facilities and from qualifying cogeneration facilities. “A ‘small power production facility’ is one that has a production capacity of no more than 80 megawatts and uses biomass, waste, or renewable resources (such as wind, water, or solar energy) to produce electric power.” F.E.R.C. v. Mississippi, 456 U.S. 742, 750 n. 11, 102 S.Ct. 2126, 2132 n. 11, 72 L.Ed.2d 532, 540-41 n. 11 (1982). “A ‘cogeneration facility" is one that produces both electric energy and steam or some other form of useful energy, such as heat.” Id. The legislation required the Federal Energy Regulatory Commission (FERC) to prescribe rules to encourage cogeneration and small power production and to require electric utilities to offer to purchase electric energy from qualifying facilities. 16 U.S.C. § 824a-3(a) & (b).

PURPA “directs FERC, in consultation with state regulatory authorities, to promulgate ‘such rules as it determines necessary to encourage cogeneration and small power production,’ including rules requiring utilities to offer to sell electricity to, and purchase electricity from, qualifying cogeneration and small power production facilities.” F.E.R.C., 456 U.S. at 751, 102 S.Ct. at 2133, 72 L.Ed.2d at 541-42; 16 U.S.C. § 824a-3(b). However, PURPA provides that no such rule “shall provide for a rate which exceeds the incremental cost to the electric utility of alternative electric energy.” 16 U.S.C. § 824a-3(b). The incremental cost is defined as “the cost to the electric utility of the electric energy which, but for the purchase from such cogenerator or small power producer, such utility would generate or purchase from another source.” 16 U.S.C. § 824a-3(d). FERC’s [782]*782rules use the term “avoided costs” to mean the incremental cost. 18 C.F.R. § 292.101(a)(6).

If a state chooses to regulate electric utilities, it must implement FERC rules. F.E.R.C., 456 U.S. at 751, 102 S.Ct. at 2133, 72 L.Ed.2d at 541-42; 16 USC § 824a-3(f)(1). However, a state regulatory authority has discretion in determining the manner in which the rules will be implemented, and may comply by issuing regulations, by resolving disputes on a case-by-case basis, or by other action reasonably designed to give effect to FERC’s rules. F.E.R.C., 456 U.S. at 751, 102 S.Ct. at 2133, 72 L.Ed.2d at 541-42. The “ ‘Act establishes a program of cooperative federalism that allows the States, within limits established by federal minimum standards, to enact and administer their own regulatory programs, structured to meet their own particular needs.’ ” Id. at 767, 102 S.Ct. at 2141, 72 L.Ed.2d at 552.

FERC’s rules acknowledge two ways in which a qualifying facility can establish a right to sell power to an electric utility. The utility and the facility can negotiate a rate at which the utility will purchase the electric power, 18 C.F.R. § 292.301(b)(1), or the facility can establish the right to require the utility to purchase the power “pursuant to a legally enforceable obligation for the delivery of energy or capacity over a specified term,” 18 C.F.R. § 292.304(d)(2). When it adopted the latter rule, FERC explained its purpose as follows:

Paragraph (d)(2) permits a qualifying facility to enter into a contract or other legally enforceable obligation to provide energy or capacity over a specified term. Use of the term “legally enforceable obligation” is intended to prevent a utility from circumventing the requirement that provides capacity credit for an eligible qualifying facility merely by refusing to enter into a contract with the qualifying facility.

45 Fed.Reg. 12214, 12224 (February 25, 1980).

FERC requires that there be a standard avoided-cost rate at which electric utilities are required to purchase power from qualifying facilities with a design capacity of up to 100 kilowatts. 18 CFR § 292.304(c)(1). The standard avoided-cost rate is called the “published rate” by IPUC. The limit on the size of the qualifying facility that is eligible for the published rate is commonly referred to as the “eligibility cap.” Qualifying facilities within the eligibility cap are entitled to sell power at the published rate, while the rate at which those above the eligibility cap are entitled to sell power is determined on a case-by-case basis.

IPUC initially set the eligibility cap at one megawatt, but it later increased it for wind projects to an average of ten megawatts (10 aMW) on a monthly basis. Because wind projects do not generate power all of the time, a qualified wind facility that is capable of producing more than ten megawatts of power would qualify for the published rate if the power produced during a month averaged ten megawatts.

In late 2007, Wasatch Wind Intermountain, LLC (Wasatch Wind), began investigating the feasibility of a wind power project located near Lynn, Utah, close to the Idaho-Utah border. It initially considered constructing a wind farm that would generate 150 megawatts of power, but later decided to reduce the size of the project. It desired to sell the power to Idaho Power Company (Idaho Power). On June 29, 2009, Wasatch Wind incorporated Grouse Creek Wind Park, LLC (Grouse Creek I).

Wasatch Wind first contacted Idaho Power in late February 2010. On February 26, 2010, Wasatch Wind sent Idaho Power an email stating, “Wasatch Wind Intermountain would like to request that Idaho Power commence Power Purchase Agreement negotiations with our subsidiary, Grouse Creek Wind Park, LLC for either a 10 Average MW or something less than 80 MW Qualifying Facility under PURPA.” Because the project site was outside of Idaho Power’s service area, Wasatch Wind needed to find a way to connect with the Idaho Power system. Wasatch Wind stated in the e-mail, “[W]e [783]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
316 P.3d 1278, 155 Idaho 780, 2013 WL 6658554, 2013 Ida. LEXIS 360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaho-power-co-v-idaho-public-utilities-commission-idaho-2013.