Rogers, Burgun, Shahine & Deschler, Inc. v. Dongsan Construction Co.

598 F. Supp. 754, 1984 U.S. Dist. LEXIS 21608
CourtDistrict Court, S.D. New York
DecidedNovember 30, 1984
Docket84 Civ. 7984 (SWK)
StatusPublished
Cited by4 cases

This text of 598 F. Supp. 754 (Rogers, Burgun, Shahine & Deschler, Inc. v. Dongsan Construction Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rogers, Burgun, Shahine & Deschler, Inc. v. Dongsan Construction Co., 598 F. Supp. 754, 1984 U.S. Dist. LEXIS 21608 (S.D.N.Y. 1984).

Opinion

MEMORANDUM OPINION AND ORDER

KRAM, District Judge.

The above-captioned action is before this Court upon plaintiffs motion for a preliminary injunction enjoining defendant from calling a certain Letter of Guarantee for payment and upon defendant’s motion to stay these proceedings pending arbitration. For the reasons stated below, both motions are granted.

—BACKGROUND—

Rogers, Burgun, Shahine & Deschler, Inc. (“RBSD”) is a New York corporation engaged in business as architectural designers of hospitals.

Dongsan Construction Company, Ltd. (“Dongsan”) is a Korean corporation, with offices in New Jersey, engaged in business as general contractors in construction projects.

In 1982, Saudi Arabia undertook to build a hospital in Jubail. Dongsan secured the main contract on this project. Dongsan subcontracted a portion of the architectural and engineering design work on the project to RBSD (the “Subcontract”).

Under the Subcontract, RBSD agreed to perform certain services, some of which RBSD, in turn, subcontracted to other entities. In return for those services, Dongsan agreed to pay RBSD some $2,596,086. Dongsan further agreed to pay RBSD twenty per cent of that amount ($519,217) in advance of RBSD’s performance. In order to secure this advance payment, RBSD provided Dongsan a Letter of Guarantee from Bank Al-Jazira in the full amount of the advance payment. The amount guaranteed by this letter was to decrease periodically commensurate with the percentage of work performed by RBSD and paid for by Dongsan.

The Subcontract also provided in broad terms for resolution of disputes by arbitration in Paris, France, under the rules of Conciliation and Arbitration of the International Chamber of Commerce. 1

RBSD has performed some of the services required by the Subcontract and Dongsan has paid RBSD for that work. Pursuant to the terms of the Letter of Guarantee, the amount currently secured is $155,-766. There have been occasional disputes during the course of RBSD’s performance regarding changed specifications, new demands, and delays in performance. These disputes, for the most part, were resolved amicably by the parties and a modification of the Subcontract agreed to on August 22, 1984. The modification essentially established a firm, detailed schedule for the completion of performance under the Subcontract. The modification also provides that “[ejxcept as expressly provided herein, both parties reserve all rights under the Subcontract and the Subcontract remains unmodified and in full force and effect.” The modification in no way alters the dispute resolution mechanism set out in Article XVI of the Subcontract.

Thereafter, a dispute arose with respect to RBSD’s performance in accordance with the schedule set forth in the August 1984 modification. RBSD claims that the dispute concerns a very small portion of the *756 work performed or owing. On September 16, 1984, Dongsan notified RBSD that it intended to complete certain of RBSD’s obligations itself, effecting a partial termination of the Subcontract as modified. Additionally, Dongsan indicated that it would withhold the remaining balance due RBSD under the Subcontract to set-off the anticipated expenses in completing those parts of RBSD’s services it had terminated.

RBSD claims that it has substantially performed all of its obligations due to date, that it is owed some $752,865 for actual and tendered performance, and that it is entitled to the release of the remaining $155,766 held by way of the Letter of Guarantee as security.

RBSD filed the complaint herein on November 5, 1984, alleging breach of contract by Dongsan and seeking inter alia the $908,631 allegedly owed RBSD by Dongsan and a preliminary injunction enjoining Dongsan from calling the Letter of Guarantee. By Order to Show Cause dated November 5,1984, RBSD moved this Court for the preliminary injunction, pursuant to Fed.R.Civ.P. 65. The Court thereby also entered a temporary restraining order against Dongsan enjoining it from calling the Letter of Guarantee. At the request of, and with the consent of, Dongsan, the hearing scheduled on that motion was adjourned from November 13 to November 21, 1984, and the temporary restraining order continued for that period.

On November 21, 1984, Dongsan filed its motion to dismiss or stay this action pending arbitration of the disputes herein. 2

On November 21 this Court held a hearing on both motions. 3 Based upon the affidavits and memoranda submitted, and upon counsel’s arguments at that hearing, the Court finds that both motions should be granted. 4

—DISCUSSION—

Dongsan’s Motion for Stay

For years, courts were hostile to agreements which called for arbitration. See H.R.Rep. No. 96, 68th Cong., 1st Sess., I, 2 (1924). That hostility was reversed by the enactment of the Federal Arbitration Act, 9 U.S.C. § 1 et seq. The enactment of the Arbitration Act reflected the new policy in favor of resolving disputes by arbitration in order “to allow parties to avoid ‘the costliness and delays of litigation,' and to place arbitration agreements upon the same footing as other contracts.” Scherk v. Alberto-Culver Co., 417 U.S. 506, 510-11, 94 S.Ct. 2449, 2452-53, 41 L.Ed.2d 270 (1974) (quoting H.R.Rep. No. 96, 68th Cong., 1st Sess., 1, 2 (1924)). That strong public policy in favor of dispute resolution by arbitration extends to international contracts. Fotochrome, Inc. v. Copal Co., 517 F.2d 512, 516 (2d Cir.1975). Indeed, specifically to encourage Americans engaged in international commerce to submit their commercial disputes to arbitration, Congress adopted and implemented the Convention of Recognition and Enforcement of Foreign Arbitral Awards of June 10, 1958, 9 U.S.C. § 201 et seq. (the “Convention”). Island Territory of Curacao v. Solitron Devices, Inc., 356 F.Supp. 1, 14 (S.D.N.Y.), aff'd, 489 F.2d 1313 (2d Cir.1973), cert. *757 denied, 416 U.S. 986, 94 S.Ct. 2389, 40 L.Ed.2d 763 (1974); see also Scherk, 417 U.S. at 520 n. 15, 94 S.Ct. at 2457 n. 15.

Against this background favoring arbitration, we must decide whether this dispute between RBSD and Dongsan is subject to arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanchez v. General Electric Co.
196 F. Supp. 3d 726 (S.D. Texas, 2016)
Bahrain Telecommunications Co. v. Discoverytel, Inc.
476 F. Supp. 2d 176 (D. Connecticut, 2007)
International Shipping Co. v. Hydra Offshore, Inc.
675 F. Supp. 146 (S.D. New York, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
598 F. Supp. 754, 1984 U.S. Dist. LEXIS 21608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rogers-burgun-shahine-deschler-inc-v-dongsan-construction-co-nysd-1984.