Roger Baskin v. Pierce & Allred Construction, Inc.

CourtTennessee Supreme Court
DecidedSeptember 28, 2023
DocketM2021-00144-SC-R11-CV
StatusPublished

This text of Roger Baskin v. Pierce & Allred Construction, Inc. (Roger Baskin v. Pierce & Allred Construction, Inc.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roger Baskin v. Pierce & Allred Construction, Inc., (Tenn. 2023).

Opinion

09/28/2023 IN THE SUPREME COURT OF TENNESSEE AT NASHVILLE November 9, 2022 Session Heard at Jackson

ROGER BASKIN v. PIERCE & ALLRED CONSTRUCTION, INC.

Appeal by Permission from the Court of Appeals Chancery Court for Davidson County No. 20-872-IV Russell T. Perkins, Chancellor ___________________________________

No. M2021-00144-SC-R11-CV __________________________________

In this appeal, we address whether a Tennessee resident may sue an Alabama corporation in a Tennessee court for alleged breach of contract and breach of warranty pertaining to its construction of a custom lake house in Alabama. Tennessee resident Roger Baskin hired Pierce & Allred Construction, an Alabama corporation with its principal place of business in Alabama, to build a house on a parcel of land in Alabama. Mr. Baskin supplied the architectural plans and some of the materials, all sourced from Tennessee, and the parties communicated throughout the project from their respective states. However, all of Pierce & Allred Construction’s activities on the project occurred in Alabama. Mr. Baskin ultimately became dissatisfied with the quality and expense of the construction work, and he filed suit in the Davidson County Chancery Court. Pierce & Allred Construction moved to dismiss the complaint for lack of personal jurisdiction, arguing that the corporation lacked the “minimum contacts” with Tennessee that due process protections require. Int’l Shoe Co. v. Washington, 326 U.S. 310, 316 (1945). The trial court granted the motion, finding that the events relevant to the claims occurred in Alabama and that the corporation’s contacts with Tennessee were minor and attenuated. The Court of Appeals reversed, looking to recent decisions from this Court, see Crouch Ry. Consulting, LLC v. LS Energy Fabrication, LLC, 610 S.W.3d 460 (Tenn. 2020), and the United States Supreme Court, see Ford Motor Co. v. Mont. Eighth Jud. Dist. Ct., 141 S. Ct. 1017 (2021) (explaining that the exercise of specific personal jurisdiction requires that a plaintiff’s claim arise out of or relate to the defendant’s forum contacts). We granted permission to appeal. Based on our review, we have determined that Pierce & Allred Construction’s contacts with Tennessee were not such that the corporation reasonably should have anticipated being haled into a Tennessee court to answer this suit. In making this determination, we conclude that certain contacts with Tennessee did not reflect that the corporation purposefully availed itself of the privilege of conducting business activities in Tennessee, while certain other contacts were not sufficiently related to Mr. Baskin’s claims to support the exercise of specific personal jurisdiction. Thus, we hold that Mr. Baskin failed to establish a prima facie case of the minimum contacts necessary for a Tennessee court to exercise specific personal jurisdiction over the Alabama corporation. Accordingly, we reverse the decision of the Court of Appeals and reinstate the judgment of the trial court dismissing Mr. Baskin’s complaint.

Tenn. R. App. P. 11 Appeal by Permission; Judgment of the Court of Appeals Reversed

JEFFREY S. BIVINS, J., delivered the opinion of the Court, in which ROGER A. PAGE, C.J., and SHARON G. LEE, HOLLY KIRBY, and SARAH K. CAMPBELL, JJ., joined.

Charles S. Michels, Nashville, Tennessee, for the appellant, Pierce & Allred Construction, Inc.

Paul J. Krog and Nicholas W. Tsiouvaras, Brentwood, Tennessee, for the appellee, Roger Baskin.

OPINION

I. FACTUAL AND PROCEDURAL BACKGROUND

This case arose from a dispute between Tennessee resident Roger Baskin (“the Plaintiff”) and Pierce & Allred Construction, Inc. (“the Defendant”), an Alabama corporation whose principal place of business is in Florence, Alabama. The Defendant is a licensed general contractor in Alabama, performing both residential and commercial work. Justin Allred is the sole owner and president of the Defendant. The Defendant has seven employees who work principally out of Florence.

In September 2016, based on a personal recommendation, the Plaintiff reached out to Mr. Allred seeking the Defendant’s services for the demolition of an existing structure and construction of a custom lake house on a parcel of land in Muscle Shoals, Alabama. Working from Alabama, the Defendant crafted a construction proposal and sent it to the Plaintiff for approval. The Plaintiff accepted and signed the proposal—in the Defendant’s office in Alabama—on or about September 16, 2016. The parties do not suggest that the signed proposal (“the contract”) had a forum selection clause.1 The contract indicated that the project (“the Baskin project”) was to be completed in approximately fifteen months (around January 2018). The parties agreed that the Defendant would be paid on a “cost plus basis,” meaning that the Plaintiff would pay the reasonable cost of all labor and materials plus a contractor’s fee of twelve percent. At the time of the contract, the labor

1 The contract is not in the record. Although the parties do not appear to dispute relevant facts pertaining to the contract, the better practice in this contract dispute would be for the parties to attach the contract to at least one of the filings that addressed whether the trial court properly could exercise personal jurisdiction over the Defendant.

-2- and materials were estimated to amount to $924,000.00, meaning that the total estimated cost was $1,034,880.00.

Upon entering into the contract, the Plaintiff provided the Defendant with architectural plans designed by a Tennessee firm. However, the Defendant had no contact with the firm or role in developing the plans. Likewise, based on his existing relationships with suppliers located in Tennessee, the Plaintiff purchased lumber, tile, windows, and flooring materials in Tennessee, and he had those materials shipped to Alabama. Just as with the architectural plans, the Defendant was not involved in selecting the suppliers or materials, nor did the Defendant play a role in transporting the materials to Alabama. In accordance with the contract, however, the Plaintiff did pay the Defendant the twelve- percent contractor’s fee on those materials.

All of the Defendant’s work pursuant to the contract occurred in Alabama. In addition, all subcontractors on the project were based in Alabama, and thus, all of the expenses the Defendant incurred were from labor and materials in Alabama. In fact, no person affiliated with the Defendant ever set foot in Tennessee in relation to the Baskin project, from the proposal that led to the establishment of the contractual relationship through the eventual breakdown of the relationship. There were six to eight in-person meetings between the parties during the course of the project, but they all took place in Alabama. The parties did communicate frequently during the project by electronic mail, text message, and telephone—the Defendant from Alabama and the Plaintiff from Tennessee. The parties do not detail the substance of these communications, but it is clear that the Defendant sent invoices to the Plaintiff electronically, and the Plaintiff paid the invoices through wire transfers originating from his bank account in Tennessee.

According to the Plaintiff, the Defendant “grossly mismanaged” the Baskin project. As a result, the Plaintiff paid the Defendant more than $1,700,000.00, well in excess of the initial cost estimate. Furthermore, according to the Plaintiff, the Defendant “left [the Plaintiff] with a home riddled with construction defects that affect every major system of the home.” The Plaintiff ultimately decided to hire a replacement contractor to remedy the alleged deficiencies and complete the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milliken v. Meyer
311 U.S. 457 (Supreme Court, 1941)
Hoopeston Canning Co. v. Cullen
318 U.S. 313 (Supreme Court, 1943)
International Shoe Co. v. Washington
326 U.S. 310 (Supreme Court, 1945)
Estin v. Estin
334 U.S. 541 (Supreme Court, 1948)
Hanson v. Denckla
357 U.S. 235 (Supreme Court, 1958)
Shaffer v. Heitner
433 U.S. 186 (Supreme Court, 1977)
World-Wide Volkswagen Corp. v. Woodson
444 U.S. 286 (Supreme Court, 1980)
Rush v. Savchuk
444 U.S. 320 (Supreme Court, 1980)
Keeton v. Hustler Magazine, Inc.
465 U.S. 770 (Supreme Court, 1984)
Helicopteros Nacionales De Colombia, S. A. v. Hall
466 U.S. 408 (Supreme Court, 1984)
Burger King Corp. v. Rudzewicz
471 U.S. 462 (Supreme Court, 1985)
Carnival Cruise Lines, Inc. v. Shute
499 U.S. 585 (Supreme Court, 1991)
Dudnikov v. Chalk & Vermilion Fine Arts, Inc.
514 F.3d 1063 (Tenth Circuit, 2008)
uBID, Inc. v. GoDaddy Group, Inc.
623 F.3d 421 (Seventh Circuit, 2010)
Adelson v. Hananel
510 F.3d 43 (First Circuit, 2007)
Goodyear Dunlop Tires Operations, S. A. v. Brown
131 S. Ct. 2846 (Supreme Court, 2011)
Arthur F. Sawtelle, Etc. v. George E. Farrell
70 F.3d 1381 (First Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Roger Baskin v. Pierce & Allred Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/roger-baskin-v-pierce-allred-construction-inc-tenn-2023.