Roe v. Ladymon

318 S.W.3d 502, 2010 Tex. App. LEXIS 6087, 2010 WL 2978293
CourtCourt of Appeals of Texas
DecidedJuly 30, 2010
Docket05-08-00417-CV
StatusPublished
Cited by81 cases

This text of 318 S.W.3d 502 (Roe v. Ladymon) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roe v. Ladymon, 318 S.W.3d 502, 2010 Tex. App. LEXIS 6087, 2010 WL 2978293 (Tex. Ct. App. 2010).

Opinion

OPINION

Opinion By

Justice MOSELEY.

Kimberlea A. Roe obtained an arbitration award against Blane Ladymon and Metro Townhomes & Homes, L.L.P. (Metro LLP), a Texas registered limited liability partnership. The trial court confirmed the award against Metro LLP, but vacated the award against Ladymon. Roe and Metro LLP appeal.

This case requires us to determine who — the arbitrator or the court — has the primary responsibility to decide whether a party to the dispute is bound by an arbitration provision in a contract between other parties. The answer to that question determines how we review the decision on whether the party is bound by the arbitration provision. We also consider whether the trial court erred by confirming the award against Metro LLP.

We conclude that Ladymon individually is not a party to the contract containing the arbitration clause, and he did not “clearly and unmistakably” agree to allow the arbitrator to decide issues of arbitra-bility. Therefore, the primary responsibility to decide the issue belongs to the court, not the arbitrator. We also conclude that the trial court — reviewing the issue de novo — did not err by finding that Lady-mon was not individually bound by the arbitration provision. Lastly, we conclude the trial court — applying the deferential standard applicable to arbitration awards — did not err by confirming Roe’s award against Metro LLP. Thus, we affirm the trial court’s judgment.

*507 I. Background

In 2003, Roe contracted for Metro LLP to renovate her home. The contract defined Roe as the “Owner” and Metro LLP as the “Contractor.” Ladymon signed the contract in his capacity as a partner of Metro LLP. Metro LLP’s partners included Ladymon, Metro Townhomes and Homes, Inc. (Metro Inc.), and others.

The contract is a form prepared by the Home Builders Association of Greater Dallas. Paragraph 18 of the contract contained a detailed mediation/arbitration provision. That provision broadly defined a “Dispute” as “any controversy or claim or matters in question between the parties,” and provided that the Owner and Contractor agreed to submit any Dispute to mediation, and to submit any unresolved Dispute to the American Arbitration Association (AAA) for binding arbitration pursuant to Federal Arbitration Act (FAA). 1 See 9 U.S.C. §§ 1-16 (2006).

On July 5, 2004, Ladymon, as president of Metro Inc., filed two documents with the Texas Secretary of State. One withdrew Metro LLP’s registration as a registered limited liability partnership and the other was a certificate of limited partnership for Metro Townhomes Limited Partnership (Metro LP). The certificate stat *508 ed that Metro LLP was converting to a limited partnership, Metro LP. The certificate identified Metro Inc. as Metro LP’s sole general partner and identified Lady-mon as a limited partner. Ladymon testified his accountant advised him to change the form of the business for tax purposes. He testified there was no transfer or formal assignment of Roe’s contract to Metro LP, and the partners continued to do the work on the project. Roe did not have actual knowledge of these filings.

Unsatisfied with the remodeling work, Roe demanded arbitration against both Metro LLP and Ladymon in June 2006. Attached to her arbitration demand was a demand letter addressed to Metro LLP and Ladymon. It alleged several construction defects and failures with the remodeling project and claimed damages under a number of legal theories. 2 Although we do not have a complete record of the arbitration proceedings or a transcript of the arbitration hearing, the record reflects that after an August 2006 preliminary hearing, which Ladymon attended, the arbitrator entered a scheduling order setting deadlines for disclosing witnesses, experts, and exhibits. The arbitrator also set the arbitration hearing for February 2007; the hearing was later rescheduled for May 7, 2007.

Roe served her witness, expert, and exhibit list on April 23, 2007. The next day, Ladymon faxed a letter (on Metro Inc. letterhead) to the arbitrator requesting a sixty-day continuance based on Roe’s allegedly late disclosures, the need to retain experts to respond to Roe’s experts, and the need to hire an attorney for the arbitration hearing. On May 3, 2007, the AAA notified the parties that the arbitrator denied the continuance. Roe filed an additional disclosure of witnesses and attached several pages of new exhibits on May 4, 2007.

Metro LLP and Ladymon retained an attorney to represent them. At the beginning of the May 7, 2007 hearing, they filed five written objections to the arbitration proceeding, again requested a continuance, and requested that Ladymon be dismissed from the proceeding. Objections four and five 3 pertained to whether Ladymon was required to arbitrate Roe’s claims against him:

OBJECTION 4: Respondent Blane La-dymon has been named in his individual capacity but he has not signed an agreement to arbitrate in his individual capacity.
OBJECTION 5: Respondent Blane La-dymon has been named in his individual capacity yet there have been no allegations in the demand for arbitration as to why or how he is liable. Nor is there any allegation that would support an award or finding that the limited liability provided by the entity should be disregarded.

The arbitrator denied the continuance, reserved ruling on Ladymon’s objections until after the parties submitted post-hearing briefs, and proceeded with the hearing.

Ladymon’s post-hearing brief argued that he signed the contract solely as a partner in a registered limited liability partnership (Metro LLP) and thus had no *509 personal liability. See Tex.Rev.Civ. Stat. Ann. art. 6132b-3.07(a)(l) (Vernon Supp. 2009). When Metro LLP withdrew its registration, it converted to a limited partnership (Metro LP) as allowed by law, and Ladymon became a limited partner in Metro LP. Ladymon argued that the contracts and obligations of the old partnership were assigned to the new partnership by operation of law, and thus no formal assignment of Roe’s contract to Metro LP was required. See Tex.Rev.Civ. Stat. Ann. art. 6132b-9.05(h)(l)-(3) (Vernon Supp.2009). And, Ladymon argued, as a limited partner he had no personal liability for the partnership’s obligations. See Tex.Rev. Civ. Stat. Ann. art. 6132a-l, § 3.03(a), (b)(1) (Vernon Supp.2009).

Roe’s post-hearing brief argued that, even though Ladymon did not sign the arbitration agreement in his individual capacity, he was bound to arbitrate the claims against him because he was an officer, agent, or representative of the entity that signed the agreement and was not a stranger to the contract. She also argued that because the contract provided it was binding upon the parties and “their respective ... representatives [and] successors ...,” Ladymon was bound to arbitrate as a representative and successor to Metro LLP.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. Schuck
N.D. Texas, 2025
Luna v. Tug Hill Operating, LLC
N.D. West Virginia, 2024
Huan Dang v. Hung Van Tran
Court of Appeals of Texas, 2023
Aaron Kaufman v. Amerihealth Laboratory, LLC
Court of Appeals of Texas, 2020
in Re State Farm Lloyds
Court of Appeals of Texas, 2020

Cite This Page — Counsel Stack

Bluebook (online)
318 S.W.3d 502, 2010 Tex. App. LEXIS 6087, 2010 WL 2978293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roe-v-ladymon-texapp-2010.