Rockland Bleach & Dye Works, Co., Inc. v. Hj Williams Corporation, Inc.

219 A.2d 48, 242 Md. 375, 1966 Md. LEXIS 646
CourtCourt of Appeals of Maryland
DecidedApril 28, 1966
Docket[No. 265, September Term, 1965.]
StatusPublished
Cited by10 cases

This text of 219 A.2d 48 (Rockland Bleach & Dye Works, Co., Inc. v. Hj Williams Corporation, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rockland Bleach & Dye Works, Co., Inc. v. Hj Williams Corporation, Inc., 219 A.2d 48, 242 Md. 375, 1966 Md. LEXIS 646 (Md. 1966).

Opinion

Marbury, J.,

delivered the opinion of the Court.

Rockland Bleach and Dye Works Co., Inc. (Rockland), plaintiff-appellant, filed a declaration against H. J. Williams Corporation, Inc. (Williams), defendant-appellee, containing three counts, all of which related to damages suffered as a result of excavation and construction work undertaken in 1962 by Williams as general contractor on the section of the Jones Falls Expressway adjacent to Rockland’s land in Baltimore County, Maryland. Rockland complained that by reason of Williams’ acts, its water supply had been cut off on two separate occasions, which caused interruptions in the processing operations being carried on in its bleach and dye works. The first count alleged that Williams had committed trespass in March, 1962, by causing or allowing mud and other debris to invade Rockland’s property, which completely filled its reservoir located thereon. The second count sounded in negligence, and was related to the same facts set forth in the first count. The third count alleged another incident which occurred in April 1962, when a backhoe being operated by Williams’ employee in the vicinity of Rockland’s land broke one of its water pipes. The case was tried by a jury, Judge Menchine presiding, and at the conclusion of plaintiff’s case, the lower court granted defendant’s motion for a directed verdict on count one. At the conclusion of the whole case, the jury returned a verdict in favor of the defendant on counts two and three, and after the lower court had heard and denied a motion for new trial, final judgment was entered for the defendant, from which this appeal was taken.

The defendant-appellee was engaged to build a section of the *379 Jones Falls Expressway in Baltimore County, as general contractor under a contract with the State Roads Commission of Maryland (S.R.C.). For a period of time prior to March 13, 1962, pursuant to its contract, Williams had been making substantial changes in the grade and elevation of the property immediately adjacent to the property of appellant. Before appellee started its work, the land to the north of appellant’s was a valley or a meadow bottom. By March 13, 1962, appellee had constructed a huge fill to support the expressway at this location, which was some fifty feet high and three hundred ninety feet wide at the base.

Appellant’s property was improved by a large building in which a bleach and dye works had been operated for many years. It is similar to a large commercial laundry, in that it takes its customers’ yard goods or material—usually of cotton — which comes to it in a raw state after weaving, and processes them. The goods are purified and cleansed, the coloring matter or other impurities are removed, and the cotton is then starched or dyed for use by the subsequent manufacturer. Appellant’s plant operation is thus essentially a service organization, which owns no goods but which charges for processing the goods of others on a per yard basis. Every operation in the various processes undertaken by appellant, except the stitching of the goods at the outset, and the packing at the end of the line, uses considerable amounts of water. In March of 1962, six hundred thousand to seven hundred fifty thousand gallons of water per day were being used in the regular course of appellant’s business.

The principal source of this water was a reservoir owned by appellant which was located on its own property just at the toe of the huge slope or fill, which appellee had constructed adjacent thereto. This supply was supplemented by wells, and to a very small degree, by city water. The reservoir had always been fed by a millrace or stream entering it from the northwest, which supply was channeled into a thirty-six inch pipe constructed by Williams before it began to construct the fill, so as to preserve the water supply to the reservoir. One of the special provisions of the contract with S.R.C. for the project, introduced into evidence as plaintiff’s exhibit No. 17, called par *380 ticular attention to 1 the fact that this millrace was a source of water supply to the appellant’s plant, and specifically provided that “water flow must be maintained at all times.” Appellee’s superintendent, being aware of the extreme importance of this matter, conferred with appellant’s superintendent about it before appellee began laying the thirty-six inch pipe.

From the reservoir, which was higher in elevation than the plant, the water came by gravity through two outlets—a ten inch pipe and a six inch pipe—and then joined with pipe lines coming from the wells, which, in turn, entered the plant. Not only was the reservoir used as the principal source of water for the plant, but, being higher in elevation, it also acted as a source of pressure on the water coming from the wells, so as to enable that water to enter the plant under sufficient pressure to reach the processing machines. If the reservoir were empty or clogged with mud or debris, the natural pressure on the well water would be insufficient to bring it into the plant at a usable pressure. A combination of water available from the city water line and the wells, without the pressure from the reservoir, was insufficient to allow normal operation of the plant.

On the night of March 12, 1962, a heavy rainstorm occurred. The banks of the fill were eroded, water came from the cut section, off a hillside, and washed down the slope of the fill, and silt, mud, debris and water subsided or slid onto appellant’s land and into its reservoir, filling it—there was no free flowing water left in it. Before the trial began appellee admitted that the mud and debris which filled the reservoir came from the cut and fill recently constructed by it adjoining the reservoir. During the trial appellee’s superintendent on the job also admitted that “it wasn’t unusual to have erosion or a small slide take place in a fill that was placed by equipment * * that it was usual for fills to erode and cuts to drain, and that “you get that condition most times in the spring, towards the spring of the year when you have hard rains.”

The specifications, which were a part of the contract between S.R.C. and appellee for the work, plaintiff’s exhibit No. 16, provided in pertinent parts:

“Section 10.05-14 Maintenance of Work, During Construction
*381 “The Contractor shall maintain the work during construction and until final acceptance. This maintenance shall constitute continuous and effective work prosecuted as required with adequate equipment and forces to the end that the roadbed, or structures, are kept in satisfactory condition at all times.
“Particular attention shall be given to drainage, both permanent and temporary. The Contractor shall use all possible precautionary measures to avoid damage or loss that might result from accumulations and concentrations of drainage waters, and material carried by such waters and such drainage shall be diverted or dispersed when necessary to prevent damage to excavation, embankments, surfacing, structures or property.
“Section 10.07-15 Preservation and Restoration of Property, Trees, Monuments, Etc.
“2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matiella v. Murdock Street LLC
District of Columbia, 2023
Maryland Attorney General Opinion 96 OAG 139.pdf
Maryland Attorney General Reports, 2011
Marcas, L.L.C v. Board of County Commissioners
817 F. Supp. 2d 692 (D. Maryland, 2011)
Hanna v. ARE ACQUISITIONS, LLC
929 A.2d 892 (Court of Appeals of Maryland, 2007)
JBG/Twinbrook Metro Ltd. Partnership v. Wheeler
697 A.2d 898 (Court of Appeals of Maryland, 1997)
Rosenblatt v. Exxon Co., U.S.A.
642 A.2d 180 (Court of Appeals of Maryland, 1994)
Heinrich v. Goodyear Tire and Rubber Co.
532 F. Supp. 1348 (D. Maryland, 1982)
Fedder v. Component Structures Corp.
329 A.2d 56 (Court of Special Appeals of Maryland, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
219 A.2d 48, 242 Md. 375, 1966 Md. LEXIS 646, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rockland-bleach-dye-works-co-inc-v-hj-williams-corporation-inc-md-1966.