Rivers Development, LLC.

CourtVermont Superior Court
DecidedJanuary 8, 2008
Docket7-01-05 Vtec
StatusPublished

This text of Rivers Development, LLC. (Rivers Development, LLC.) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rivers Development, LLC., (Vt. Ct. App. 2008).

Opinion

STATE OF VERMONT ENVIRONMENTAL COURT

} Appeal of Rivers Development, LLC } Docket No. 7-1-05 Vtec } Docket No. 68-3-07 Vtec }

Corrected1 Decision on Rivers’s Initial Motions These consolidated appeals2 arise out of decisions by the Moretown Development Review Board (“DRB”) and the District #5 Environmental Commission in which Rivers Development, LLP (“Rivers”) was denied a conditional use permit and an Act 250 land use permit to construct and operate a stone processing quarry in the Town of Moretown (“Moretown”). Docket No. 7-1-05 Vtec concerns the DRB’s denial of Rivers’s zoning and conditional use application, which asserts undue adverse impacts on the Town’s character, traffic, noise levels and water supplies. Docket No. 68-3-07 Vtec concerns the denial by the District #5 Environmental Commission (“Commission”), issued on March 14, 2007, of Rivers’s Motion to Alter the Commission’s Decision of January 19, 2007. Rivers asserts in this second appeal that the Commission rendered positive findings on all but two of the twenty-nine Act 250 criteria and sub-criteria; Rivers challenges the Commission’s conclusions that Rivers’s proposal did not comply with 10 V.S.A. § 6086(a)(10) (conformance with the Town Plan) and did not meet its burden of production with respect to 10 V.S.A. § 6086(a)(1) (avoidance of undue air pollution). Both Moretown and the Neighbors have filed cross-appeals in both proceedings. Appellant-Applicant Rivers is represented by James Caffry, Esq. and Christopher J. Nordle, Esq.; Cross-Appellant “Neighbors”3 are represented by David L. Grayck, Esq. and

1 This Corrected Decision is issued in connection with the granting of Neighbors’ motion for clarification. See Entry Order dated January 18, 2008. 2 There are also two other appeals pending before the Court that relate to the proposed Rivers Quarry: In re: Rivers Dev., LLC Underground Injection Control JO, Docket No. 183-8-07 Vtec and In re: Rivers Dev. LLC Indirect Discharge JO, Docket No. 248-11-06 Vtec. The pending motions addressed in this Decision were only filed in the two appeals cited above. 3 “Neighbors” includes the following individuals to whom the District Environmental Commission granted individual party status in the Act 250 proceedings pursuant to 10 V.S.A. § 6086; these individuals have retained their party status in these proceedings, pursuant to V.R.E.C.P. 5(d)(2): Thomas Allen, Robert Dansker, Jack Byrne, Virginia Farley, Doug Hall, Cindy Hall, June Holden Life Estate, Rick Hungerford, Rita Larocca, Robert McMullin, Beverly McMullin, John Porter, Scott Sainsbury, Patricia Sainsbury, Sandy Porter, Benjamin Sanders, Denise Zachary K. Griefen, Esq.; Cross-Appellant Arthur Hendrickson and Linda Hendrickson are united with the Neighbors, but are representing themselves pro se; Moretown is represented by Ronald Shems, Esq. and Geoffrey H. Hand, Esq.; and the Land Use Panel of the Natural Resources Board (“NRB”), appearing in the Act 250 proceeding as an Interested Person, is represented by Aaron Adler, Esq. Rivers has moved for partial summary judgment on questions 3, 4 and 5 of its Statement of Questions in its appeal of the municipal determination. These Questions collectively inquire whether the August, 27, 2002 Moretown Town Plan allows on-site processing of stone at a quarry in the Agriculture-Residential District. Rivers has also moved to dismiss specific Questions in the Neighbors’ Statement of Questions in the Act 250 appeal and has further requested that the Court direct Neighbors to clarify their remaining Questions. Both the Town and the Neighbors have filed oppositions to all motions by Rivers, and in their opposition to partial summary judgment, have raised the related issue of whether Rivers has a vested right to proceed under the March 7, 2000 Moretown Zoning Regulations. For the reasons expressed below, we grant Rivers’s motion for partial summary judgment, we grant Rivers’s motion for clarification, and we grant Rivers’s motion to dismiss certain questions on appeal.

Factual Background4

A.) General History 1. Rivers is the owner of an approximately ninety-three acre parcel of land located in the Town of Moretown along the northerly side of Route 100B, about two and a half miles from Moretown Village. 2. On May 17, 2004, Rivers submitted to the DRB a zoning and conditional use application and supporting materials for the construction of a rock processing quarry (“Quarry”).5

Sanders, Karen Sharpwolf, Ruth Van Heuven, Martin Van Heuven, and Constance Van Heuven. This Court’s July 3, 2007 Decision denied certain requests for additional party status, but did not disturb these Neighbors’ pre-existing party status, as conferred by the District Commission. 4 All facts are undisputed unless otherwise noted. For purposes of this motion only, we view the material facts in a light most favorable to the non-moving parties. V.R.C.P. 56(c). We are not yet at the stage of making specific factual findings. Thus, our recitations here should not be regarded as factual findings See Blake v. Nationwide Ins. Co., 2006 VT 48, ¶ 21, 180 Vt. 14, 24, citing Fritzen v. Trudell Consulting Eng’rs, Inc., 170 Vt. 632, 633 (2000)(mem.). 5 Neighbors assert that the conditional use application, as filed on May 17, 2004, was incomplete for failure to address all adverse impacts from the project. This assertion is discussed in more detail below.

2 3. On October 18, 2005, Rivers submitted to the Commission an Act 250 land use permit application for its Quarry.

B.) Proposed Quarry Description 4. Rivers’s ninety-three acre parcel is presently wooded with a mixture of hard and soft woods and is improved only with internal woods roads. The Quarry footprint will encompass approximately seventeen acres of the parcel. 5. Quarry operations will include the clearing of vegetative cover, the stripping and storing of topsoil and overburden, drilling, blasting, excavating, stockpiling, loading, hauling, and processing of rock. There will not be onsite storage of fuel or blasting materials.6 6. The Quarry will have a maximum extraction rate of 75,000 cubic yards per year and will operate over an approximately thirty-three year period. It will be completed in six phases. 7. Rivers proposes to operate the Quarry from April 15 to December 15 each year, Monday through Friday, between 7:00 a.m. and 5 p.m., exclusive of state and federal holidays. Rivers pledges to limit blasting to Monday through Friday, between the hours of 10:00 a.m. and 4:00 p.m. Quarry employees will conduct maintenance activity at the site on Saturdays from 7:00 a.m. until noon. Rivers requests that off-season access to stockpiled materials be permitted, with the approval of the Department of Fish and Wildlife. 8. The Quarry will generate a maximum of fifty-four loaded dump trucks per day (i.e.: 108 one-way vehicle trips) and up to ten other vehicles (i.e.: twenty additional one-way vehicle trips for employees and other business invitees).7 9. Rivers proposes to operate the following equipment at the Quarry site: one hydraulic rock drill; one excavator; one bucket loader; one six by twenty foot triple deck screener; one yard/water truck; one backhoe; one crusher with a total capacity of one hundred cubic yards per hour; and other miscellaneous equipment as needed. 10. Quarry operations will generate noise, shock waves and vibrations from blasting and other quarry processes. 11. The closest point of the working Quarry will be 760 feet from Route 100B. Its access will be from Route 100B via an existing woods road, approximately 1,400 feet in length.8 This

6 Neighbors and Moretown assert that fuel and blasting materials will necessarily be stored on the property for the brief period from the time the materials enter the property, to the time they are used on the property. 7 Moretown asserts that trucks not controlled by Rivers may result in additional vehicle traffic.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brod v. Agency of Natural Resources
2007 VT 87 (Supreme Court of Vermont, 2007)
In Re Jolley Associates
2006 VT 132 (Supreme Court of Vermont, 2006)
Smith v. Winhall Planning Commission
436 A.2d 760 (Supreme Court of Vermont, 1981)
In Re Handy
764 A.2d 1226 (Supreme Court of Vermont, 2000)
Hinesburg Sand & Gravel Co. v. State
693 A.2d 1045 (Supreme Court of Vermont, 1997)
In Re MBL Associates
693 A.2d 698 (Supreme Court of Vermont, 1997)
In Re Molgano
653 A.2d 772 (Supreme Court of Vermont, 1994)
Fritzeen v. Trudell Consulting Engineers, Inc.
751 A.2d 293 (Supreme Court of Vermont, 2000)
Blake v. Nationwide Insurance
2006 VT 48 (Supreme Court of Vermont, 2006)
In Re Appeal of Taft Corners Associates, Inc.
758 A.2d 804 (Supreme Court of Vermont, 2000)
In Re Kisiel
772 A.2d 135 (Supreme Court of Vermont, 2000)
In Re John A. Russell Corp.
2003 VT 93 (Supreme Court of Vermont, 2003)
In Re Taft Corners Associates, Inc.
632 A.2d 649 (Supreme Court of Vermont, 1993)
Agency of Natural Resources v. United States Fire Insurance
796 A.2d 476 (Supreme Court of Vermont, 2001)
In re Carter
2004 VT 21 (Supreme Court of Vermont, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Rivers Development, LLC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivers-development-llc-vtsuperct-2008.