Fritzeen v. Trudell Consulting Engineers, Inc.

751 A.2d 293, 170 Vt. 632, 2000 Vt. LEXIS 45
CourtSupreme Court of Vermont
DecidedApril 6, 2000
Docket98-554
StatusPublished
Cited by103 cases

This text of 751 A.2d 293 (Fritzeen v. Trudell Consulting Engineers, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fritzeen v. Trudell Consulting Engineers, Inc., 751 A.2d 293, 170 Vt. 632, 2000 Vt. LEXIS 45 (Vt. 2000).

Opinion

Plaintiffs Eric and Louise Eritzeen, et al., appeal a Chittenden Superior Court summary judgment dismissal of their negligence and breach of contract lawsuit against defendants Trudell Consulting Engineers, Inc., et al. The court concluded that Trudell’s engineering work was not a factor in the decision of the Water Resources Board to reverse the grant of a wastewater permit, and thus Trudell’s conduct could not be a proximate cause of the Eritzeens’ alleged damages. We believe that the court misconstrued the Board’s decision and that whether Trudell’s conduct was a proximate cause of the alleged harm is a genuine issue of material fact. Accordingly, we reverse.

I. Facts

The factual and procedural history of this case is long and complicated. In 1991, the Eritzeens acquired a thirty-four acre parcel of land in Colchester from Roger Villemaire with the intent to develop it into a multi-unit condominium project. Villemaire had secured a wastewater permit from the Agency of Natural Resources (ANR) for a mound septic system, designed by Trudell, for a nine unit project. However, this permit was conditioned upon obtaining an easement from a neighbor. The Eritzeens, after purchasing the parcel from Villemaire, were unable to acquire the easement. They hired Trudell to design a new on-site septic system, rather than a mound system, to obtain an ANR permit. According to the Eritzeens, Trudell assured them that its design was the only viable plan and actively discouraged consideration of any alternative septic sites. This site was near the property of neighbors, the DesLauriers. With the help of legal counsel, the Eritzeens obtained a permit. However, the DesLauriers opposed it and filed an out-of-time revocation petition with the Department of Environmental Conservation (DEC).

A two-day adversarial hearing was held before the DEC. The Eritzeens and the DesLauriers were represented by counsel. Defendant James Hart and DEC Assistant Regional Engineer Marsha Thompson testified at the hearing. In July 1993, the DEC Commissioner, referring often to Hart and Thompson’s testimony, denied the neighbors’ revocation petition. The Commissioner concluded that the DesLauriers did not produce sufficient evidence on any of their five appellate issues, and thus could not establish that the permit failed to comply with the Environmental Protection Rules (EPRs) or that the Eritzeens provided false or misleading information in their application to the DEC.

The DesLauriers then appealed to the Water Resources Board (Board). Again, both the Eritzeens and the DesLauriers were represented by counsel, though the Eritzeens’ attorney was not the same attorney who had represented them before the ANR and the DEC. In June 1994, the Board reversed the Commissioner’s decision. * The Eritzeens, through a third *633 attorney, subsequently filed motions to correct the Board’s decision and to supplement the record of appeal. Specifically, these motions argued that important evidence, at least some of which includes Trudell’s work, was not included in the record before the Board when it rendered its decision. In September 1994, the Board denied the Eritzeens’ motions.

The Eritzeens subsequently retained another engineering firm to design an alternative system with different septic sites on the parcel. This alternative plan was approved by the ANR without objection from the DesLauriers, and installed.

The Eritzeens then brought this lawsuit in superior court alleging negligence and breach of contract against Trudell, claiming as damages the costs of subsequent design and construction of a new waste-water system, as well as lost profits. After discovery by both sides, Trudell moved for summary judgment, arguing that (1) the Eritzeens’ predecessor attorneys were negligent in handling the proceedings before the Board and this negligence constituted an efficient intervening cause of the Eritzeens’ damages; (2) the Eritzeens’ predecessor attorneys’ alleged negligence was imputable to the Eritzeens and that such imputed negligence exceeded that of Trudell; and (3) the Eritzeens assumed the risk of a successful revocation action by the DesLauriers when they purchased the property and authorized a septic design different from the one previously done by Trudell for Villemaire.

The court granted Trudell’s summary judgment motion, concluding that the only reasonable conclusion, based upon the evidence, was that Trudell’s conduct was not the proximate cause of the Eritzeens’ damages. This appeal followed.

II. Discussion

We review a grant of summary judgment with the same standard as the trial court. See In re Margaret Susan P., 169 Vt. 252, 257, 733 A.2d 38, 43 (1999). Summary judgment is appropriate only where, taking the allegations of the nonmoving party as true, it is evident that there exist no genuine issues of material fact and the movant is entitled to judgment as a matter of law. See Baisley v. Missisquoi Cemetery Ass’n, 167 Vt. 473, 477, 708 A.2d 924, 926 (1998). “Summary judgment is not a substitute for a determination on the merits, so long as evidence has been presented which creates an issue of material fact, no matter what view the court may take of the relative weight of that evidence.” Vermont Envtl. Bd. v. Chickering, 155 Vt. 308, 319, 583 A.2d 607, 613-14 (1990). It is not the function of the trial court to find facts on a motion for summary judgment, even if the record appears to lean strongly in one direction. See Booska v. Hubbard Ins. Agency, Inc., 160 Vt. 305, 309, 627 A.2d 333, 335 (1993).

The salient material fact in this dispute is whether Trudell’s work was a cause of the Board’s decision to reverse the Commissioner’s decision. The Eritzeens’ theory of the case is that it was Trudell’s negligence in designing the wastewater system that caused the alleged harm. Trudell counters that in reversing the Commissioner’s decision the Board never passed judgment on Trudell’s work, and *634 the only possible conclusion as the cause-in-fact for the reversal was the Eritzeens’ failure to introduce adequate documentation before the ANR, the DEC, and the Board.

The court’s summary judgment decision was predicated on its proximate cause analysis which in turn was premised on its conclusion that there was no material dispute of fact as to the basis for the Board’s decision. In determining that the Eritzeens could not demonstrate proximate cause, the court found that “[The Eritzeens] are... in the position of suing [Trudell] on the ground that [Trudell’s] work resulted in revocation of the permit, when that work was omitted and absent from the decisional database which resulted in revocation.” Although the court's analysis is sound if one accepts defendant’s characterization of the “decisional database,” a careful reading of the Board’s rulings reveals that at least some of Trudell’s engineering work was relevant to the reversal of the Commissioner’s decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silva DRB App 23-12 - Decision on Motion
Vermont Superior Court, 2024
leblanc v. estate of snelgrove
Vermont Superior Court, 2024
Grimaldi NOV - Decision on Motions
Vermont Superior Court, 2021

Cite This Page — Counsel Stack

Bluebook (online)
751 A.2d 293, 170 Vt. 632, 2000 Vt. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fritzeen-v-trudell-consulting-engineers-inc-vt-2000.