SOTOMAYOR, Circuit Judge.

This is a case about fish and other aquatic organisms. Power plants and other industrial operations withdraw billions of gallons of water from the nation’s waterways each day to cool their facilities. The flow of water into these plants traps (or “impinges”) large aquatic organisms against grills or screens, which cover the intake structures, and draws (or “en-trains”) small aquatic organisms into the cooling mechanism; the resulting impingement and entrainment from these operations kill or injure billions of aquatic organisms every year. Petitioners here challenge a rule promulgated by the Environmental Protection Agency (“the EPA” or “the Agency”) pursuant to section 316(b) of the Clean Water Act (“CWA” or “the. Act”), 33 U.S.C. § 1326(b),1 that is intended to protect fish, shellfish, and other aquatic organisms from being harmed or killed by regulating “cooling water intake structures” at large, existing power-producing facilities.

For the reasons that follow, we grant in part and deny in part the petitions for review, concluding that certain aspects of the EPA’s rule are based on a reasonable interpretation of the Act and supported by substantial evidence in the administrative record, but remanding several aspects of the rule because they are inadequately explained or inconsistent with the statute, or because the EPA failed to give adequate notice of its rulemaking. We also dismiss for lack of jurisdiction one aspect of the petitions because there is no final agency action to review.

BACKGROUND

Our decision in Riverkeeper, Inc. v. EPA 358 F.3d 174 (2d. Cir.2004) (“River[90]*90keeper I”), which addressed challenges to the EPA’s rule governing cooling water intake structures at new — as opposed to existing — facilities discusses at length the procedural and factual background of the rulemaking pursuant to section 316(b). We presume familiarity with Riverkeeper I and provide here only a brief overview of the statute and the various stages of the rulemaking.

These consolidated petitions for review concern a final rule promulgated by the EPA regarding the water that large, existing power plants withdraw from rivers, lakes, and other waterways of the United States to cool their facilities. See 40 C.F.R. § 125.91(a). This cooling process requires power plants to extract billions of gallons of water per day from the nation’s waters, thereby impinging and entraining a huge number of aquatic organisms. Riverkeeper I, 358 F.3d at 181. Indeed, a single power plant can kill or injure billions of aquatic organisms in a single year. Id.

Cognizant of this problem, Congress in 1972 amended the CWA, 33 U.S.C. §§ 1251-1387, to regulate cooling water intake structures. See Federal Water Pollution Control Act Amendments of 1972, Pub.L. No. 92-500, 86 Stat. 816 (1972). We have described Congress’s regulation of such structures as “something of an afterthought,” Riverkeeper I, 358 F.3d at 186 n. 12, given that the directive appears in a section of the Act addressing the seemingly unrelated issue of thermal pollution, see CWA § 316(a), 33 U.S.C. § 1326(a). The Act, as amended, provides that “[a]ny standard established pursuant to section 1311 of this title [CWA section 301] or section 1316 of this title [CWA section 306] and applicable to a point source shall require that the location, design, construction, and capacity of cooling water intake structures reflect the best technology available for minimizing adverse environmental impact.” CWA § 316(b), 33 U.S.C. § 1326(b).

The provisions of the Act cross-referenced in section 316(b) direct the EPA to issue rules regulating the discharge of pollution from existing point sources, CWA § 301, 33 U.S.C. § 1311, and new point sources, CWA § 306, 33 U.S.C. § 1316.2 As we noted in Riverkeeper I, “[w]hen the EPA established new source performance discharge standard[s] ... it ought then to have regulated ... intake structures.... ” 358 F.3d at 185 (internal quotation marks omitted; emphasis in original). Put differently, section 316(b) required the EPA to promulgate regulations for cooling water intake structures at the same time that it established pollution discharge standards pursuant to sections 301 and 306. The EPA’s first attempt at regulation under section 316(b), however, was remanded by the Fourth Circuit in 1977 on procedural grounds, and years passed without the EPA issuing new rules. Id. at 181 (citing Appalachian Power Co. v. Train, 566 F.2d 451 (4th Cir.1977)). Environmental groups ultimately sued the EPA and won a consent decree, pursuant to which the Agency established a timetable to issue rules pursuant to Section 316(b) in three “phases.” Id. & n. 3. Phase I- — addressed in Riverkeeper I — governs new facilities; Phase II — addressed here — covers large, existing power plants; and Phase III will regulate existing power plants not governed by Phase II, as well as other industrial facilities. See Riverkeeper, Inc. v. Whitman, 2001 WL 1505497, at *1 n. 3 (S.D.N.Y. Nov.27, 2001).

[91]*91Our interpretation of section 316(b) is informed by the two provisions it cross-references, CWA sections 301 and 306. Section 301 sets forth a framework under which limitations on the discharge of pollutants from existing sources would become more stringent over time. CWA § 301(b), 33 U.S.C. § 1311(b); see Riverkeeper I, 358 F.3d at 185.

Section 301(b)(1)(A) required the EPA; beginning in 1977, to set effluent limitations for existing sources based on “the best practicable control technology currently available,” or “BPT.” CWA § 301(b)(1)(A), 33 U.S.C. § 1311(b)(1)(A). By 1989, existing source effluent limitations were to be based on the more stringent “best available technology economically achievable,” or “BAT.” CWA § 301(b)(2)(A), 33 U.S.C. § 1311(b)(2)(A). Additionally, section 306 requires the EPA to establish “standards of performance” for the control of the discharge of pollutants from new sources based on “the best available demonstrated control technology,” a standard that “reflects the greatest degree of effluent reduction.” CWA § 306(a)(1), 33 U.S.C. § 1316(a)(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Riverkeeper, Inc. v. United States Environmental Protection Agency, 475 F.3d 83 (2d Cir. 2007).

475 F.3d 83 (Riverkeeper, Inc. v. United States Environmental Protection Agency) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related